TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  08/17/2017 7:14:11PM Notice End Date/Time:  09/16/2017 9:00:00am
Post Date/Time:  8/17/2017 7:14:11 PM Notice ID: 364390
Reqrd Rsp:  1 Rsp Date:  08/17/2017
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  TGP Outage Impact Report
Notice Text:
20170817 - Market Impact Report.xlsx

 

 

TGP - Outage Impact Report

Seven Day Forecast (updated 08/17/17)

-Primary restrictions  may be necessary

-Major impact restrictions  may be necessary

-Minor impact restrictions  may be necessardepending on flow conditions

-Little to no impact, though minor outages may cause incrementareductions

 

Station # / Lateral (FH)=forward haul (BH)=backward haul

 

Est Nominal Design Capacity (Thousand Dth)

Saturday

(8/19)

Sunday

(8/20)

Monday

(8/21)

Tuesday

(8/22)

W Wednesday

(8/23)

Thursday

(8/24)

Friday

(8/25)

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Station 1 (segment 409

BH)

 

262

 

238

 

238

 

238

 

238

 

238

 

238

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

688

 

688

 

688

 

688

 

688

 

688

 

688

 

Station 17 South of Zone 100L SP (segment 109

BH)

 

734

 

650 (84)

 

650 (84)

 

650 (84)

 

650 (84)

 

650 (84)

 

650 (84)

 

650 (84)

MLV 17-1 to 20-1: Spike Test  (M) (7/31/2017 - 9/30/2017)

 

Sta. 47 (segment 143

BH)

 

570

 

507

 

507

 

507

 

507

 

507

 

507

 

507

 

 

MLV 823 (segment 823

BH)

 

83

 

83

 

83

 

83

 

83

 

83

 

83

 

83

 

 

MLV 843 (segment 834

BH)

 

223

 

223

 

223

 

0 (223)

 

0 (223)

 

0 (223)

 

0 (223)

 

0 (223)

MLV 836 to MLV 837: Delhi Lateral Tie-I (8/21/2017 - 8/31/2017) Sta. 836A: Station Tie-I (8/21/2017 - 8/31/2017)

 

Station 546 (segment 542

BH)

 

1,498

 

1,216

 

1,216

 

1,216

 

1,216

 

1,216

 

1,216

 

1,216

 

 

Station 860 (segment 548

BH)

 

1,527

 

1000 (245)

 

1000 (245)

 

1000 (245)

 

1000 (245)

 

1000 (245)

 

1000 (245)

 

1000 (245)

EMERGENT REPAIRS AT STA 546 AND STA 55 (8/15/2017 - 8/31/2017)

Station 110 (segment 187

BH) (south thru Kentucky)

 

 

2,369

 

2220 (149)

 

2220 (149)

 

2220 (149)

 

2120 (249)

 

2220 (149)

 

2120 (249)

 

2220 (149)

MLV 96-2 to 87-2: ILI/Cleaning8/22, 8/24 & 8/2 (8/22/2017 - 8/29/2017) MLV 106-4D to 108-4: Spike Test   (7/20/2017 - 10/7/2017)

Sta. 871-3A: Power Side Overhau (8/14/2017 - 9/15/2017)

 

Station 114 (segment BH)

 

710

 

710

 

710

 

710

 

710

 

710

 

710

 

710

 

 

Station 204 (Segment 204

BH)

 

1,838

 

1805 (29)

 

1805 (29)

 

1805 (29)

 

1805 (29)

 

1805 (29)

 

1805 (29)

 

1805 (29)

Sta. 209-7A: Unit Maintenance    (8/7/2017 - 8/25/2017)

MLV 205-1 to 206-1: Anomaly Remediation    (8/14/2017 - 8/30/2017)

 

Station 237 (segment 237

FH)

 

1,020

 

1,004

 

1,004

 

1,004

 

1,004

 

840 (164)

 

1,004

 

1,004

Sta. 237: Filter Replacement    (8/23/2017 - 8/23/2017)

 

Station 245 (segment 245

FH)

 

1,029

 

1,013

 

1,013

 

1,013

 

1,013

 

1,013

 

1,013

 

1,013

 

 

Station 254 (segment 256

FH)

 

1,180

 

1,164

 

1,164

 

1,164

 

1,164

 

1,164

 

1,164

 

1,164

 

 

Station 261 (segment 260

FH)

 

1,091

 

1,080

 

1,080

 

955 (125)

 

1,080

 

1,080

 

1,080

 

1,080

MLV 258-1 & 2: Hot Ta (8/21/2017 - 8/24/2017)

 

Station 307 (segment 307

BH)

 

1,185

 

1,145

 

1,145

 

1,145

 

1,145

 

1,145

 

