TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  11/30/2016 4:55:08PM Notice End Date/Time:  12/30/2016 9:00:00am
Post Date/Time:  11/30/2016 4:55:08 PM Notice ID: 361627
Reqrd Rsp:  1 Rsp Date:  11/30/2016
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Updated TGP Scheduled Outages
Notice Text:

November 30, 2016

 

TO:  ALL TENNESSEE CUSTOMERS

 

RE:  UPDATED TGP SCHEDULED OUTAGES

 

This notice is an update of the 2016 planned outages and maintenance

activities on Tennessee Gas Pipeline.

 

The Outage and Maintenance schedule is available in an Excel

spreadsheet format which may be found in DART.

 

Some projects may reduce capacity to a level below anticipated

demand (nominations), or require taking individual meters out of

service. 

 

For each project, based upon anticipated demand, the highest

level of service Tennessee expects to be impacted is noted. 

Unless noted otherwise, all impacts are in the Supply to Market

direction.

 

Projects may be added, altered, delayed or canceled.  Tennessee

will provide updates by posting revisions on a weekly basis or

more often if necessary.

 

Projects revised or added since the last posting are preceded

by ***.  Within the Excel Spreadsheet and Adobe Files, revisions

are highlighted and an asterisk has been added to the "Revised"

column.

 

Unless otherwise noted, all listed meters will be physically shut

-in for the duration of the project.

 

Unless otherwise noted, all scheduled dates represent gas days

as defined in the Tennessee Gas Pipeline tariff to mean a period

of twenty-four consecutive hours, beginning and ending at 9:00

a.m. (Central Clock Time).

 

=========================

Completed Outages

=========================

"***MLV 25-2BR to 26-2:  Hydrotest

***Completed

………………………………"

"***MLV 40-1S, 2S, 3S & 4S:  Hydrotest

***Completed

………………………………"

"***Sta. 230C-4A:  Unit Maintenance

***Completed

………………………………"

"***MLV 508-1:  Line Recoats

***Completed

………………………………"

=========================

100 Line Outages

=========================

"Sta. 17:  Station Reversal

--5/31/16 through 5/31/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 36-3 to 38-3:  Hydrotest

--10/12/16 through 12/6/16:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 54-3D to 56-3:  Hydrotest

--10/3/16 through 11/23/16:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations. The listed meters will be shut-in for approximately eight hours during the scheduled dates listed below.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

412586 - ANR/TGP GREENVILLE

420941 - ANR/TGP GREENVILLE

………………………………"

"MLV 54-3A:  New MLV Install

--10/3/16 through 12/9/16:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 57-3 to 58-3:  Pipe Remediation

--11/18/16 through 6/1/17:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 60-4 to 63-4:  Hydrotest

--10/31/16 through 12/5/16:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 62-2 to 63-2:  Hydrotest

--10/17/16 through 11/17/16:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Sta. 63:  A Building Classification Project

--9/19/16 through 10/31/16:  This project will require a building outage, which will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Sta. 63:  B Building Classification Project

--10/10/16 through 11/23/16:  This project will require a building outage, which will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 79:  Station Reversal

--1/1/17 through 12/31/17:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 82-3C to 87-3:  ILI/Cleaning Pig 11/28, 11/29 & 12/1

--12/15/16 through 12/31/16:  This activity will require operating at controlled flow rates.   Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Sta. 87-1C thru 6C:  Unit Maintenance

--11/7/16 through 12/22/16:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 106-4D to 200-2S:  ILI/Cleaning Pig: 11/10, 11/15 & 11/17

--11/10/16 through 11/30/16:  This outage will require the pipeline to be taken out of service. For the duration of the project, TGP will only be able to deliver gas to the listed meter.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

=========================

200 Line Outages

=========================

"Sta. 204-7A:  Foundation Repair

--10/10/16 through 12/2/16:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"Sta. 214-12A:  Unit Maintenance

--11/28/16 through 12/2/16:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"***Sta. 214-2A:  Unit Maintenance

--10/1/16 through 12/1/16:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

***Date Change, Previously scheduled 10/1/16 to 11/18/16.

………………………………"

"Sta. 214-5A:  Unit Maintenance

--12/5/16 through 12/9/16:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Sta. 237-3A:  Unit Maintenance

--12/5/16 through 12/8/16:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 251-2 & 251-3:  Tie-In

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 251-1 & 251-3: Tie-In

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 257-3: Tie-In

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 260-1 to 261-1: Line Tie-Ins

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 260-1 to 261-1A:  Tie-In

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 261-1 to 261-1A:  Line Tie-Ins

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 261-1 to 261-1A:  Tie-In

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

=========================

300 Line Outages

=========================

"Sta. 317:  Ancillary Piping Relocation

--12/10/16 through 12/12/16:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 354-1:  Tie-In

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 355-1:  Tie-In

--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

=========================

500 Line Outages

=========================

"***MLV 538-1 to 542-1:  ILI/Cleaning Pig: 12/8, 12/13 & 12/15

--11/30/16 through 12/2/16:  This activity will require operating at controlled flow rates.   The meters listed below will be shut-in for a couple of hours until the pig passes. Customers may experience pressure fluctuations; however, no other service impact is anticipated.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

420807 – ATMOS-MS/TGP PINE SPRINGS ROAD LEAK

412060 – AMMID MD/TGP UDP HEIDELBURG TRANSPO

***Date Change, Previously scheduled 11/29/16 to 12/1/16.

………………………………"

"545-1 & 545-2:  Meter Install (Hot Taps)

--12/11/16 through 12/13/16:  This outage will require pressure reductions and possibly line isolations.  However no other service impact is anticipated.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

=========================

800 Line Outages

=========================

"Sta 834:  Station Outage

--6/1/16 through 9/9/16:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

 

If you have any questions, please contact your Scheduler.

 

...