May 25, 2017
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2017 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***MLV 20-1 to 20-1A: Pipe Replacement
***Completed
………………………………"
"***Sta. 106: ESD Test and New ESD Control Line Installation
"***Sta. 204-2A: Unit Maintenance
"***Sta. 209-8A: Unit Maintenance
"***Sta. 214-10A: Unit Maintenance
"***Sta. 230C: Station Maintenance
"***Sta. 241-1B: Unit Maintenance
"***MLV 270C-300: Anomaly Remediation
"***MLV 270C-301: Anomaly Remediation
"***Sta. 315-1B: Unit Maintenance
"***Meter 420245: Flow Control Valve Replacement
The following meters are available for nominations:
420245 – COL GAS/TGP MILFORD PA BIG PIKE
"***MLV 507K-104: Maintenance Pig
The following meter will be shut-in for the entire duration of the run.
412884 – KINETICA/TGP GRAND CHENIER PLANT I
The following meters might experience higher than average pressure for the duration of the run:
410671 – TARGA/TGP UDP LOWRY PLANY DEHY CAME
900553 – TGP/NGPL CHALKLEY CAMERON
412680 – TRUNKLINE/TGP LACASSINE JEFFERSON DA
412002 – ANR/TGP CHALKLEY TRANSPORT JEFFERON
"***Sta. 860: ESD Test
100 Line Outages
"Sta. 17: Station Reversal
--5/31/16 through 6/15/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential out of path restrictions may be at risk.
"MLV 17-1 to 20-1: Spike Test
--8/8/17 through 10/8/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
420167 - COKINOS/TGP WOODS FARM TX FORT BEND
"MLV 17-2 to 20-2: Spike Test
--6/8/17 through 8/8/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
411788 - DCP GLP/TGP KATY TRANSPORT WALLER
412722 - JOY RES/TGP UDP MERI JOSEY HARRIS
"MLV 17-3 to 20-3: Spike Test
--3/20/17 through 6/7/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
411159 - ENTRPRSE/TGP KATY DEHY TRANS WALLER
412647 - F-W OIL/TGP KULHANEK AUSTIN
421085 - CEGS/TGP PEDERSON ROAD WALLER
"MLV 17-3 to 13-3: Hydrotest
--4/26/17 through 6/15/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
421055 - TRES PAL/TGP TRES PALACIOS STORAGE
420190 – COKINOS/TGP SULAK FARM TX WHARTON
411938 – LASERGTH/TGP UDP NORTH LOUISE DHY
411911 – ETP/TGP WHARTON COUNTY TRANSPORT EX
412099 - LASERGTH/TGP UDP JONES CREEK OTELL
"Bear Creek: Shut-In Test
--10/17/17 through 10/23/17: This project will require a storage outage.
"MLV 40-1D to 47-1S: ILI/Cleaning: 5/16, 5/17, 5/18 & 5/22
--5/16/17 through 5/22/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 40-2D to 47-2S: ILI Cleaning: 6/14, 6/20 & 6/22
--6/14/17 through 6/22/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 41-2A to 42-2: Bi-Directional Trap Installation
--8/7/17 through 9/22/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 47: Hydrotest
--9/18/17 through 10/13/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 47-1 to 49-1: Spike Test
--5/23/17 through 7/24/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 47-1 to 54-1: ILI/Cleaning: 5/3 - 8/7, 8/9, 8/17 & 8/17
--8/7/17 through 8/17/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 47-2 to 48-2: Spike Test
--7/3/17 through 9/15/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
47872 - ATMOS/TGP CHAUVIN OUACHITA
"MLV 55-1 to 63-1: Anomaly Remediation
--3/3/17 through 5/19/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 57-3 to 58-3: Pipe Remediation
--11/18/16 through 6/1/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 67-2: Hydrotest
--9/4/17 through 10/13/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 70-4, 2, 1 and South Header: Hydrotest
--7/7/17 through 11/3/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 71-4D to 73-4: Anomaly Remediation
--5/1/17 through 8/10/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 96-3 to 106-3: Anomaly Remediation
--5/22/17 through 6/30/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Added
"Sta. 106 to Sta.200: Anomaly Digs
--3/13/17 through 5/31/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 106-4D to 108-4: Spike Test
--7/17/17 through 10/7/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 107-5 to 109-5: Pipe Replacement
--3/13/17 through 6/10/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 117-2 to MLV 114-2: ILI/Cleaning: 5/24 & 6/7
--5/24/17 through 6/7/17: This activity will require operating at controlled flow rates. The meters listed below may experience pressure and flow fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
420627 - MTNEER/TGP CABELL TRANSPORT CABELL
"***MLV 114-2 to 114-2A: Pipe Replacement
--5/30/17 through 6/1/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLV 118-1: Broad Run Expansion Tie-In
--11/27/17 through 12/10/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLV 119-2: Broad Run Expansion Tie-In
--9/1/17 through 9/14/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***MLV 119-2: Pipe Replacement
--9/1/17 through 9/14/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled Sep./Oct. – Exact Dates TBD.