1,145

 

1,145

 

 

Station 315 (segment 315

BH)

 

1,781

 

1,781

 

1680 (101)

 

1680 (101)

 

1680 (101)

 

1680 (101)

 

1680 (101)

 

1,781

Sta. 317-1B & 1C: Unit Restage & Commissionin (8/20/2017 - 8/24/2017)

 

Station 321 (segment 321

FH)

 

1,657

 

1347 (310)

 

1347 (310)

 

1,657

 

1,657

 

1,657

 

1,657

 

1,657

EMERGENT REPAIR AT STA 32 (8/14/2017 - 8/20/2017)

 

Sta. 325 (segment 324

FH)

 

1,597

 

1287 (310)

 

1287 (310)

 

1350 (247)

 

1350 (247)

 

1350 (247)

 

1350 (247)

 

1350 (247)

EMERGENT REPAIR AT STA 32 (8/14/2017 - 8/20/2017)

MLV 321-2 to MLV 325-2: Anomaly Remediation    (8/21/2017 - 8/26/2017)

 

Sta. 229 (Segment 224

FH)

 

384

 

370 (14)

 

370 (14)

 

370 (14)

 

370 (14)

 

370 (14)

 

370 (14)

 

370 (14)

Sta. 229-6A: Unit Maintenance    (5/30/2017 - 9/30/2017)

MLV 229-2 to MLV 232-2: Anomaly Dig (8/24/2017 - 8/30/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

Outage Capacity Impact Report

August 2017 (updated 08/17/17)

-Primary restrictions may be necessary

-Major  impact  restrictions may be necessary

-Minor  impact  restrictions may be necessary depending on flow conditions

-Little  to no impact,  though  minor  outages may cause  incremental reductions

 

Station  # / Lateral

Est Nom inal Design  Capacity (Thousand Dth)

Week 1 (7/31 - 8/6)

Week 2 (8/7 - 8/13)

Week 3 (8/14 - 8/20)

Week 4 (8/21 - 8/27)

Week 5 (8/28 - 9/3)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409 (Donna Line) (segment 490

FH)

 

561

 

 

 

 

 

537

 

 

Station 1 (segment 409

BH)

 

262

 

 

 

 

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

 

 

 

 

650 (38)

MLV 17-1 to 12-1: Pressure Weld Replacement (M) (9/1/2017 - 10/31/2017)

Station 17

South of Zone

100L SP (segment 109

BH)

 

734

 

 

 

 

 

650 (84)

MLV 17-1 to 20-1: Spike Test  (M) (7/31/2017  - 9/30/2017)

 

Sta. 47 (segment 143

BH)

 

570

 

 

 

 

 

507

 

 

MLV 823 (segment 823

BH)

 

83

 

 

 

 

 

83

 

 

MLV 843 (segment 834

BH)

 

223

 

 

 

 

 

0 (223)

MLV 836 to MLV 837: Delhi Lateral Tie-I (8/21/2017  - 8/31/2017) Sta. 836A: Station Tie-I (8/21/2017  - 8/31/2017)

 

Station 546 (segment 542

BH)

 

1,498

 

 

 

 

 

1,216

 

 

Station 860 (segment 548

BH)

 

1,527

 

 

 

 

 

1000 (245)

EMERGENT REPAIRS  AT STA 546 AND STA 55 (8/15/2017  - 8/31/2017)

Station 110 (segment 187

BH) (south thru Kentucky)

 

2,369

 

 

 

 

 

2120 (249)

MLV 96-2 to 87-2: ILI/Cleaning: 8/22, 8/24 & 8/2 (8/22/2017  - 8/29/2017) MLV 106-4D to 108-4: Spike Tes (7/20/2017  - 10/7/2017)

Sta. 871-3A: Power Side Overhau (8/14/2017  - 9/15/2017)

 

Station 114 (segment BH)

 

710

 

 

 

 

 

710

 

 

Station 204 (Segment 204

BH)

 

1,838

 

 

 

 

 

1820 (18)

MLV 205-1 to 206-1: Anomaly Remediation  (8/14/2017  - 8/30/2017)

 

Station 237 (segment 237

FH)

 

1,020

 

 

 

 

 

1,004

 

 

Station 245 (segment 245

FH)

 

1,029

 

 

 

 

 

1,013

 

 

Station 254 (segment 256

FH)

 

1,180

 

 

 

 

 

1,164

 

 

Station 261 (segment 260

FH)

 

1,091

 

 

 

 

 

1,080

 

 

Station 307 (segment 307

BH)

 

1,185

 

 

 

 

 

1,145

 

 

Station 315 (segment 315

BH)

 

1,781

 

 

 

 

 

1,781

 

 

Sta. 325 (segment 324

FH)

