Subject:  Updated TGP Scheduled Outages
Notice Text:

March 23, 2017

 

TO:  ALL TENNESSEE CUSTOMERS

 

RE:  UPDATED TGP SCHEDULED OUTAGES

 

This notice is an update of the 2017 planned outages and maintenance

activities on Tennessee Gas Pipeline.

 

The Outage and Maintenance schedule is available in an Excel

spreadsheet format which may be found in DART.

 

Some projects may reduce capacity to a level below anticipated

demand (nominations), or require taking individual meters out of

service. 

 

For each project, based upon anticipated demand, the highest

level of service Tennessee expects to be impacted is noted. 

Unless noted otherwise, all impacts are in the Supply to Market

direction.

 

Projects may be added, altered, delayed or canceled.  Tennessee

will provide updates by posting revisions on a weekly basis or

more often if necessary.

 

Projects revised or added since the last posting are preceded

by ***.  Within the Excel Spreadsheet and Adobe Files, revisions

are highlighted and an asterisk has been added to the "Revised"

column.

 

Unless otherwise noted, all listed meters will be physically shut

-in for the duration of the project.

 

Unless otherwise noted, all scheduled dates represent gas days

as defined in the Tennessee Gas Pipeline tariff to mean a period

of twenty-four consecutive hours, beginning and ending at 9:00

a.m. (Central Clock Time).

 

=========================

Completed Outages

=========================

"***MLV 47-2D to 54-2S:  Anomaly Remediation

***Completed

………………………………"

"***MLV 47-4D to 54-4S:  Anomaly Remediation

***Completed

………………………………"

"***Sta. 209-9A:  Unit Maintenance

***Completed

………………………………"

"***Sta. 317:  Susquehanna West Project - Station Tie-Ins

***Completed

………………………………"

"***Sta. 317:  Tie-in for Susquehanna West Project

***Completed

………………………………"

=========================

100 Line Outages

=========================

"Sta. 1:  ESD Test

--4/11/17 through 4/11/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 16-3 to 17-3S:  Tee Installation

--3/27/17 through 4/7/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 17:  Station Reversal

--5/31/16 through 5/31/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 17-1S to 9-1D:  Anomaly Remediation

--2/10/17 through 3/31/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in during the timeframe listed below.

 

2/10/17 – 3/4/17

412723 – PATTERSN/TGP HILL WHARTON

400454 – H-M RES/TGP UDP EGYPT NORTH WEST DE

412023 – HGI/TGP UDP ENGLEHARDT COLORADO

 

Potential out of path restrictions may be at

………………………………"

"MLV 17-1 to 20-1:  Spike Test

--7/26/17 through 9/12/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

420167 - COKINOS/TGP WOODS FARM TX FORT BEND

………………………………"

"MLV 17-2 to 20-2:  Spike Test

--6/1/17 through 7/19/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

411788 - DCP GLP/TGP KATY TRANSPORT WALLER

412722 - JOY RES/TGP UDP MERI JOSEY HARRIS

………………………………"

"MLV 17-3 to 20-3:  Spike Test

--3/20/17 through 5/19/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

411159 - ENTRPRSE/TGP KATY DEHY TRANS WALLER

412647 - F-W OIL/TGP KULHANEK AUSTIN

 421085 - CEGS/TGP PEDERSON ROAD WALLER

………………………………"

"*** MLV 17-3 to 13-3: Hydrotest

--4/10/17 through 6/30/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in during the timeframes listed below.

 

4/10/17 – 4/24/17 & 6/26/17 – 6/30/17

421055 - TRES PAL/TGP TRES PALACIOS STORAGE

 

The meters listed below will be shut-in for the entire duration of the project.

 

420190 – COKINOS/TGP SULAK FARM TX WHARTON

411938 – LASERGTH/TGP UDP NORTH LOUISE DHY

411911 – ETP/TGP WHARTON COUNTY TRANSPORT EX

412099 - LASERGTH/TGP UDP JONES CREEK OTELL

 

In the path nominations may be at risk.

