November 16, 2017
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2017 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***MLV 47-3D to 54-3S: Anomaly Remediation
***Completed
………………………………"
"***Sta. 114: ESD System Modification
"***Sta313: Hebron Storage Shut In Test
"***Sta. 313A: Ellisburg Storage Shut In Test
"***MLV.313-1&2 to MLV.307-1&2: Maintenance Pig: 300-1 11/14, 300-2 11/15
"***MLV 325-1 to MLV 329-1: Anomaly Digs
"***Meter 412180: Meter Outage
The following meters are available for nominations:
412180 IROQUOIS/TGP SHELTON INTERCONNECT F
"***MLV 506: Pipe Recoat
"***MLV 846-1 to MLV 847-1: Hydrotest
420328 - ATMOS-MS/TGP HARDY STA MS GRENADA
100 Line Outages
"MLV 1-1D to MLV 9-1S: Remediation
--1/15/18 through 3/10/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential in the path restrictions may be at risk.
"***MLV 1-1D to MLV 9-1S: Remediation
***Added
"*** MLV.9-1S to MLV.1-1D: EMAT
--1/16/18: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
412490 UES/TGP RENEWAL CENTER DEHY VICTORI
421083 DEVON GS/TGP PORT OF VICTORIA: DIP
410063 GCENGY/TGP UDP ROCHE DEHY REFUGIO
412877 EF MIDS/TGP BANQUETE PLANT: RIP 1T
"MLV.9-1S to MLV.1-1D: ILI/Cleaning: 11/28, 11/30, 12/5
--11/28/17 through 12/5/17: This activity will require operating at controlled flow rates. The meters listed below will be temporary shut-in while the pig passes. Potential in the path restrictions may be at risk.
"***Sta. 17: Station Reversal
--5/31/16 through 12/15/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 5/31/16 to 11/15/17.
"MLV 17-1 to 12-1: Pressure Weld Replacement
--9/15/17 through 11/25/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential in the path restrictions may be at risk.
400454 H-M RES/TGP UDP Egypt North West Dehy
420162 Cokinos/TGP Raun Farm #2
420479 Cokinos/TGP Cattle Farm (Garwood PD)
412023 HGI/TGP Englehardt (Garwood Plate) Colorado
420332 Cokinos/TGP Nitsch Farm
421054 Cokinos/TGP Swanson Farm
420467 Cokinos/TGP Holob Farm
420466 Cokinos/TGP Holt Farm
420442 Cokinos/TGP Rasmussen Farm (Abeulo)
412723 Patterson/TGP Hill
412523 UES/TGP Wildcat Rasmussen #1
420369 Cokinos/TGP Wiggington Farm
420183 Cokinos/TGP Krenek Farm
420158 Cokinos/TGP Raun Farm #1
420185 Cokinos/TGP Ottis Farm
"Sta. 32: Cooling Water and Oil System Modification
--10/2/17 through 12/15/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 63-3D to 64-3: Pig Trap Installation
--9/18/17 through 11/21/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV.39-1 to MLV.40-1: Wrinkle Bend Remediation
--11/28/17 through 12/15/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 78-2 to 79-2: Pipe Replacement
--10/26/17 through 11/19/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 78-4 to 79-4D: Pipe Replacement
--10/26/17 through 12/31/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 10/26/17 to 11/6/17.
"Sta.106: Tie Ins
--12/11/17 through 12/15/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience pressure and flow fluctuations. Potential in the path restrictions may be at risk.
"***MLV 118-1: Broad Run Expansion Tie-In
--12/1/17 through 12/12/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. The meters listed below will be shut-in for the entire duration of the project. Potential in the path restrictions may be at risk.
420639 – DOMINION/TGP INSTITUTE SALES KANAWH
420409 – CRANBERY/TGP INSTITUTE WV KANAWHA
***Date Change, Previously scheduled 11/27/17 to 12/7/17.
"***MLV 119-2: Broad Run Expansion Tie-In
--12/13/17 through 12/19/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential in the path restrictions may be at risk.
