TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  01/21/2017 11:00:29AM Notice End Date/Time:  02/20/2017 9:00:00am
Post Date/Time:  1/21/2017 11:00:29 AM Notice ID: 362141
Reqrd Rsp:  1 Rsp Date:  01/21/2017
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 1-21-17 ID1
Notice Text:
Effective Timely Cycle (9:00) for the gas day of February 9, 2014

Effective Intraday Cycle 1 (14:00) for the gas day of January 21, 2017 Tennessee restricted the following:

 

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO Monthly Action Alert for Zone 4 for under-deliveries

 

RESTRICTIONS

Heidelberg Delivery Meter (Pin 420291) – through approx 40% of SIPss ID1 increases due to nominations in excess of operational capacity; 5,822 Dths

 

STA 204 (Segment 204 BH) – through 100% of SOP ID1 increases due to scheduled maintenance and nominations in excess of operational capacity; 44,712 Dths

 

STA 224 (Segment 224 FH) / HC Zn 5 (Segment 299 FH) – through approx 65% of SOP ID1 increases due to nominations in excess of operational capacity; 81,101 Dths

 

Arlington Storage Receipt Meter (Pin 412803) – through 100% of SIPsp ID1 increases due to imbalance management and operational concerns; 11,933 Dths

 

STA 245 (Segment 245 FH) – through approx 91% of SOP ID1 increases due to nominations in excess of operational capacity; 352,808 Dths

 

STA 307 (Segment 307 BH) – through 100% of SOP ID1 increases due to nominations in excess of operational capacity; 57,924 Dths

 

MLV 314 (Segment 314 BH) – through 100% of SOP ID1 increases due to nominations in excess of operational capacity; 61,178 Dths

 

STA 315 (Segment 315 BH) – through approx 90% of SOP ID1 increases due nominations in excess of operational capacity; 166,061 Dths

 

STA 325 (Segment 321 FH) - through approx 52% of SOP ID1 increases due to nominations in excess of operational capacity; 114,577 Dths

 

MLV 336 (Segment 324 FH) – through approx 76% of SOP ID1 increases due to nominations in excess of operational capacity; 9,251 Dths

 

Mahwah Delivery Meter (Pin 420207) – through approx 91% of SIPss ID1 increases due to nominations in excess of operational capacity; 77,937 Dths

 

LINEPACK RESTRICTIONS

Downstream of STA 237 on the 200 Line – through 100% of payback from TGP; 33,968 Dths

Not accepting PALD or PALAO Parks/Payback to the Pipe System Wide

 

STORAGE RESTRICTIONS

No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA)

Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR

CONFIRMATION REDUCTIONS.

 

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND

ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED

SERVICE OUTAGES.

 

If you have any questions, please contact your Scheduler.

 

...