 

1,597

 

 

 

 

 

1280 (317)

MLV 325-1 to MLV 329-1: Anomaly Dig (8/28/2017  - 11/13/2017)

 

MLV 355 (segment 355

FH)

 

198

 

 

 

 

 

0 (198)

MLV 355-1: Connecticut  Loop Tie-I (8/28/2017  - 8/31/2017)

 

Sta. 229 (segment 224

FH)

 

384

 

 

 

 

 

360 (24)

MLV 224-2 to Kinder Road: Anomaly Remediation  (8/28/2017  - 9/8/2017) Sta. 229-6A: Unit Maintenance   (5/30/2017  - 9/30/2017)

MLV 229-2 to MLV 232-2: Anomaly Dig (8/24/2017  - 8/30/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report.

The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.



 

Outage Capacity Impact Report

September 2017 (updated 08/17/17)

-Primary restrictions may be necessary

-Major  impact  restrictions may be necessary

-Minor  impact  restrictions may be necessary depending on flow conditions

-Little  to no impact,  though  minor  outages may cause  incremental reductions

 

Station  # / Lateral

Est Nom inal Design  Capacity (Thousand Dth)

Week 1 (9/4 - 9/10)

Week 2 (9/11 - 9/17)

Week 3 (9/18 - 9/24)

Week 4 (9/25 - 10/1)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409A (Alamo) (segment 492

FH)

 

241

 

241

 

241

 

150 (91)

 

150 (91)

Sta. 409A: Automation  Controls Upgrad (9/18/2017  - 10/13/2017)

Station 409 (Donna Line) (segment 490

FH)

 

561

 

537

 

537

 

537

 

537

 

 

Station 1 (segment 409

BH)

 

262

 

238

 

238

 

238

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

650 (38)

 

650 (38)

 

650 (38)

 

650 (38)

MLV 17-1 to 12-1: Pressure Weld Replacement (M) (9/1/2017 - 10/31/2017)

Station 17

South of Zone

100L SP (segment 109

BH)

 

734

 

650 (84)

 

650 (84)

 

650 (84)

 

650 (84)

MLV 17-1 to 20-1: Spike Test  (M) (7/31/2017  - 9/30/2017)

 

Sta. 47 (segment 143

BH)

 

570

 

507

 

507

 

507

 

507

 

 

MLV 823 (segment 823

BH)

 

83

 

83

 

83

 

83

 

83

 

 

MLV 847 (segment 847

BH)

 

230

 

230

 

0 (230)

 

0 (230)

 

0 (230)

MLV 846-1 to MLV 847-1: Hydrotest   (M) (9/15/2017  - 10/15/2017) Sta. 847: Hydrotest    (9/15/2017  - 10/15/2017)

 

Station 546 (segment 542

BH)

 

1,498

 

1,216

 

1,216

 

1,216

 

1,216

 

 

Station 860 (segment 548

BH)

 

1,527

 

1,245

 

1,245

 

1,245

 

1,245

 

Station 110 (segment 187

BH) (south thru Kentucky)

 

2,369

 

2220 (149)

 

2150 (219)

 

2150 (219)

 

2150 (219)

MLV 106-4D to 108-4: Spike Tes (7/20/2017  - 10/7/2017) Sta. 871-3A: Power Side Overhau (8/14/2017  - 9/15/2017) Sta. 875: Tie-In (9/11/2017  - 9/30/2017)

 

Station 114 (segment BH)

 

710

 

710

 

710

 

710

 

710

 

 

Station 204 (Segment 204

BH)

 

1,838

 

1,838

 

1,838

 

1,838

 

1,838

 

 

Station 237 (segment 237

FH)

 

1,020

 

1,004

 

1,004

 

1,004

 

1,004

 

 

Station 245 (segment 245

FH)

 

1,029

 

1,013

 

1,013

 

1,013

 

1,013

 

 

Station 254 (segment 256

FH)

 

1,180

 

1,164

 

1,164

 

1,164

 

1,164

 

 

Station 261 (segment 260

FH)

 

1,091

 

660 (420)

 

980 (100)

 

680 (400)

 

980 (100)

MLV 260-1 to 261-1A: Tie-I (9/5/2017 - 9/11/2017)

Sta. 261-1D, 1C & 5A: Borescope  Maintenance   (9/12/2017  - 9/15/2017) Sta. 261-4A: Unit Maintenance   (9/25/2017  - 9/28/2017)

Sta. 264-1C & 2C: Borescope  Maintenance   (9/19/2017  - 9/20/2017)

 

Station 307 (segment 307

BH)

 

1,185

 

1,145

 

1,145

 

1,145

 

1,145

 

 

Station 315 (segment 315

BH)