200 Line Outages
"***MLV 200-4B to MLV 204-4: Anomaly Remediation
--7/6/17 through 7/11/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential in the path restrictions may be at risk.
***Date Change, Previously scheduled 7/3/17 to 7/11/17.
"MLV 204-2 to MLV 209-2: Anomaly Remediation
--7/13/17 through 8/5/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 204-4 to MLV 208-4: Anomaly Remediation
--8/7/17 through 8/19/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 207-4 to 208-4: Landslide Restoration
--5/26/17 through 6/7/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 209-1 to MLV 214-1: Anomaly Remediation
--6/12/17 through 6/17/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 209-2 to MLV 214-2: Anomaly Remediation
--6/19/17 through 7/1/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta. 214-1A: Foundation Replacement
--3/27/17 through 8/1/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta. 219-1 to 214-1: Efficiency Pig
--5/31/17: This activity will require operating at controlled flow rates. Customers may experience pressure and flow fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"MLV 224-2 to Kinder Road: Anomaly Remediation
--8/14/17 through 8/24/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"***Sta. 229: ESD Test
--6/13/17 through 6/13/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 237-1: SCCDA
--7/10/17 through 7/15/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 229-2 to MLV 232-2: Anomaly Digs
--7/17/17 through 7/22/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta. 230C: Station Maintenance
--6/6/17 through 6/8/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 231-2: Pipe Replacement
--7/1/17 through 9/30/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 237-1 to MLV 245-1: Anomaly Digs
--6/26/17 through 8/5/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta. 237-3A: Unit Maintenance
--6/19/17 through 6/22/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
--7/24/17 through 7/28/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 245: ESD
--6/19/17 through 6/23/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 249-1A: Unit Maintenance
--5/8/17 through 6/4/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 249-1B: Unit Maintenance
--6/5/17 through 6/16/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 249-2B: Unit Maintenance
--6/19/17 through 6/30/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 251-2 & 251-3: Tie-In
--7/24/17 through 7/29/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 251-2 to 252-2: Hydrotest
--7/24/17 through 8/1/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 251-1 & 251-3: Tie-In
--7/31/17 through 8/22/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 257-3: Tie-In
--7/17/17 through 9/2/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 260-1 to 261-1A: Tie-In
--8/7/17 through 8/29/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 260-2: ECDA
--6/26/17 through 7/8/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 261B-100: Hydrotest
--6/19/17 through 6/23/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
400484 - BAY ST/TGP AGAWAM MASS HAMPDEN
"MLV 263A-100: ECDA
"Sta. 264-1C & 2C: Unit Maintenance
--5/22/17 through 5/26/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta. 264: ESD Test
--7/11/17 through 7/11/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 265C-100: Anomaly Remediation
--8/7/17 through 8/11/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 265A-100: Anomaly Remediation
--8/14/17 through 8/25/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta. 266A: Controls Replacement
--9/26/17 through 10/20/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. The listed meter below might experience pressure and flow fluctuations. Potential out of path restrictions may be at risk.
