Subject:  TGP Outage Impact Report
Notice Text:
20170525 - Market Impact Report.xlsx

 

 

TGP - Outage Impact Report

Seven Day Forecast (updated 05/25/17)

-Major impact restrictions may be necessary

-Minor impact restrictions  may be necessary depending on flow conditions

-Little to no impact, though minor outages may cause incremental  reductions

 

Station # / Lateral (FH)=forward haul (BH)=backward haul

 

Est Nominal Design Capacity (Thousand Dth)

Saturday

(5/27)

Sunday

(5/28)

Monday

(5/29)

Tuesday

(5/30)

Wednesday

(5/31)

Thursday

(6/1)

Friday

(6/2)

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409 (Donna Line) (segment 490

FH)

 

561

 

537

 

537

 

537

 

537

 

537

 

537

 

537

 

 

Station 1 (segment 409

BH)

 

262

 

238

 

238

 

238

 

238

 

238

 

238

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

560 (128)

 

560 (128)

 

560 (128)

 

560 (128)

 

560 (128)

 

560 (128)

 

560 (128)

Sta. 17: Station Reversal   (5/31/2016 - 6/15/2017) MLV 17-3 to 13-3: Hydrotest  (M) (4/26/2017 - 6/15/2017)

Station 17 South of Zone 100L SP (segment 109

BH)

 

734

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

MLV 17-3 to 20-3: Spike Test  (M) (3/20/2017 - 6/7/2017)

 

Sta. 47 (segment 143

FH)

 

570

 

507

 

507

 

507

 

507

 

507

 

507

 

507

 

 

MLV 843 (segment 834

BH)

 

223

 

223

 

223

 

223

 

223

 

223

 

223

 

223

 

 

Station 546 (segment 542

BH)

 

1,498

 

1,216

 

1,216

 

1,216

 

1,216

 

1,216

 

1000 (245)

 

1,216

MLV 534-2 to 538-2: ILI/Cleaning:  5/23 & 6/1  (M) (5/23/2017 - 6/1/2017) MLV 538-2 to 542-2: ILI/Cleaning:  5/25 & 6/8  (M) (5/25/2017 - 6/8/2017)

 

Station 860 (segment 548

BH)

 

1,527

 

1,245

 

1,245

 

1,245

 

1,245

 

1,245

 

1,245

 

1,245

Sta. 546: Trap Modifications    (4/10/2017 - 6/10/2017)

 

Station 110 (segment 187

BH) (south thru Kentucky)

 

 

2,369

 

 

2220 (149)

 

 

2220 (149)

 

 

2220 (149)

 

 

2220 (149)

 

 

2220 (149)

 

 

2220 (149)

 

 

2220 (149)

MLV 96-3 to 106-3: Anomaly Remediation    (5/22/2017 - 6/30/2017) Sta. 106 to Sta.200: Anomaly Digs   (3/13/2017 - 5/31/2017)

MLV 107-5 to 109-5: Pipe Replacement    (3/13/2017 - 6/10/2017) Sta. 871-1A: Unit Overhaul   (5/15/2017 - 6/5/2017)

 

Station 114 (segment BH)

 

710

 

710

 

710

 

710

 

580 (130)

 

580 (130)

 

580 (130)

 

710

MLV 117-2 to MLV 114-2: ILI/Cleaning:  5/24 & 6/7  (M) (5/24/2017 - 6/7/2017) MLV 114-2 to 114-2A: Pipe Replacement    (5/30/2017 - 6/1/2017)

 

Station 204 (Segment 204

BH)

 

1,838

 

1690 (148)

 

1690 (148)

 

1690 (148)

 

1690 (148)

 

1690 (148)

 

1690 (148)

 

1690 (148)

MLV 207-4 to 208-4: Landslide Restoration    (5/26/2017 - 6/7/2017) Sta. 209-12A: Unit Maintenance    (5/22/2017 - 6/9/2017)

Sta. 209-3A: Unit Maintenance    (5/30/2017 - 6/2/2017)

Sta. 214-1A: Foundation Replacement    (3/27/2017 - 8/1/2017)

 

Station 237 (segment 237

FH)

 

1,020

 

1,004

 

1,004

 

1,004

 

1,004

 

1,004

 

1,004

 

1,004

 

 

Station 245 (segment 245

FH)

 

1,029

 

880 (133)

 

