PROJECT SCHEDULE CHANGED: MLV 702-1: Hydrotest
This notice is to inform customers of a schedule change for the MLV 702-1 Hydrotest as described below:
“***MLV 702-1: Hydrotest
--9/25/17 through 10/21/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project: Potential in the path restrictions may be at risk.
410031 - ETX GAS/TGP EAST TX PLANT DEHY PANO
411200 - VAR/TGP ENTEX PANOLA TRANSPORT PANO
411330 - TEXLA/TGP CHEMARD LAKE DEHY DE SOTO
411525 - PETROQUE/TGP BELLE BOWER DEHY PANOL
412033 - MARLIN/TGP CARTHAGE TRANSPORT PANOL
412081 - EPE/TGP UDP BETHANY LONGSTREET FIEL
412141 - ETP/TGP CARTHAGE GAS UNIT 13 PANOL
412607 - EPE/TGP UDP HOLLY FIELD DE SOTO
412610 - MAGNUMPL/TGP WEST MANSFIELD DE SOTO
412688 - ENBRIDGE/TGP PANOLA TRANSPORT 2 PAN
412725 - EAGLROCK/TGP UDP DE SOTO
412759 - UES/TGP UDP BURFORD GATHERING: RIP
412764 - ENT GATH/TGP UDP STATE LINE PROCESS
412775 - EOG/TGP TRENTON SALES: RIP 703H-1 5
412807 - ETC FS/TGP LOGANSPORT B: RIP 704H 1
420723 - ETP/TGP CARTHAGE GAS UNIT 13 PANOLA
412819 – LOUISMID/TGP CONVERSE CENTRAL: RIP
412706 – ETC/TGP LOGANSPORT DE SOTO
412765 – EMP/TGP HARRIS 19.1: RIP 703G 101.1
412583 – GCENGY/TGP BENSON AND CONVERSE DE S
411755 – IND MKTG/TGP GROGAN FIELD DE SOTO
***Date Change, Previously scheduled 9/25/17 to 10/20/17.
………………………………"
If you have any questions, please contact your Scheduler.