420285 – AGT/TGP MENDON MASS TIE OVER WORCHE
"MLV 268A-200: ECDA
--6/19/17 through 6/24/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 270A-100: Anomaly Remediation
--5/22/17 through 6/23/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 270C-103: ILI/Cleaning
--8/4/17 through 8/9/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 270C-1100 to 270C-1101: ILI/Cleaning
--8/7/17 through 8/16/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
300 Line Outages
"Sta. 303-1A: Unit Maintenance
--6/5/17 through 6/10/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 307-2 to MLV 219-3: ILI/Cleaning: 5/23 & 5/25
--5/23/17 through 5/25/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta. 307-2A: Unit Maintenance
--7/26/17 through 8/2/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 307-4A: Unit Maintenance
--5/15/17 through 6/4/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 307-6A: Unit Maintenance
--5/1/17 through 5/28/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 310-1A: Unit Maintenance
--5/24/17 through 5/26/17: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"***Sta. 315: Susquehanna West Project Tie-In
--5/30/17 through 5/31/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"Sta. 315: Susquehanna West Project - Station Tie-In
--6/5/17 through 6/11/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential in the path restrictions may be at risk.
"Sta. 315: Susquehanna West Project
--7/3/17 through 7/16/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential in the path restrictions may be at risk.
"***Sta. 317: Electrical Tie-Ins
--7/17/17 through 7/21/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 6/11/17 to 6/15/17.
"***Sta. 317: Tie-In
--7/31/17 through 8/9/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 7/17/17 to 7/27/17.
"***Sta. 317: Electrical Tie-Ins Outage
--10/2/17 through 10/6/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"Sta. 319: Compressor Replacement
--3/6/17 through 6/23/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Meter 420203: Meter Station Upgrade
--6/1/17 through 9/1/17: This project will require a meter station outage. The listed meter below will be shut-in for the entire duration of the project.
420203 - UGIPENN/TGP UNIONDALE PA SUSQUEHANNA
"MLV 321-2 to MLV 325-2: Anomaly Remediation
--8/1/17 through 8/11/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta. 323A: Station Tie-In
--6/16/17 through 6/29/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 325-1 to MLV 329-1: Anomaly Digs
--8/28/17 through 11/11/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential in the path restrictions may be at risk.
"Sta. 325-3A & 4A: Unit Maintenance
--5/30/17 through 6/2/17: This project will require a unit outages, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 325-4A: Unit Maintenance
--5/26/17 through 5/26/17: This project will require a unit outages, which could limit throughput through the station and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***MLV 329-1 to 336-1: Anomaly Digs
--6/5/17 through 6/17/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 5/30/17 to 6/7/17.
"MLV 329B-100: ECDA
--7/24/17 through 7/29/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 331-2: ILI Run
--7/31/17 through 8/12/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 332-1R2-CR: ECDA
--6/7/17 through 6/10/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 336-1 to 356-1: ILI Cleaning: 5/2, 5/4, 5/9 & 5/31
--5/2/17 through 5/31/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The capacity for the listed meters below will be restricted for the duration of the runs. Potential out of path restrictions may be at risk.
420453 - CONN NG/TGP NORTH BLOOMFIELD CT HAR
420205 – CONN NG/TGP BLOOMFIELD CT HARTFORD
"MLV 354-1: Tie-In
--7/24/17 through 7/30/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
400 Line Outages
"Sta. 409A: Automation Controls Upgrade
--(Sep./Oct. – Exact Dates TBD):This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
"MLV 405-2 to 408-2: Spike Test
--(Jan. 2018/Feb. 2018 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
500 Line Outages
"***MLV 507-1D to 516-1: ILI/Cleaning: 6/20 & 6/22
--6/20/17 through 6/22/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
The listed meters below will be shut-in for the entire duration of the run.
