Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  04/27/2017 6:41:37PM Notice End Date/Time:  05/27/2017 9:00:00am
Post Date/Time:  4/27/2017 6:41:37 PM Notice ID: 363108
Reqrd Rsp:  1 Rsp Date:  04/27/2017
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Updated TGP Scheduled Outages
Notice Text:

April 27, 2017

 

TO:  ALL TENNESSEE CUSTOMERS

 

RE:  UPDATED TGP SCHEDULED OUTAGES

 

This notice is an update of the 2017 planned outages and maintenance

activities on Tennessee Gas Pipeline.

 

The Outage and Maintenance schedule is available in an Excel

spreadsheet format which may be found in DART.

 

Some projects may reduce capacity to a level below anticipated

demand (nominations), or require taking individual meters out of

service. 

 

For each project, based upon anticipated demand, the highest

level of service Tennessee expects to be impacted is noted. 

Unless noted otherwise, all impacts are in the Supply to Market

direction.

 

Projects may be added, altered, delayed or canceled.  Tennessee

will provide updates by posting revisions on a weekly basis or

more often if necessary.

 

Projects revised or added since the last posting are preceded

by ***.  Within the Excel Spreadsheet and Adobe Files, revisions

are highlighted and an asterisk has been added to the "Revised"

column.

 

Unless otherwise noted, all listed meters will be physically shut

-in for the duration of the project.

 

Unless otherwise noted, all scheduled dates represent gas days

as defined in the Tennessee Gas Pipeline tariff to mean a period

of twenty-four consecutive hours, beginning and ending at 9:00

a.m. (Central Clock Time).

 

=========================

Completed Outages

=========================

"***Sta. 409:  ESD Test

***Completed

………………………………"

"***MLV 32-3S to 25-3D:  ILI/Cleaning: 4/3-4/8,  4/18 & 4/20

***Completed

The following meters are available for nominations:

400448 – CICO/TGP MERCY GU 1 LIBERTY

44521 – TGP/KMTP CLEVELAND SAN JACINTO

412500 – SANDHAWK/TGP DREW'S LANDING SAN JACINTO

412747  TEXLA/TGP DREWS LANDING NO 2; RIP 2

412453 – TEXLA/TGP WEST LUMBER #2 POLK

412738 - TECOGATH/TGP TECO INDIAN SPRINGS

411374 – UNIT PET/TGP UDP NEW ACE DEHY POLL

………………………………"

"***Sta. 209-6A:  Unit Maintenance

***Completed

………………………………"

"***MLV 214-1 to MLV 215-1:  Drip Removal

***Completed

The following meters are available for nominations:

420066 - DOMINION/TGP AUGUSTA OH CARROLL

………………………………"

"***Sta. 310:  Station Outage

***Completed

………………………………"

"***MLV 866-1 to 867-1:  Pipe Replacement

***Completed

………………………………"

=========================

100 Line Outages

=========================

"Sta. 17:  Station Reversal

--5/31/16 through 5/31/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 17-1 to 20-1:  Spike Test

--8/7/17 through 9/25/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

420167 - COKINOS/TGP WOODS FARM TX FORT BEND

………………………………"

"MLV 17-2 to 20-2:  Spike Test

--6/1/17 through 7/30/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

411788 - DCP GLP/TGP KATY TRANSPORT WALLER

412722 - JOY RES/TGP UDP MERI JOSEY HARRIS

………………………………"

"MLV 17-3 to 20-3:  Spike Test

--3/20/17 through 5/19/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

411159 - ENTRPRSE/TGP KATY DEHY TRANS WALLER

412647 - F-W OIL/TGP KULHANEK AUSTIN

 421085 - CEGS/TGP PEDERSON ROAD WALLER

………………………………"

"MLV 17-3 to 13-3:  Hydrotest

--4/26/17 through 6/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  In the path nominations may be at risk.

421055 - TRES PAL/TGP TRES PALACIOS STORAGE

420190 – COKINOS/TGP SULAK FARM TX WHARTON

411938 – LASERGTH/TGP UDP NORTH LOUISE DHY

411911 – ETP/TGP WHARTON COUNTY TRANSPORT EX

412099 - LASERGTH/TGP UDP JONES CREEK OTELL

………………………………"

"MLV 20-1 to 20-1A:  Pipe Replacement

--3/20/17 through 5/5/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Bear Creek:  Shut-In Test

--4/18/17 through 4/24/17:  This project will require a storage outage. 

………………………………"

"Bear Creek:  Shut-In Test

--10/17/17 through 10/23/17:  This project will require a storage outage. 