880 (133)

 

880 (133)

 

880 (133)

 

880 (133)

 

880 (133)

 

880 (133)

Sta. 249-1A: Unit Maintenance    (5/8/2017 - 6/4/2017)

 

Station 254 (segment 256

FH)

 

1,180

 

1,164

 

1,164

 

1,164

 

1,164

 

1,164

 

1,164

 

1,164

 

 

Station 261 (segment 260

FH)

 

1,091

 

1,080

 

1,080

 

1,080

 

1,080

 

1,080

 

1,080

 

1,080

 

 

Station 307 (segment 307

BH)

 

1,185

 

1130 (15)

 

1130 (15)

 

1,145

 

1,145

 

1,145

 

1,145

 

1,145

Sta. 307-6A: Unit Maintenance    (5/1/2017 - 5/28/2017)

 

Station 315 (segment 315

BH)

 

1,781

 

1,781

 

1,781

 

1,781

 

1700 (81)

 

1700 (81)

 

1,781

 

1,781

Sta. 315: Susquehanna  West Project Tie-In   (5/30/2017 - 5/31/2017)

 

Sta. 325 (segment 324

FH)

 

1,597

 

1,597

 

1,597

 

1,597

 

1580 (17)

 

1580 (17)

 

1580 (17)

 

1580 (17)

Sta. 325-3A & 4A: Unit Maintenance    (5/30/2017 - 6/2/2017)

Sta. 405

HC Line

(segment 299

FH)

 

821

 

805

 

805

 

805

 

805

 

700 (105)

 

805

 

805

Sta. 405A: Internal Inspection   (5/31/2017 - 5/31/2017)

 

Sta. 229 (segment 224

FH)

 

381

 

370 (11)

 

370 (11)

 

370 (11)

 

370 (11)

 

370 (11)

 

370 (11)

 

370 (11)

Sta. 229-6A: Unit Maintenance    (5/30/2017 - 9/30/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

Outage Capacity Impact Report

June 2017 (updated 05/25/17)

-Major impact  restrictions may be necessary

-Minor impact restrictions may be necessary depending on flow conditions

-Little to no impact,  though  minor outages  may cause incremental reductions

 

Station # / Lateral

Est Nominal Design Capacity (Thousand Dth)

Week 1 (6/5 - 6/11)

Week 2 (6/12 - 6/18)

Week 3 (6/19 - 6/25)

Week 4 (6/26 - 7/2)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Station 409 (Donna Line) (segment 490

FH)

 

561

 

537

 

537

 

537

 

537

 

 

Station 1 (segment 409

BH)

 

262

 

238

 

238

 

238

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

560 (128)

 

560 (128)

 

688

 

688

Sta. 17: Station Reversal  (5/31/2016 - 6/15/2017) MLV 17-3 to 13-3: Hydrotest (M) (4/26/2017 - 6/15/2017)

Station 17

South of Zone

100L SP (segment 109

BH)

 

734

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

MLV 17-2 to 20-2: Spike Test (M) (6/8/2017 - 8/8/2017) MLV 17-3 to 20-3: Spike Test (M) (3/20/2017 - 6/7/2017)

 

Sta. 47 (segment 143

FH)

 

570

 

507

 

507

 

507

 

507

 

 

MLV 823 (segment 823

BH)

 

223

 

223

 

223

 

223

 

223

 

 

Station 546 (segment 542

BH)

 

1,498

 

690 (526)

 

1,216

 

1,216

 

1,216

MLV 538-2 to 542-2: ILI/Cleaning: 5/25 & 6/8 (M) (5/25/2017 - 6/8/2017)

 

Station 860 (segment 548

BH)

 

1,527

 

1,245

 

1040 (205)

 

1040 (205)

 

1,245

Sta. 546: Trap Modifications  (4/10/2017 - 6/10/2017)

MLV 555-1 to 550-1: ILI Pigging: 6/13, 6/14, 6/20 & 6/22   (2/20/2017 - 6/22/2017)

Station 110 (segment 187

BH) (south thru Kentucky)

 

2,369

 

2220 (149)

 

2220 (149)

 

2220 (149)

 

2220 (149)

MLV 96-3 to 106-3: Anomaly Remediation  (5/22/2017 - 6/30/2017) MLV 107-5 to 109-5: Pipe Replacement  (3/13/2017 - 6/10/2017) Sta. 871-1A: Unit Overhaul  (5/15/2017 - 6/5/2017)