420825 - JEFFSTOR/TGP JEFFERSON ISLAND IBERI
412398 - JEFFSTOR/TGP JEFFERSON ISLAND IBERI
410907 – TRUNKLINE/TGP CENTERVILLE DEHY TRANS
421056 – CYPRSSPL/TGP INDIAN BAYOU: DIP 510B
420915 – CEGs/TGP PORT IBERIA SALES IBERIA
420825 – JEFFSTOR/TGP JEFFERSON ISLAND IBERI
412398 – JEFFSTOR/TGP JEFFERSON ISLAND IBER
The listed meters below will experience flow restrictions for the duration of the run.
412684 – ANR/TGP SHAYDYSIDE ST MARY
4012594 – NAUTILUS/TGP GARDEN CITY ST MARY
450105 - AMMID SC/TGP QUIVIRA ST MARY
***Meters Added
"MLV 507-1D to 516-1: Anomaly Remediation
--7/1/17 through 7/31/17: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 534: Drip Removal
--8/8/17 through 9/1/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in during the scheduled dates listed below. Potential out of path restrictions may be at risk.
8/22/2017 - 9/1/2017
420719 - WILLMUT/TGP CAMP SHLEBY FORREST
"MLV 534-2 to 538-2: ILI/Cleaning: 5/23 & 6/1
--5/23/17 through 6/1/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
420719 - WILLMUT/TGP CAMP SHELBY FORREST
"MLV 538-2 to 542-2: ILI/Cleaning: 5/25 & 6/8
--5/25/17 through 6/8/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
412789 - LEAF/TGP JASPER COUNTY: RIP 538 2 5
"Sta. 546: Trap Modifications
--4/10/17 through 6/10/17: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 555-1 to 550-1: ILI Pigging: 6/13, 6/14, 6/20 & 6/22
--2/20/17 through 6/22/17: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential out of path restrictions may be at risk.
"MLV 562-2 to 563-2: Anomaly Remediation
--7/5/17 through 7/10/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"MLV 563-1 to 564-1: Anomaly Remediation
--7/11/17 through 7/22/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
800 Line Outages
"MLV 823 to MLV 824: Pipe Recoat
--4/3/17 through TBD: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The first phase of this project was completed. The second phase will be scheduled at a later date. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 4/3/17 through 5/31/17.
"***Sta. 823: Station Reversal
--7/5/17 through 7/21/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers in the area may experience higher than normal pressure for the duration of the outage. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 6/30/17 to 7/11/17.
"Sta. 823: Cooling System Upgrade
--9/1/17 through 11/30/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers in the area may experience higher than normal pressure for the duration of the outage. Potential out of path restrictions may be at risk.
"***MLV 826to MLV 827: Hydrotest
--7/28/17 through 8/14/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project. Potential out of path restrictions may be at risk.
420296 – FORSTHIL/TGP FOREST HILL LA RAPIDES
412847 - ACADIAN/TGP CHENEYVILLE RAPIDES
***Date Change, Previously scheduled 7/11/17 to 8/5/17.
"Sta. 827: Station Reversal
--5/9/17 through 8/17/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"***Sta 834: Station Outage
--6/1/16 through 5/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 6/1/16 to 5/15/17.
"***MLV 836 to MLV 837: Delhi Lateral Tie-In
--8/21/17 through 8/31/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Date Change, Previously scheduled 8/7/17 to 8/17/17.
"***Sta. 836A: Station Tie-In
--8/21/17 through 8/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Producers in the area could experience higher than normal operating pressures. Potential out of path restrictions may be at risk.
"MLV 846-1 to MLV 847-1: Hydrotest
--9/15/17 through 10/15/17: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 847: Station Reversal
--8/12/17 through 12/14/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
"Sta. 847: Hydrotest
"MLV 864-1 to 865-1: Anomaly Remediation
--7/24/17 through 7/29/17: This outage will require pressure reductions and possibly line isolations. This will limit throughput and may result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
If you have any questions, please contact your Scheduler.