………………………………"

"MLV 40-1D to 47-1S:  ILI/Cleaning: 5/16, 5/17, 5/18 & 5/22

--5/16/17 through 5/22/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 40-2D to 47-2S:  ILI Cleaning: 6/14, 6/20 & 6/22

--6/14/17 through 6/22/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 40-3 to MLV 32-3:  ILI/ Cleaning Run: 4/24, 4/28 & 5/1

--4/24/17 through 5/1/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 41-2A to 42-2:  Bi-Directional Trap Installation

--8/7/17 through 9/22/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 47:  Hydrotest

--9/18/17 through 10/13/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 47-1 to 54-1:  ILI/Cleaning: 5/3 - 5/5, 5/8 & 5/11

--5/3/17 through 5/11/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 47-1 to 49-1:  Spike Test

--6/5/17 through 7/29/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 47-2 to 48-2:  Spike Test

--7/3/17 through 9/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

47872 - ATMOS/TGP CHAUVIN OUACHITA

………………………………"

"MLV 55-1 to 63-1:  Anomaly Remediation

--3/3/17 through 5/6/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 56-3 to 57-3:  Anomaly Remediation

--4/10/17 through 4/12/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 57-3 to 58-3:  Pipe Remediation

--11/18/16 through 6/1/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 71-4D to 73-4:  Anomaly Remediation

--5/1/17 through 8/10/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 106 to Sta.200:  Anomaly Digs

--3/13/17 through 4/3/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"***Sta. 106:  ESD Test and New ESD Control Line Installation

--5/11/17 through 5/12/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Other Change

………………………………"

"MLV 106-4D to 108-4:  Spike Test

--7/17/17 through 10/7/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 107-5 to 109-5:  Pipe Replacement

--3/13/17 through 5/27/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"***MLV 113-3:  Drip Removal

--6/13/17 through 6/23/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

***Date Change, Previously scheduled 6/15/17 to 6/23/17.

………………………………"

"MLV 119-2:  Pipe Replacement

--9/1/17 through 10/31/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

=========================

200 Line Outages

=========================

"MLV 200-4 to 200-4A:  ILI Run

--4/26/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 200-4B to MLV 204-4:  Anomaly Remediation

--5/29/17 through 6/10/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 204-10A:  Unit Maintenance

--3/13/17 through 4/24/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 204-2 to MLV 209-2:  Anomaly Remediation

--6/26/17 through 7/8/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 204-4 to MLV 208-4:  Anomaly Remediation

--7/24/17 through 7/29/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 207-4 to 208-4:  Landslide Restoration

--5/26/17 through 6/7/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"***Sta. 209-3A, 4A, 9A & 10A:  Unit Maintenance

--5/8/17 through 5/12/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Added

………………………………"

"MLV 209-1 to MLV 214-1:  Anomaly Remediation

--7/10/17 through 7/15/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 209-2 to MLV 214-2:  Anomaly Remediation

--6/12/17 through 6/24/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 209-3 to MLV 214-3:  Anomaly Remediation

--7/17/17 through 7/22/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 209-8A:  Unit Maintenance

--4/24/17 through 5/12/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 214-1A:  Foundation Replacement

--3/27/17 through 8/1/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 224-2 to Kinder Road:  Anomaly Remediation

--8/14/17 through 8/26/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 237-1:   SCCDA

--7/10/17 through 7/15/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 229-2 to MLV 232-2:  Anomaly Digs

--7/17/17 through 7/22/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 230C:  ESD Test

--5/17/17 through 5/17/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 230C:  Station Maintenance

--5/18/17 through 5/18/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 230C:  Station Maintenance

--6/6/17 through 6/8/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 231-2:  Pipe Replacement

--7/1/17 through 9/30/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 237-1 to MLV 245-1:  Anomaly Digs

--6/26/17 through 8/5/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"***Sta. 241-1B:  Unit Maintenance

--5/8/17 through 5/15/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

***Added

………………………………"

"Sta. 241-2A:  Unit Maintenance

--4/17/17 through 4/28/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 245:  ESD

--6/19/17 through 6/23/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 249-1A:  Unit Maintenance

--5/8/17 through 6/4/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 249-1B:  Unit Maintenance

--6/5/17 through 6/16/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 249-2B:  Unit Maintenance

--6/19/17 through 6/30/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 251-2 & 251-3:  Tie-In

--7/24/17 through 7/29/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 251-1 & 251-3:  Tie-In

--7/29/17 through 8/16/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 254-2B:  Unit Maintenance

--5/1/17 through 5/7/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 257-3:  Tie-In

--7/14/17 through 8/31/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 260-1 to 261-1A:  Tie-In

--7/23/17 through 7/29/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 260-2:  ECDA

--6/26/17 through 7/8/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 261B-100:  Hydrotest

--(Exact Dates TBD):  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

400484 - BAY ST/TGP AGAWAM MASS HAMPDEN

………………………………"

"MLV 263A-100::  ECDA

--6/12/17 through 6/17/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 264B-101 to 264B-101:  ILI/Cleaning: 4/12 & 4/13

--4/12/17 through 4/13/17:  This activity will require operating at controlled flow rates. The listed meter below might experience pressure and flow fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

420191 - BOSTN/TGP SPENCER MA WORCHESTER

………………………………"

"MLV 265C-100:  Anomaly Remediation

--8/7/17 through 8/11/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 265A-100:  Anomaly Remediation

--8/14/17 through 8/25/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 266A:  Controls Replacement

--9/26/17 through 10/20/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. The listed meter below might experience pressure and flow fluctuations.  Potential out of path restrictions may be at risk.