 

1,781

 

1,781

 

1,781

 

1,781

 

1,781

 

 

Sta. 325 (segment 324

FH)

 

1,597

 

1280 (317)

 

1280 (317)

 

1280 (317)

 

1280 (317)

Sta. 323-1A & 2A: Performance Test (Bypass Line 1 on 2A Outage (9/5/2017 - 9/8/2017) MLV 325-1 to MLV 329-1: Anomaly Dig (8/28/2017  - 11/13/2017)

 

Sta. 229 (segment 224

FH)

 

384

 

360 (24)

 

370 (14)

 

370 (14)

 

370 (14)

MLV 224-2 to Kinder Road: Anomaly Remediation  (8/28/2017  - 9/8/2017) Sta. 229-6A: Unit Maintenance   (5/30/2017  - 9/30/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.



 

Outage Capacity Impact Report

October 2017 (updated 08/17/17)

-Primary restrictions may be necessary

-Major  impact  restrictions may be necessary

-Minor  impact  restrictions may be necessary depending on flow conditions

-Little  to no impact,  though  minor  outages may cause  incremental reductions

 

Station  # / Lateral

Est Nom inal Design  Capacity (Thousand Dth)

Week 1 (10/2 - 10/8)

Week 2 (10/9 - 10/15)

Week 3 (10/16 - 10/22)

Week 4 (10/23 - 10/29)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409A (Alamo) (segment 492

FH)

 

241

 

150 (91)

 

150 (91)

 

241

 

241

Sta. 409A: Automation  Controls Upgrad (9/18/2017  - 10/13/2017)

Station 409 (Donna Line) (segment 490

FH)

 

561

 

537

 

537

 

537

 

537

 

 

Station 1 (segment 409

BH)

 

262

 

238

 

238

 

238

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

650 (38)

 

650 (38)

 

650 (38)

 

650 (38)

MLV 17-1 to 12-1: Pressure Weld Replacement (M) (9/1/2017 - 10/31/2017)

Station 17

South of Zone

100L SP (segment 109

BH)

 

734

 

734

 

734

 

734

 

734

 

 

Sta. 47 (segment 143

BH)

 

570

 

507

 

507

 

507

 

507

 

 

MLV 823 (segment 823

BH)

 

83

 

83

 

83

 

83

 

83

 

 

MLV 847 (segment 847

BH)

 

230

 

0 (230)

 

0 (230)

 

230

 

230

MLV 846-1 to MLV 847-1: Hydrotest   (M) (9/15/2017  - 10/15/2017) Sta. 847: Hydrotest    (9/15/2017  - 10/15/2017)

 

Station 546 (segment 542

BH)

 

1,498

 

1,216

 

1,216

 

1,216

 

1,216

 

 

Station 860 (segment 548

BH)

 

1,527

 

1,245

 

1,245

 

1,245

 

1,245

 

Station 110 (segment 187

BH) (south thru Kentucky)

 

2,369

 

2280 (89)

 

2,369

 

2,369

 

2,369

MLV 106-4D to 108-4: Spike Tes (7/20/2017  - 10/7/2017)

 

Station 114 (segment BH)

 

710

 

300 (410)

 

300 (410)

 

710

 

710

MLV 119-2: Broad Run Expansion Tie-I (4th Qtr. Exact Dates TBD) MLV 119-2: Pipe Replacement  (10/9/2017  - 10/15/2017)

 

Station 204 (Segment 204

BH)

 

1,838

 

1,838

 

1,838

 

1,838

 

1,838

 

 

Station 237 (segment 237

FH)

 

1,020

 

1,004

 

1,004

 

1,004

 

1,004

 

 

Station 245 (segment 245

FH)

 

1,029

 

1,013

 

1,013

 

1,013

 

1000 (13)

Sta. 245-1C: Borescope  Inspection    (10/23/2017  - 10/27/2017)

 

Station 254 (segment 256

FH)

 

1,180

 

1,164

 

1,164

 

1,164

 

1,164

 

 

Station 261 (segment 260

FH)

 

1,091

 

1,080

 

1,080

 

1,080

 

1,080

 

 

Station 307 (segment 307

BH)

 

1,185

 

1,145

 

1,145

 

1,145

 

1,145

 

 

Station 315 (segment 315

BH)

 

1,781

 

1680 (101)

 

1,781

 

1,781

 

1,781

Sta. 317: Electrical Tie-Ins Outag (10/2/2017  - 10/6/2017)

 

Sta. 325 (segment 324

FH)

 

1,597

 

1280 (317)

 

1280 (317)

 

1280 (317)

 

1280 (317)

MLV 325-1 to MLV 329-1: Anomaly Dig (8/28/2017  - 11/13/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


.