 

*** Scope Change, Meters Added. Date Change, Previously scheduled 4/24/17 to 5/19/17.

………………………………"

"MLV 20-1 to 20-1A:  Pipe Replacement

--3/20/17 through 4/24/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***MLV 24-3:  Pipe Replacement

--2/24/17 through 3/24/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

***Date Change, Previously scheduled 2/24/17 to 3/20/17.

………………………………"

MLV 32-3S to 25-3D:  ILI/Cleaning: 4/3-4/8, 4/18 & 4/20

--4/3-4/8, 4/18 & 4/20:  This project will require a chemical cleaning on 4/3 through 4/8.  Out of Path nominations may be at risk.

 

 

 

The ILI pigging on 4/18 and 4/20 will require controlled flow rates in the noted pipeline segment (Segment 125 BH) on 4/18 & 4/20. During the pigging, each meter listed below will be restricted to a capacity of no more than 10k dth/d for the duration of the pig runs on 4/18 & 4/20 only.  After the pig run is completed on 4/18 & 4/20 these meters may resume scheduled flow.

 

400448 – CICO/TGP MERCY GU 1 LIBERTY

44521 – TGP/KMTP CLEVELAND SAN JACINTO

412500 – SANDHAWK/TGP DREW'S LANDING SAN JACINTO

412747 - TEXLA/TGP DREWS LANDING NO 2; RIP 2

412453 – TEXLA/TGP WEST LUMBER #2 POLK

412738 - TECOGATH/TGP TECO INDIAN SPRINGS

411374 – UNIT PET/TGP UDP NEW ACE DEHY POLL

 

Potential out of path restrictions may be at risk.

………………………………"

"Bear Creek:  Shut-In Test

--4/18/17 through 4/24/17:  This project will require a storage outage. 

………………………………"

"Bear Creek:  Shut-In Test

--10/17/17 through 10/23/17:  This project will require a storage outage. 

………………………………"

"MLV 40-1D to 47-1S:  ILI/Cleaning: 5/16, 5/17, 5/18 & 5/22

--5/16/17 through 5/22/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 41-2A to 42-2:  Bi-Directional Trap Installation

--8/7/17 through 9/22/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 47:  Hydrotest

--9/18/17 through 10/13/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 47-1 to 54-1:  ILI/Cleaning: 5/3 - 5/5, 5/8 & 5/11

--5/3/17 through 5/11/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 47-1 to 49-1:  Spike Test

--6/5/17 through 7/29/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 47-2 to 48-2:  Spike Test

--7/3/17 through 9/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meters listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

47872 - ATMOS/TGP CHAUVIN OUACHITA

………………………………"

"MLV 55-1 to 63-1:  Anomaly Remediation

--3/3/17 through 5/6/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 56-3 to 57-3:  Anomaly Remediation

--5/6/17 through 5/10/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 57-3 to 58-3:  Pipe Remediation

--11/18/16 through 6/1/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 71-4D to 73-4:  Anomaly Remediation

--5/15/17 through 8/10/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 87-1C thru 6C:  Unit Maintenance

--11/7/16 through 12/22/16:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 96-2D:  Unit Maintenance

--3/14/17 through 3/31/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 106 to Sta.200:  Anomaly Digs

--3/13/17 through 4/3/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 106-4D to 108-4:  Spike Test

--6/26/17 through 9/16/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 107-5 to 109-5:  Pipe Replacement

--3/13/17 through 5/27/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 113-3:  Drip Removal

--6/15/17 through 6/23/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 119-2:  Pipe Replacement

--7/1/17 through 9/30/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

=========================

200 Line Outages

=========================

"MLV 200-4 to 200-4A:  ILI Run

--4/26/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 200-4B to MLV 204-4:  Anomaly Remediation

--5/29/17 through 6/10/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"***Sta. 204-10A:  Unit Maintenance

--3/13/17 through 4/24/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Date Change, Previously scheduled 3/13/17 to 3/24/17.

………………………………"

"MLV 204-2 to MLV 209-2:  Anomaly Remediation

--6/26/17 through 7/8/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 204-4 to MLV 208-4:  Anomaly Remediation

--7/24/17 through 7/29/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 209-1 to MLV 214-1:  Anomaly Remediation

--7/10/17 through 7/15/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 209-2 to MLV 214-2:  Anomaly Remediation

--6/12/17 through 6/24/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 209-3 to MLV 214-3:  Anomaly Remediation

--7/17/17 through 7/22/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 214-1 to MLV 215-1:  Drip Removal

--4/17/17 through 5/1/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. The capacity for the listed meter below will be limited to 550 k/Dth for the duration of the outage.  Potential in the path restrictions may be at risk.