Sta. 871-2A: Compressor Overhaul  (6/6/2017 - 6/27/2017)

 

Station 114 (segment BH)

 

710

 

480 (230)

 

710

 

710

 

710

MLV 117-2 to MLV 114-2: ILI/Cleaning: 5/24 & 6/7 (M) (5/24/2017 - 6/7/2017)

 

Station 204 (Segment 204

BH)

 

1,838

 

1690 (148)

 

1750 (88)

 

1780 (58)

 

1780 (58)

MLV 207-4 to 208-4: Landslide Restoration  (5/26/2017 - 6/7/2017) MLV 209-1 to MLV 214-1: Anomaly Remediation  (6/12/2017 - 6/17/2017) Sta. 209-12A: Unit Maintenance  (5/22/2017 - 6/9/2017)

MLV 209-2 to MLV 214-2: Anomaly Remediation  (6/19/2017 - 7/1/2017) Sta. 214-1A: Foundation Replacement   (3/27/2017 - 8/1/2017)

 

Station 237 (segment 237

FH)

 

1,020

 

1,004

 

1,004

 

1,004

 

1,004

 

 

Station 245 (segment 245

FH)

 

1,029

 

890 (123)

 

800 (213)

 

760 (253)

 

890 (123)

MLV 237-1 to MLV 245-1: Anomaly Digs  (6/26/2017 - 8/5/2017) Sta. 241: ESD   (6/12/2017 - 6/16/2017)

Sta. 245: ESD   (6/19/2017 - 6/23/2017)

Sta. 249-1B: Unit Maintenance  (6/5/2017 - 6/16/2017) Sta. 249-2B: Unit Maintenance  (6/19/2017 - 6/30/2017)

 

Station 254 (segment 256

FH)

 

1,180

 

1,164

 

1,164

 

1,164

 

1,164

 

 

Station 261 (segment 260

FH)

 

1,091

 

1,080

 

1,080

 

1,080

 

1,080

 

 

Station 307 (segment 307

BH)

 

1,185

 

1020 (125)

 

1,145

 

1,145

 

1,145

Sta. 303-1A: Unit Maintenance  (6/5/2017 - 6/10/2017)

 

Station 315 (segment 315

BH)

 

1,781

 

1490 (291)

 

1680 (101)

 

1,781

 

1,781

Sta. 315: Susquehanna West Project - Station Tie-In  (6/5/2017 - 6/11/2017)

 

Sta. 325 (segment 324

FH)

 

1,597

 

1,597

 

1400 (197)

 

1400 (197)

 

1400 (197)

Sta. 323A: Station Tie-In   (6/16/2017 - 6/29/2017) Sta. 323: Hot Taps   (6/16/2017 - 6/29/2017)

 

Sta. 229 (segment 224

FH)

 

381

 

370 (11)

 

265 (115)

 

370 (11)

 

370 (11)

Sta. 229: ESD Test   (6/13/2017 - 6/13/2017)

Sta. 229-6A: Unit Maintenance  (5/30/2017 - 9/30/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.  Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.



 

Outage Capacity Impact Report

July 2017 (updated 05/25/17)

-Major impact  restrictions may be necessary

-Minor impact restrictions may be necessary depending on flow conditions

-Little to no impact,  though  minor outages  may cause incremental reductions

 

Station # / Lateral

Est Nominal Design Capacity (Thousand Dth)

Week 1 (7/3 - 7/9)

Week 2 (7/10 - 7/16)

Week 3 (7/17 - 7/23)

Week 4 (7/24 - 7/30)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

 

Station 409 (Donna Line) (segment 490

FH)

 

561

 

537

 

537

 

537

 

537

 

 

Station 1 (segment 409

BH)

 

262

 

238

 

238

 

238

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

688

 

688

 

688

 

688

 

Station 17

South of Zone

100L SP (segment 109

BH)

 

734

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

MLV 17-2 to 20-2: Spike Test (M) (6/8/2017 - 8/8/2017)

 

Sta. 47 (segment 143

FH)

 

570

 

507

 

507

 

507

 

507

 

 

MLV 823 (segment 823

BH)

 

223

 

0 (223)

 

0 (223)

 

0 (223)

 

0 (223)

Sta. 823: Station Reversal  (7/5/2017 - 7/21/2017)

