TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  10/27/2016 5:35:24PM Notice End Date/Time:  11/26/2016 9:00:00am
Post Date/Time:  10/27/2016 5:35:24 PM Notice ID: 361307
Reqrd Rsp:  1 Rsp Date:  10/27/2016
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  TGP Outage Impact Report
Notice Text:
20161027 Market Impact Report.xlsx

 

 

TGP - Outage Impact Report

Seven Day Forecast (updated 10/27/16)

-Major impact  restrictions may be necessary

-Minor impact restrictions may be necessary depending on flow conditions

-Little to no impact, though minor outages may cause incremental reductions

 

Station # / Lateral (FH)=forward haul (BH)=backward haul

 

Est Nominal Design Capacity (Thousand Dth)

Saturday

(10/29)

Sunday

(10/30)

Monday

(10/31)

Tuesday

(11/1)

Wednesday

(11/2)

Thursday

(11/3)

Friday

(11/4)

 

Primary Outage(s) that may Impact Throughput

Est. Operational Capacity (Operational Impact) - Thousand Dth

Station 409A (Segment 492

FH)

 

251

170 (81)

170 (81)

170 (81)

170 (81)

170 (81)

170 (81)

170 (81)

Station 409A-1: Emergent Repair

Station 409 (Donna Line) (segment 490

FH)

 

541

 

541

 

541

 

541

 

541

 

541

 

541

 

541

 

 

Station 1 (segment 409

BH)

 

242

 

242

 

242

 

242

 

242

 

242

 

242

 

242

 

 

Station 9 (segment 109

BH)

 

698

 

598 (100)

 

598 (100)

 

598 (100)

 

598 (100)

 

598 (100)

 

598 (100)

 

598 (100)

Station 9: Emergent Repair

 

Sta. 47 (segment

143 FH)

 

1,652

 

1,370

 

1,370

 

1,370

 

1,370

 

1,370

 

1,370

 

1,370

 

 

MLV 843 (segment 834

BH)

 

223

 

223

 

223

 

223

 

223

 

223

 

223

 

223

 

 

Station 546 (segment 542

BH)

 

1,504

 

1,222

 

1,222

 

1,222

 

1,222

 

1,222

 

1,222

 

1,222

 

MLV 538-1 to 542-1: ILI/Cleaning Pig: 11/2, 11/7 & 11/9  (M) (11/2/2016 - 11/9/2016)

 

Station 860 (segment 548

BH)

 

1,547

 

1,265

 

1,265

 

1,265

 

1,265

 

1,265

 

1,265

 

1,265

 

Sta. 550: Trap Modification (9/15/2016 - 11/8/2016)

 

Station 110 (segment 187

BH) (south thru Kentucky)

 

 

2,363

 

 

2100 (183)

 

 

2100 (183)

 

 

2100 (183)

 

 

2100 (183)

 

 

2100 (183)

 

 

2100 (183)

 

 

2100 (183)

 

 

MLV 96-2B to 100-2 & MLV 100-2 to 102-2: Hydrotest   (7/11/2016 - 11/5/2016) Sta. 96-2D: Unit Maintenance   (10/24/2016 - 11/7/2016)

MLV 200-1S to MLV 106-3: 11/9: ILI/Cleaning Pi (9/27/2016 - 11/8/2016)

 

Station 114 (segment BH)

 

714

 

450 (184)

 

450 (184)

 

450 (184)

 

634

 

634

 

634

 

634

 

MLV 114-3 to 117-3: Emergent Repai (8/24/2016 - 10/31/2016) MLV 121-1 to 122-1: Trap Modifications  (M) (9/7/2016 - 11/23/2016)

 

Station 204 (Segment 204

BH)

 

1,846

 

1670 (176)

 

1800 (46)

 

1800 (46)

 

1800 (46)

 

1800 (46)

 

1800 (46)

 

1800 (46)

 

Sta. 200-1B: Unit Maintenance   (10/25/2016 - 10/29/2016) Sta. 204-7A: Foundation Repai (10/10/2016 - 12/2/2016) Sta. 214-2A: Unit Maintenance   (10/1/2016 - 11/18/2016)

 

Station 237 (segment 237

FH)

 

1,004

 

988

 

988

 

988

 

988

 

988

 

988

 

988

 

 

Station 245 (segment 245

FH)

 

1,014

 

998

 

998

 

998

 

998

 

998

 

998

 

998

 

 

Station 254 (segment 249

FH)

 

1,239

 

1,223

 

1,223

 

1,223

 

960 (263)

 

1,223

 

1,223

 

1,223

 

Sta. 254-2B: Unit Maintenance   (11/1/2016 - 11/1/2016)

 

Station 261 (segment 260

FH)

 

1,121

 

1,110

 

1,110

 

1,110

 

1,110

 

1,110

 

1,110

 

1,110

 

 

Station 307 (segment 307

BH)

 

1,191

 

1,151

 

1,151

 

1,151

 

1,151

 

1,151

 

1,151

 

1,151

 

 

Station 315 (segment 315

BH)

 

1,774

 

1,774

 

1,774

 

1,774

 

1,774

 

1,774

 

1,774

 

1,774

 

 

Sta. 325 (segment 321

FH)

 

1,594

 

1,594

 

1,594

 

1,594

 

1,594

 

1,594

 

1,594

 

1,594

 

Sta. 405

HC Line

(segment 299

FH)

 

829

 

813

 

813

 

813

 

813

 

813

 

813

 

813

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.  Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.