420066 - DOMINION/TGP AUGUSTA OH CARROLL

………………………………"

"Sta. 214-7A & 11A:  Unit Maintenance

--3/20/17 through 3/24/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 224-2 to Kinder Road:  Anomaly Remediation

--8/14/17 through 8/26/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 237-1:   SCCDA

--7/10/17 through 7/15/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 229-2 to MLV 232-2:  Anomaly Digs

--7/17/17 through 7/22/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 230C:  ESD Test

--5/17/17 through 5/17/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 230C:  Station Maintenance

--5/18/17 through 5/18/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 230C:  Station Maintenance

--6/6/17 through 6/8/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 231-2:  Pipe Replacement

--7/1/17 through 9/30/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 237-1 to MLV 245-1:  Anomaly Digs

--6/26/17 through 8/5/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"***Sta. 245:  ESD

--6/19/17 through 6/23/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Date Change, Previously scheduled 5/15/17 to 5/19/17.

………………………………"

"Sta. 249-1A:  Unit Maintenance

--5/8/17 through 6/4/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 249-1B:  Unit Maintenance

--6/5/17 through 6/16/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 249-2B:  Unit Maintenance

--6/19/17 through 6/30/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 251-2 & 251-3:  Tie-In

--7/24/17 through 7/29/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 251-1 & 251-3:  Tie-In

--7/29/17 through 8/16/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 254-1A:  Unit Maintenance

--4/3/17 through 4/5/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 254-2A:  Unit Maintenance

--4/5/17 through 4/10/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 254-2B:  Unit Maintenance

--5/1/17 through 5/7/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 254-6A:  Unit Maintenance

--4/11/17 through 4/13/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 257-3:  Tie-In

--7/14/17 through 8/31/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 260-1 to 261-1A:  Tie-In

--7/23/17 through 7/29/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 260-2:  ECDA

--6/26/17 through 7/8/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 263A-100: ECDA

--6/12/17 through 6/17/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"***MLV 264B-101 to 264B-101:  ILI/Cleaning: 4/12 & 4/13

--4/12/17 through 4/13/17:  This activity will require operating at controlled flow rates. The listed meter below might experience pressure and flow fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

420191 - BOSTN/TGP SPENCER MA WORCHESTER

***Other Change

………………………………"

"MLV 265C-100:  Anomaly Remediation

--8/7/17 through 8/11/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 265A-100:  Anomaly Remediation

--8/14/17 through 8/25/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 266A:  Controls Replacement

--9/26/17 through 10/20/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. The listed meter below might experience pressure and flow fluctuations.  Potential out of path restrictions may be at risk.

420285 – AGT/TGP MENDON MASS TIE OVER WORCHE

………………………………"

"MLV 268A-101 to MLV 268A-100:  ILI/Cleaning

--4/24/17 through 4/26/17:  This activity will require operating at controlled flow rates. The listed meter below might experience pressure and flow fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

420112 - FITCHBRG/TGP FITCHBURG MA WORCHESTE

420111 - BOSTN/TGP LEOMINSTER MA WORCHESTER

………………………………"

"MLV 268A-200:  ECDA

--6/19/17 through 6/24/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270B-400 to 270B-401:  ILI/Cleaning: 4/10 & 4/11

--4/10/17 through 4/11/17:  This activity will require operating at controlled flow rates. The listed meter below might experience pressure and flow fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

420121 - BAY ST/ TGP LAWRENCE MA ESSEX

………………………………"

"***MLV 270A-100:  Anomaly Remediation

--5/22/17 through 6/23/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

***Other Change

………………………………"

"MLV 270C-103:  ILI/Cleaning

--8/4/17 through 8/9/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 270C-1100 to 270C-1101:  ILI/Cleaning

--8/7/17 through 8/16/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"***MLV 270C-300:  Anomaly Remediation

--4/3/17 through 4/28/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

***Other Change

………………………………"

"***MLV 270C-300:  Anomaly Remediation

--5/1/17 through 5/19/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

***Other Change

………………………………"