420285 – AGT/TGP MENDON MASS TIE OVER WORCHE

………………………………"

"MLV 268A-101 to MLV 268A-100:  ILI/Cleaning

--4/24/17 through 4/26/17:  This activity will require operating at controlled flow rates. The listed meter below might experience pressure and flow fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

420112 - FITCHBRG/TGP FITCHBURG MA WORCHESTE

420111 - BOSTN/TGP LEOMINSTER MA WORCHESTER

………………………………"

"MLV 268A-200:  ECDA

--6/19/17 through 6/24/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270B-400 to 270B-401:  ILI/Cleaning: 4/10 & 4/11

--4/10/17 through 4/11/17:  This activity will require operating at controlled flow rates. The listed meter below might experience pressure and flow fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

420121 - BAY ST/ TGP LAWRENCE MA ESSEX

………………………………"

"MLV 270A-100:  Anomaly Remediation

--5/22/17 through 6/23/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270C-103:  ILI/Cleaning

--8/4/17 through 8/9/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270C-1100 to 270C-1101:  ILI/Cleaning

--8/7/17 through 8/16/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270C-300:  Anomaly Remediation

--4/3/17 through 4/28/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270C-300:  Anomaly Remediation

--5/1/17 through 5/19/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270C-301:  Anomaly Remediation

--5/1/17 through 5/19/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 405:  ESD Test

--5/9/17 through 5/9/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

=========================

300 Line Outages

=========================

"Sta. 303-1A:  Unit Maintenance

--6/5/17 through 6/10/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 307-1 to MLV 219-2:  ILI/Cleaning: 4/18, 4/20 & 4/25

--4/18/17 through 4/25/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The listed meter below will be shut-in for the entire duration of the project.  Potential in the path restrictions may be at risk.

420730 - NFG/TGP CRANBERRY SMS VENANGO

………………………………"

"MLV 307-2 to MLV 219-3:  ILI/Cleaning: 5/23 & 5/25

--5/23/17 through 5/25/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 307-2A:  Unit Maintenance

--7/26/17 through 8/2/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 307-4A:  Unit Maintenance

--5/15/17 through 6/4/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 307-5A:  Unit Maintenance

--4/24/17 through 4/27/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 307-6A:  Unit Maintenance

--5/1/17 through 5/6/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"***Sta. 310-1A:  Unit Maintenance

--5/24/17 through 5/26/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Added

………………………………"

"MLV 313A-100/313A-400:  ILI Cleaning: 5/9, 5/11 & 5/16

--5/9/17 through 5/16/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 315:  Susquehanna West Project - Station Tie-In

--6/5/17 through 6/11/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 315:  Susquehanna West Project

--7/3/17 through 7/16/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential in the path restrictions may be at risk.

………………………………"

"***Sta. 315-1B:  Unit Maintenance

--5/21/17 through 5/24/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Added

………………………………"

"Sta. 317:  Vent Pipe Relocation

--4/18/17 through 4/20/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 317:  Electrical Tie-Ins

--6/11/17 through 6/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 317:  Tie-In

--7/17/17 through 7/27/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 319:  Compressor Replacement

--3/6/17 through 6/23/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Meter 420203:  Meter Station Upgrade

--6/1/17 through 9/1/17:  This project will require a meter station outage. The listed meter below will be shut-in for the entire duration of the project. 

420203 - UGIPENN/TGP UNIONDALE PA SUSQUEHANNA

………………………………"

"MLV 321-2 to MLV 325-2:  Anomaly Remediation

--(Exact Dates TBD):  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 323A:  Station Tie-In

--6/16/17 through 6/29/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***Meter 420245:  Flow Control Valve Replacement

--5/23/17 through 5/25/17:  This project will require a meter station outage. The listed meter below will be shut-in for the entire duration of the project. 

420245 – COL GAS/TGP MILFORD PA BIG PIKE

***Date Change, Previously scheduled 5/9/17 to 5/11/17.

………………………………"

"MLV 325-1 to MLV 329-1:  Anomaly Digs

--8/28/17 through 11/11/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 325-3A & 4A:  Unit Maintenance

--5/30/17 through 6/2/17:  This project will require a unit outages, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 329-1 to 336-1:  Anomaly Digs

--5/30/17 through 6/7/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 329B-100:  ECDA

--7/24/17 through 7/29/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 331-2:  ILI Run

--7/31/17 through 8/12/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 332-1R2-CR:  ECDA

--6/7/17 through 6/10/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"***MLV 336-1 to 356-1:  ILI Cleaning: 5/2, 5/4, 5/9 & 5/31

--5/2/17 through 5/31/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The capacity for the listed meters below will be restricted for the duration of the runs.  Potential out of path restrictions may be at risk.

