TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  08/18/2017 11:17:46AM Notice End Date/Time:  09/17/2017 9:00:00am
Post Date/Time:  8/18/2017 11:17:46 AM Notice ID: 364396
Reqrd Rsp:  1 Rsp Date:  08/18/2017
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 8-18-17 ID1
Notice Text:
Effective Timely Cycle (9:00) for the gas day of February 9, 2014

Effective Intraday Cycle 1 (14:00) for the gas day of August 18, 2017 Tennessee restricted the following:

 

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO Daily Critical Day 1 for Zone 0 south of STA 25 and north of STA 409 for under-deliveries and over-takes for all balancing parties

OFO Daily Action Alert for Zone 1, Zone 2, and Zone 3 for under-deliveries and over-takes for all balancing parties

 

RESTRICTIONS

MLV 406 (Segment 409 BH) – through 100% of SOP ID1 increases due to nominations in excess of operational capacity; 6,701 Dths

 

STA 17 (Segment 109 BH) – through 100% of PIP ID1 increases due to scheduled maintenance; 876 Dths

 

Dominion Broad Run Cornwell Delivery Meter (Pin 420044) – through 100% of SIPss ID1 receipt increases due to emergent repair issue; 157 Dths

 

STA 860 (Segment 548 BH) – through 100% of PIP ID1 increases due to the emergent repair at STA 546/STA 550; 1,872 Dths

 

Heidelberg Delivery Meter (Pin 420291) – through approx 10% of SIPss ID1 increases due to nominations in excess of operational capacity; 307 Dths

 

STA 204 (Segment 204 BH) – through approx 84% of PIP ID1 increases due to scheduled maintenance; 12,448 Dths

 

STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through approx 84% of SOP ID1 increases due to scheduled maintenance and nominations in excess of operational capacity; 151,528 Dths

 

STA 245 (Segment 245 FH) – through approx 94% of SOP ID1 increases due to nominations in excess of operational capacity; 384,004 Dths

STA 307 (Segment 307 BH) – through 100% of SOP ID1 increases due to scheduled maintenance; 117,439 Dths

 

STA 315 (Segment 315 BH) – through 100% of SOP ID1 increases due to scheduled maintenance and nominations in excess of operational capacity; 398,564 Dths

 

STA 321 (Segment 321 FH) - through approx 98% of SOP ID1 increases due to emergent repair issue at STA 325 and nominations in excess of operational capacity; 331,125 Dths

 

STA 325 (Segment 324 FH) – through approx 15% of SIPss ID1 increases due to emergent repair issue at STA 325; 13,171 Dths

 

Rivervale Delivery Meter (Pin 420101) – through 100% of SOP ID1 increases due to nominations in excess of operational capacity; 125,050 Dths

 

MLV 355 (Segment 355 BH) – through 100% of SOP ID1 increases due to operational concerns; 2,221 Dths

 

LINEPACK RESTRICTIONS

Downstream of STA 237 – through 100% of payback from TGP; 5,000 Dths

 

STORAGE RESTRICTIONS

No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA)

Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR

 CONFIRMATION REDUCTIONS.

 

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND

ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED

SERVICE OUTAGES.

 

If you have any questions, please contact your Scheduler.

...