"MLV 270C-301:  Anomaly Remediation

--5/1/17 through 5/19/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

=========================

300 Line Outages

=========================

"MLV 307-1 to MLV 219-2:  ILI/Cleaning: 4/18, 4/20 & 4/25

--4/18/17 through 4/25/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 307-2 to MLV 219-3:  ILI/Cleaning: 5/23 & 5/25

--5/23/17 through 5/25/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 307-2A:  Unit Maintenance

--7/26/17 through 8/2/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 307-4A:  Unit Maintenance

--5/15/17 through 6/4/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 307-5A:  Unit Maintenance

--3/27/17 through 3/30/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 307-6A:  Unit Maintenance

--4/27/17 through 5/10/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Harrison:  Storage Shut-In

--3/20/17 through 3/27/17:  This project will require a storage outage. 

………………………………"

"Ellisburg:  Shut-In

--4/4/17 through 4/10/17:  This project will require a storage outage. 

………………………………"

"MLV 313A-100/313A-400:  ILI Cleaning: 5/9, 5/11 & 5/16

--5/9/17 through 5/16/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 315:  Susquehanna West Project - Station Tie-In

--6/5/17 through 6/11/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 315:  Susquehanna West Project

--7/3/17 through 7/16/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 317:  Electrical Tie-Ins

--6/11/17 through 6/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 317:  Tie-In

--7/17/17 through 7/27/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 319:  Compressor Replacement

--3/6/17 through 6/23/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***Meter 420203:  Meter Station Upgrade

--6/1/17 through 9/1/17:  This project will require a meter station outage. The listed meter below will be shut-in for the entire duration of the project. 

420203 - UGIPENN/TGP UNIONDALE PA SUSQUEHANNA

***Added

………………………………"

"MLV 321-2 to MLV 325-2:  Anomaly Remediation

--4/24/17 through 5/6/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 323A:  Station Tie-In

--6/16/17 through 6/29/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 325-1 to MLV 329-1:  Anomaly Digs

--8/28/17 through 11/11/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential in the path restrictions may be at risk.

………………………………"

"***Sta. 325-3A & 4A:  Unit Maintenance

--5/30/17 through 6/2/17:  This project will require a unit outages, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Added

………………………………"

"MLV 329-1 to 336-1:  Anomaly Digs

--5/30/17 through 6/7/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 329B-100:  ECDA

--7/24/17 through 7/29/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 331-2:  ILI Run

--7/31/17 through 8/12/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 332-1R2-CR:  ECDA

--6/7/17 through 6/10/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 336 to MLV 356:  ILI/Cleaning

--4/27/17 through 5/31/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 354-1:  Tie-In

--7/24/17 through 7/30/17:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

=========================

400 Line Outages

=========================

"MLV 405-2 to 408-2:  Spike Test

--(Sep./Oct. – Exact Dates TBD): This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 409-2A:  Unit Maintenance

--3/29/17 through 3/29/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"Sta. 409A:  Automation Controls Upgrade

--(Sep./Oct. – Exact Dates TBD): This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"***Sta. 409:  ESD Test

--4/27/17 through 4/30/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Added

………………………………"

"***Sta. 409A:  ESD Test

--5/5/17 through 5/7/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

***Added

………………………………"

=========================

500 Line Outages

=========================

"MLV 506:  Pipe Recoat

--3/28/17 through 4/2/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"***MLV 507-1D to 516-1:  ILI/Cleaning

--6/20/17 through 6/23/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

***Date Change, Previously scheduled 6/21/17 to 6/23/17.

………………………………"

"MLV 507-1D to 516-1:  Anomaly Remediation

--7/1/17 through 7/31/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Meter 21041:  Filter Replacement and Inspection

--4/13/17 through 4/26/17:  This project will require a meter outage. The meter listed below will be shut-in for the duration of the project. 

421041 - KINETICA/TGP ACADIAN BLUEWATER INTE

………………………………"

"***MLV 534:  Drip Removal

--8/8/17 through 9/1/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in during the scheduled dates listed below.  Potential out of path restrictions may be at risk.