MLV 826 to MLV 827: Hydrotest (M) (7/28/2017 - 8/14/2017)

 

Station 546 (segment 542

BH)

 

1,498

 

1,216

 

1,216

 

1,216

 

1,216

 

 

Station 860 (segment 548

BH)

 

1,527

 

1,245

 

1,245

 

1,245

 

1,245

 

Station 110 (segment 187

BH) (south thru Kentucky)

 

2,369

 

2220 (149)

 

2220 (149)

 

2220 (149)

 

2220 (149)

MLV 106-4D to 108-4: Spike Test  (7/17/2017 - 10/7/2017)

MLV 864-1 to 865-1: Anomaly Remediation  (7/24/2017 - 7/29/2017) Sta. 871-3A: Power Side Overhaul  (7/5/2017 - 8/16/2017)

 

Station 114 (segment BH)

 

710

 

710

 

710

 

710

 

710

 

 

Station 204 (Segment 204

BH)

 

1,838

 

1440 (398)

 

1440 (398)

 

1800 (38)

 

1800 (38)

MLV 200-4B to MLV 204-4: Anomaly Remediation  (7/6/2017 - 7/11/2017) MLV 204-2 to MLV 209-2: Anomaly Remediation  (7/13/2017 - 8/5/2017) Sta. 214-1A: Foundation Replacement   (3/27/2017 - 8/1/2017)

 

Station 237 (segment 237

FH)

 

1,020

 

1,004

 

1,004

 

1,004

 

1,004

 

 

Station 245 (segment 245

FH)

 

1,029

 

940 (73)

 

940 (73)

 

940 (73)

 

940 (73)

MLV 237-1 to MLV 245-1: Anomaly Digs  (6/26/2017 - 8/5/2017)

 

Station 254 (segment 256

FH)

 

1,180

 

1,164

 

1,164

 

960 (204)

 

780 (384)

MLV 251-2 & 251-3: Tie-In  (7/24/2017 - 7/29/2017) MLV 251-2 to 252-2: Hydrotest  (7/24/2017 - 8/1/2017) MLV 257-3: Tie-In   (7/17/2017 - 9/2/2017)

 

Station 261 (segment 260

FH)

 

1,091

 

1,080

 

610 (470)

 

1,080

 

1,080

Sta. 264: ESD Test   (7/11/2017 - 7/11/2017)

 

Station 307 (segment 307

BH)

 

1,185

 

1,145

 

1,145

 

1,145

 

1,145

 

 

Station 315 (segment 315

BH)

 

1,781

 

1490 (291)

 

1490 (291)

 

1680 (101)

 

1,781

Sta. 315: Susquehanna West Project  (7/3/2017 - 7/16/2017) Sta. 317: Electrical Tie-Ins  (7/172017 - 7/21/2017)

 

Sta. 325 (segment 324

FH)

 

1,597

 

1,597

 

1,597

 

1,597

 

1,597

 

 

Sta. 229 (segment 224

FH)

 

381

 

370 (11)

 

370 (11)

 

0 (381)

 

370 (11)

Sta. 229-6A: Unit Maintenance  (5/30/2017 - 9/30/2017)

MLV 229-2 to MLV 232-2: Anomaly Digs  (7/17/2017 - 7/22/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.  Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.



 

Outage Capacity Impact Report

August 2017 (updated 05/25/17)

-Major  impact  restrictions may be necessary

-Minor  impact  restrictions may be necessary depending on flow conditions

-Little to no impact,  though  minor  outages may cause  incremental reductions

 

Station  # / Lateral

Est Nominal Design  Capacity (Thousand Dth)

Week 1 (7/31 - 8/6)

Week 2 (8/7 - 8/13)

Week 3 (8/14 - 8/20)

Week 4 (8/21 - 8/27)

Week 5 (8/28 - 9/3)

 

Primary Outage(s)

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409 (Donna Line) (segment 490

FH)

 

561

 

537

 

537

 

537

 

537

 

537

 

 

Station 1 (segment 409

BH)

 

262

 

238

 

238

 

238

 

238

 

238

 

 

Station 9 (segment 101

BH)

 

688

 

688

 

688

 

688

 

688

 

688

 

Station 17

South of Zone

100L SP (segment 109

BH)

 

734

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

 

550 (184)