420453 - CONN NG/TGP NORTH BLOOMFIELD CT HAR                  

420205 – CONN NG/TGP BLOOMFIELD CT HARTFORD

***Date Change, Previously scheduled 4/27, 5/3, 5/8 & 5/31

………………………………"

=========================

400 Line Outages

=========================

"Sta. 409A:  Automation Controls Upgrade

--(Sep./Oct. – Exact Dates TBD): This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 405-2 to 408-2:  Spike Test

--(Jan. 2018/Feb. 2018 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

=========================

500 Line Outages

=========================

"MLV 507-1D to 516-1:  ILI/Cleaning

--6/20/17 through 6/23/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 507-1D to 516-1:  Anomaly Remediation

--7/1/17 through 7/31/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Meter 21041:  Filter Replacement and Inspection

--4/13/17 through 4/26/17:  This project will require a meter outage. The meter listed below will be shut-in for the duration of the project. 

421041 - KINETICA/TGP ACADIAN BLUEWATER INTE

………………………………"

"MLV 534:  Drip Removal

--8/8/17 through 9/1/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in during the scheduled dates listed below.  Potential out of path restrictions may be at risk.

8/22/2017 - 9/1/2017

420719 - WILLMUT/TGP CAMP SHLEBY FORREST

………………………………"

"MLV 534-2 to 538-2:  ILI/Cleaning: 5/23 & 6/1

--5/23/17 through 6/1/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

420719 - WILLMUT/TGP CAMP SHELBY FORREST

………………………………"

"MLV 538-2 to 542-2:  ILI/Cleaning: 5/25 & 6/8

--5/25/17 through 6/8/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

412789 - LEAF/TGP JASPER COUNTY: RIP 538 2 5

………………………………"

"Sta. 546:  Trap Modifications

--4/10/17 through 6/10/17:  This outage will require the pipeline to be taken out of service.  For the duration of the project, pressures may be lower.  This project may limit throughput and could result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 555-1 to 550-1:  ILI Pigging: 6/13, 6/14, 6/20 & 6/22

--2/20/17 through 6/22/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 562-2 to 563-2:  Anomaly Remediation

--5/14/17 through 5/16/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 563-1 to 564-1:  Anomaly Remediation

--5/3/17 through 5/12/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

=========================

800 Line Outages

=========================

"***Sta. 820 to Sta. 823:  Maintenance Pig

--5/10/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. The meter listed below will be shut-in for approximately 1 hour while the pig passes:

420581 – ENTRGYLA/TGP BECKWITH CREEK CALCASI

 

The meters listed below will be shut-in for the entire duration of the pig run:

412768 – GLDNPASS/TGP STARKS LNG: RIP 820 10

412737 – LBERTYGS/TGP UDP DE QUINCY GAS STOR

412013 – ENTRPRSE/TGP SABINE RIVER TRANS NE 

Potential out of path restrictions may be at risk.

***Added

………………………………"

"MLV 823 to MLV 824:  Pipe Recoat

--4/3/17 through 5/31/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***Sta. 823:  Compressor Building Welding

--5/3/17:  This project will require a building outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

***Added

………………………………"

"Sta. 823:  Station Reversal

--6/5/17 through 6/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 823:  Cooling System Upgrade

--9/1/17 through 11/30/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 826to MLV 827:  Hydrotest

--6/19/17 through 7/20/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

420296 – FORSTHIL/TGP FOREST HILL LA RAPIDES

412847 - ACADIAN/TGP CHENEYVILLE RAPIDES

………………………………"

"Sta. 827:  Station Reversal

--5/9/17 through 8/17/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 834:  Station Outage

--6/1/16 through 5/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 836 to MLV 837:  Delhi Lateral Tie-In

--8/7/17 through 8/17/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 836A:  Station Tie-In

--8/7/17 through 8/17/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Producers in the area could experience higher than normal operating pressures.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 846-1 to MLV 847-1:  Hydrotest

--9/15/17 through 10/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 847:  Station Reversal

--8/12/17 through 12/14/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 847:  Hydrotest

--9/15/17 through 10/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***Sta. 860:  ESD Test

--5/23/17:  his project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential out of path restrictions may be at risk.

***Added

………………………………"

"MLV 864-1 to 865-1:  Anomaly Remediation

--8/11/17 through 8/18/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

 

If you have any questions, please contact your Scheduler.

 

..