8/22/2017 - 9/1/2017

420719 - WILLMUT/TGP CAMP SHLEBY FORREST

***Date Change, Previously scheduled 8/7/17 to 9/1/17.

………………………………"

"MLV 534-2 to 538-2:  ILI/Cleaning: 5/23 & 6/1

--5/23/17 through 6/1/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 538-2 to 542-2:  ILI/Cleaning: 5/25 & 6/8

--5/25/17 through 6/8/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 546:  Trap Modifications

--4/15/17 through 5/15/17:  This outage will require the pipeline to be taken out of service.  For the duration of the project, pressures may be lower.  This project may limit throughput and could result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 555-1 to 550-1:  ILI Pigging

--2/20/17 through 3/31/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 555-2 to 550-2:  ILI Pigging: 4/11 & 4/13

--4/11/17 through 4/13/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 555-3 to 552-3:  ILI Pigging: 3/21 & 3/23

--3/21/17 through 3/23/17:  This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 562-2 to 563-2:  Anomaly Remediation

--5/23/17 through 5/27/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 563-1 to 564-1:  Anomaly Remediation

--5/16/17 through 5/22/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

=========================

800 Line Outages

=========================

"MLV 823 to MLV 824:  Pipe Recoat

--4/3/17 through 5/31/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 823:  Station Reversal

--6/5/17 through 6/15/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 823:  Cooling System Upgrade

--9/1/17 through 11/30/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 827-1 to 823-1:  ILI/Cleaning:  3/20, 3/23 & 3/27

-- 3/20/17, 3/23/17 and 3/27/17:  This activity will require operating at controlled flow rates.  Potential out of path restrictions may be necessary.

The meters listed below will be shut-in for the entire pig run on each of the referenced days.  After the pig run is completed on each day, the meters may again resume flow.

421043 – PINE PRA/TGP PINE PRAIRIE NORTH RAP (*previously listed as 412729)

412847 – ACADIAN/TGO CHENEYVILLE RAPIDES

 

The meters listed below will be temporarily shut in only while the pig passes:

412713 – HUGHES E/TGP UDP BLACK STONE 13 EVEN

412844 – TEXLA/TGP ROY MARTIN GATHERING; RIP

420296 – FORSTHILL/TGP FOREST HILL LA RAPIDES

420530 – GLNMORA/TGP GLENMORA LA EXCH RAPIDE

421042 - ELIZ NG/TGP EVANGELINE SALES EVANGE

420629 – ELIZ NG/TGP OAKDALE DETENTION SALES

420687 - ELIZ NG/TGP ALLEN PARISH PRISON SAL

420406 – ELIZ NG/TGP ELIZABETH LA EMERGENCY

 

Out of path nominations may be at risk.

………………………………"

"MLV 826to MLV 827:  Hydrotest

--6/16/17 through 7/20/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The meter listed below will be shut-in for the duration of the project.  Potential out of path restrictions may be at risk.

420296 – FORSTHIL/TGP FOREST HILL LA RAPIDES

412847 - ACADIAN/TGP CHENEYVILLE RAPIDES

………………………………"

"Sta. 827:  Station Reversal

--4/17/17 through 8/17/17:  his project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta 834:  Station Outage

--6/1/16 through 4/19/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 836 to MLV 837:  Delhi Lateral Tie-In

--6/5/17 through 6/18/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 836A:  Station Tie-In

--6/15/17 through 6/18/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Producers in the area could experience higher than normal operating pressures.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 846-1 to MLV 847-1:  Hydrotest

--10/13/17 through 11/15/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 847:  Station Reversal

--8/12/17 through 12/14/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 847:  Hydrotest

--10/13/17 through 10/27/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"Sta. 860-1B:  Unit Maintenance

--3/21/17 through 3/22/17:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 864-1 to 865-1:  Anomaly Remediation

--5/8/17 through 5/15/17:  This outage will require pressure reductions and possibly line isolations.  This will limit throughput and may result in restrictions based on customer nominations.  Potential out of path restrictions may be at risk.

………………………………"

"MLV 866-1 to 867-1:  Pipe Replacement

--4/14/17 through 4/23/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential in the path restrictions may be at risk.

………………………………"

"MLV 871-1 to 876-1:  Anomaly Digs

--2/22/17 through 3/26/17:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential out of path restrictions may be at risk.

………………………………"

 

If you have any questions, please contact your Scheduler.

 

...