MLV 17-1 to 20-1: Spike Test  (M) (8/8/2017 - 10/8/2017) MLV 17-2 to 20-2: Spike Test  (M) (6/8/2017 - 8/8/2017)

 

Sta. 47 (segment 143

FH)

 

570

 

507

 

507

 

507

 

507

 

507

 

 

MLV 823 (segment 823

BH)

 

223

 

0 (223)

 

0 (223)

 

223

 

223

 

223

MLV 826 to MLV 827: Hydrotest   (M) (7/28/2017  - 8/14/2017)

 

MLV 843 (segment 834

BH)

 

223

 

0 (223)

 

0 (223)

 

0 (223)

 

223

 

223

MLV 836 to MLV 837: Delhi Lateral Tie-In   (8/7/2017 - 8/17/2017) Sta. 836A: Station Tie-In   (8/7/2017 - 8/17/2017)

 

Station 546 (segment 542

BH)

 

1,498

 

1,216

 

1,216

 

1,216

 

1,216

 

1,216

 

 

Station 860 (segment 548

BH)

 

1,527

 

1,245

 

1,245

 

1,245

 

1,245

 

1,245

 

Station 110 (segment 187

BH) (south thru Kentucky)

 

2,369

 

2220 (149)

 

2220 (149)

 

2220 (149)

 

2280 (89)

 

2280 (89)

Sta. 87-2E: Unit Maintenance   (7/31/2017  - 8/25/2017) MLV 106-4D to 108-4: Spike Test   (7/17/2017  - 10/7/2017) Sta. 871-3A: Power Side Overhaul    (7/5/2017 - 8/16/2017)

 

Station 114 (segment BH)

 

710

 

710

 

710

 

710

 

710

 

300 (410)

MLV 119-2: Pipe Replacement   (9/1/2017 - 9/14/2017)

 

Station 204 (Segment  204

BH)

 

1,838

 

1800 (38)

 

1570 (268)

 

1570 (268)

 

1,838

 

1,838

MLV 204-2 to MLV 209-2: Anomaly Remediation   (7/13/2017  - 8/5/2017) MLV 204-4 to MLV 208-4: Anomaly Remediation   (8/7/2017 - 8/19/2017) Sta. 214-1A: Foundation  Replacement   (3/27/2017  - 8/1/2017)

 

Station 237 (segment 237

FH)

 

1,020

 

1,004

 

1,004

 

1,004

 

1,004

 

1,004

 

 

Station 245 (segment 245

FH)

 

1,029

 

940 (73)

 

1,013

 

1,013

 

1,013

 

1,013

MLV 237-1 to MLV 245-1: Anomaly Digs   (6/26/2017  - 8/5/2017)

 

Station 254 (segment 256

FH)

 

1,180

 

780 (384)

 

960 (204)

 

960 (204)

 

960 (204)

 

960 (204)

MLV 251-2 to 252-2: Hydrotest    (7/24/2017  - 8/1/2017) MLV 251-1 & 251-3: Tie-In   (7/31/2017  - 8/22/2017) MLV 257-3: Tie-In   (7/17/2017  - 9/2/2017)

 

Station 261 (segment 260

FH)

 

1,091

 

1,080

 

660 (420)

 

660 (420)

 

660 (420)

 

660 (420)

MLV 260-1 to 261-1A: Tie-In   (8/7/2017 - 8/29/2017)

 

Station 307 (segment 307

BH)

 

1,185

 

1,145

 

1,145

 

1,145

 

1,145

 

1,145

 

 

Station 315 (segment 315

BH)

 

1,781

 

1680 (101)

 

1680 (101)

 

1,781

 

1,781

 

1,781

Sta. 317: Tie-In   (7/31/2017  - 8/9/2017)

 

Sta. 325 (segment 324

FH)

 

1,597

 

1150 (447)

 

1150 (447)

 

1,597

 

1,597

 

1,597

MLV 321-2 to MLV 325-2: Anomaly Remediation   (8/1/2017 - 8/11/2017)

 

Sta. 229 (segment 224

FH)

 

381

 

370 (11)

 

365 (16)

 

365 (16)

 

370 (11)

 

370 (11)

Sta. 229-6A: Unit Maintenance   (6/5/2017 - 9/30/2017)

MLV 224-2 to Kinder Road: Anomaly Remediation   (8/14/2017  - 8/24/2017)

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this re

The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

...