420749 – CRANBERY/TGP CRANBERRY SALES KANAWH
***Date Change, Previously scheduled 12/9/17 to 12/15/17.
200 Line Outages
"Sta. 204: ESD Test
--11/13/17 through 11/17/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience pressure and flow fluctuations. Potential in the path restrictions may be at risk.
"Sta. 204-3A: Unit Maintenance
--12/18/17 through 1/5/18: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 204-4A: Unit Maintenance
--11/27/17 through 12/15/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 204-5A: Unit Maintenance
--11/13/17 through 11/24/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 204-6A: Unit Maintenance
--11/13/17 through 11/17/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 204-8A: Unit Maintenance
--10/16/17 through 11/17/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Station 214: Header Piping Modifications
"Sta. 214-1A: Foundation Replacement
--3/27/17 through 12/31/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 214-10A: Unit Valve Replacement
--10/30/17 through 11/30/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 214-12A: Unit Maintenance
--12/1/17 through 12/31/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Colden Shut-In Test: Shut-In Test
--11/13/17 through 11/20/17: This project will require a storage outage.
"***MLV 260-2: ECDA
--9/4/17 through 12/1/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 9/4/17 to 10/23/17.
"MLV 268A-200: ECDA
--8/7/17 through 12/31/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
300 Line Outages
"Sta. 307-4A: Unit Maintenance
--5/15/17 through 11/17/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***Meter 420203: Meter Station Upgrade
--6/23/17 through 12/1/17: This project will require a meter station outage. The listed meter below will be shut-in for the entire duration of the project. Potential in the path restrictions may be at risk.
420203 - UGIPENN/TGP UNIONDALE PA SUSQUEHANNA
***Date Change, Previously scheduled 6/23/17 to 11/14/17.
"***MLV 336-1 to 356-1: Anomaly Remediation
--10/5/17 through 11/22/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure and flow fluctuations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 10/5/17 to 10/31/17.
500 Line Outages
"***Sta. 500C1: Controls Upgrade
--10/30/17 through 11/20/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 10/30/17 to 11/15/17.
"MLV 534 to MLV 538-2: Chemical Cleaning (11/2, 11/3, 11/4 & 11/5) & ILI Runs (11/16)
--11/2/17 through 11/16/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations. The meter listed below will be shut-in during the chemical cleaning runs. Potential in the path restrictions may be at risk.
420719 - WILLMUT/TGP CAMP SHLEBY FORREST
"MLV 538-2 to MLV 542-2: Chemical Cleaning (11/10, 11/11, 11/12 11/13 & 11/14) ILI Runs (11/28)
--11/10/17 through 11/28/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta. 550-1B: Unit Maintenance
--8/15/17 through 11/23/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 550-1A: Unit Maintenance
--8/15/17 through 11/17/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 555: MCC and Unit Valve Replacement
--11/6/17 through 12/1/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience pressure and flow fluctuations. Potential in the path restrictions may be at risk.
800 Line Outages
"Sta. 823: Cooling System Upgrade
--10/1/17 through 12/6/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers in the area may experience higher than normal pressure for the duration of the outage. Potential out of path restrictions may be at risk.
"Sta. 827: Station Reversal
--5/9/17 through 12/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 827-1 to 829-1A: Pipe Replacement
--12/5/17 through 12/14/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 834-1: 3300 - 535+17.5 to MLV 835-1: 3400 - 248+77: Spike Test
--2/5/18 through 3/17/18: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the entire duration of the project. Potential out of path restrictions may be at risk.
412619 – 00 MURPHEP/TGP MEDUSA
49554 – AM MIDLA/TGP NORTH PEOPLES RD FRANK
"MLV 834-1: 3300 - 535+17.5 to MLV 835-1: 3400 - 248+77: Spike Test
"Sta. 847: Station Reversal
--8/12/17 through 12/14/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 872-2 to MLV 873-2A: Anomaly Remediation
--11/27/17 through 12/3/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and will result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
If you have any questions, please contact your Scheduler.