 

 

Outage Capacity Impact Report

November 2016 (updated 10/27/16)

-Major impact restrictions may be necessary

-Minor impact  restrictions may be necessary depending on flow conditions

-Little to no impact,  though minor outages  may cause incremental reductions

 

Station # / Lateral

 

Est Nominal Design Capacit(Thousand Dth)

Week 1 (10/31 - 11/6)

Week 2 (11/7 - 11/13)

Week 3 (11/14 - 11/20)

Week 4 (11/21 - 11/27)

Week 5 (11/28 - 12/4)

 

Primary Outage(s)

Est. Operational Capacity (Operational  Impact) - Thousand Dth

 

Station 409 (Donna Line) (segment 490

FH)

 

541

 

 

541

 

541

 

541

 

541

 

 

Station 1 (segment 409

BH)

 

242

 

 

242

 

242

 

242

 

242

 

 

Station 9 (segment 109

BH)

 

698

 

 

650 (48)

 

698

 

698

 

698

MLV 24-3A to 20-3A: ILI/Cleaning Pig Reru (11/10/2016)

 

Sta. 47 (segment 143

FH)

 

1,652

 

 

1,370

 

1,370

 

1,370

 

1,370

 

 

MLV 843 (segment 834

BH)

 

223

 

 

223

 

223

 

223

 

223

 

 

Station 546 (segment 542

BH)

 

1,504

 

 

1,222

 

1,222

 

1,222

 

1,222

 

MLV 538-1 to 542-1: ILI/Cleaning Pig: 11/2, 11/7 & 11/9  (M) (11/2/2016 - 11/9/2016)

545-1 & 545-2: Meter Install (Hot Taps)   (11/15/2016 - 11/17/2016)

 

Station 860 (segment 548

BH)

 

1,547

 

 

1,265

 

1,265

 

1,265

 

1,265

 

 

Sta. 550: Trap Modification (9/15/2016 - 11/8/2016)

Station 110 (segment 187

BH) (south thru Kentucky)

 

2,363

 

 

1850 (433)

 

1800 (483)

 

2,283

 

2,283

Sta. 87: ESD Test   (11/16/2016 - 11/16/2016)

Sta. 87-2C, 3C, 4C & 5C: Unit Maintenance   (11/7/2016 - 12/15/2016) Sta. 96-2D: Unit Maintenance   (10/24/2016 - 11/7/2016)

MLV 200-1S to MLV 106-3: ILI/Cleaning Pig: 11/ (9/27/2016 - 11/8/2016)

MLV 106-4D to 200-2S ILI/Cleaning Pig: 11/10, 11/15 & 11/1 (11/10-2016 - 11/17/2016)

 

Station 114 (segment BH)

 

714

 

 

350 (284)

 

634

 

634

 

634

 

MLV 121-1 to 122-1: Trap Modifications  (M) (9/7/2016 - 11/23/2016)

MLV 121-2A to 114-3: ILI/Cleaning Pig: 11/5 & 11/ (11/5/2016 - 11/7/2016)

 

Station 204 (Segment 204

BH)

 

1,846

 

 

1800 (46)

 

1420 (426)

 

1800 (46)

 

1800 (46)

 

Sta 204: Station Outag (11/15/2016 - 11/18/2016) Sta. 204-7A: Foundation Repai (10/10/2016 - 12/2/2016) Sta. 214: Station Outag (11/15/2016 - 11/20/2016)

Sta. 214-2A: Unit Maintenance   (10/1/2016 - 11/18/2016)

 

Station 237 (segment 237

FH)

 

1,004

 

 

988

 

988

 

988

 

988

 

 

Station 245 (segment 245

FH)

 

1,014

 

 

998

 

998

 

998

 

998

 

 

Sta 241-2A: Unit Maintenance   (11/7/2016 - 11/9/2016)

 

Station 254 (segment 249

FH)

 

1,239

 

 

1,223

 

1,223

 

1,223

 

1,223

 

 

Station 261 (segment 260

FH)

 

1,121

 

 

1,110

 

1,110

 

1,110

 

1,110

 

 

Station 307 (segment 307

BH)

 

1,191

 

 

1,151

 

1,151

 

1,151

 

1,151

 

 

Station 315 (segment 315

BH)

 

1,774

 

 

1,774

 

1,774

 

1,774

 

1,774

 

 

Sta. 325 (segment 321

FH)

 

1,594

 

 

1,594

 

1,594

 

1,594

 

1,594

 

 

Sta. 405

HC Line

(segment 299

FH)

 

829

 

 

813

 

813

 

813

 

813

 

This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.  Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.

 

..