October 27, 2016
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2016 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***Sta. 25-2D: Unit Maintenance
***Completed
………………………………"
"***Bear Creek: Storage
"***Sta. 96: ESD Test
"***MLV 105-2L (Begin Loop) to 106-2S: 9/8,9/13 & 10/4: ILI/Cleaning Pig
"***MLV 121-2 to 122-2: Trap Modifications
The following meters are available for nominations:
420044 – DOMINION/TGP BORAD RUN CORNWELL KAN
"***Sta. 200-10A & 5A: Unit Maintenance
"***Sta. 214-11A: Unit Maintenance
"***241-3A,1B,2B: Control Panel Replacement
"***Sta. 261-1D,1C & 5A: Water Wash
"***Sta. 325-3A: Unit Maintenance
"***MLV 534-1A to 538-1: ILI/Cleaning Pig: 10/4, 10/6 & 10/21
• 412612 – TEXLA/TGP BEI WALKER 1-8 JONES
• 420714 – CPTENTEX/TGP LAUREL SALES JONES
• 420726 - CPTENTEX/TGP LAUREL SALES 2 JONES
"***Sta. 542-1A: Unit Maintenance
100 Line Outages
"Sta 9: Unit Work
--3/19/16 through 8/31/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 17: Station Reversal
--5/31/16 through 5/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 24-3 to MLV 20-3A: ILI/Cleaning Pig
--11/10/16 through 11/10/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Added
"MLV 25-2BR to 26-2: Hydrotest
--9/21/16 through 11/5/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 36-3 to 38-3: Hydrotest
--10/12/16 through 11/19/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 40-1S, 2S, 3S & 4S: Hydrotest
--8/1/16 through 11/10/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 54-3D to 56-3: Hydrotest
--10/3/16 through 11/23/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The listed meters will be shut-in for approximately eight hours during the scheduled dates listed below. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412586 - ANR/TGP GREENVILLE
420941 - ANR/TGP GREENVILLE
"MLV 54-3A: New MLV Install
--10/3/16 through 12/9/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 60-4 to 63-4: Hydrotest
--10/31/16 through 12/5/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 62-2 to 63-2: Hydrotest
--10/17/16 through 11/17/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 63: A Building Classification Project
--9/19/16 through 10/31/16: This project will require a bulding outage, which will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 63: B Building Classification Project
--10/10/16 through 11/23/16: This project will require a bulding outage, which will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 71-1 to 77-1A: Anomaly Remediation
--9/12/16 through 11/15/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in for the entire length of the outage. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420761 - D2ENERGY/TGP ADAMSVILLE TN MC NAIRY
"Station 79: Station Reversal
--1/1/17 through 12/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 82-3C to 87-3: ILI/Cleaning Pig 11/14 & 11/16
--11/28/16 through 12/1/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 11/14/16 to 11/16/16.
"Sta. 87: ESD Test
--11/16/16 through 11/16/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 96-1D: Unit Maintenance
--10/10/16 through 10/21/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 96-2B to 100-2 & MLV 100-2 to 102-2: Hydrotest
--7/11/16 through 11/5/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 96-2D: Unit Maintenance
--10/24/16 through 11/7/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***MLV 106-4D to 200-2S: ILI/Cleaning Pig: 11/10, 11/15 & 11/17
--11/10/16 through 11/17/16: This outage will require the pipeline to be taken out of service. For the duration of the project, TGP will only be able to deliver gas to the listed meter. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date Change, Previously scheduled 12/31/16.
"***MLV 121-1 to 122-1: Trap Modifications
--9/7/16 through 11/23/16: This outage will require the pipeline to be taken out of service. For the duration of the project, TGP will only be able to receive gas from the listed meter. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420044 - DOMINION/TGP BROAD RUN CORNWELL KAN
***Date Change, