PROJECT SCOPE CHANGE: Sabine to MLV 823-1: ILI/Cleaning: 9/26, 9/27 & 9/29
"***Sabine to MLV 823-1: ILI/Cleaning: 9/26, 9/27 & 9/29
--9/26/17 through 9/29/17: This activity will require operating at controlled flow rates. Potential out of path restrictions may be at risk.
The meter listed below will be shut-in for approximately 1 hour while the pig passes:
420581 – ENTRGYLA/TGP BECKWITH CREEK CALCASI
The meters listed below will be shut-in for the entire duration of the pig run:
412768 – GLDNPASS/TGP STARKS LNG: RIP 820 10
412737 – LBERTYGS/TGP UDP DE QUINCY GAS STOR
412013 – ENTRPRSE/TGP SABINE RIVER TRANS NE
494446 – CAM IPL/TGP BANKEN RD AT HWY 27 DE
411586 – TRNSCO/TGP STARKS LA TRANSPORT CALC
*** Meter Added.
………………………………"
If you have any questions, please contact your Scheduler.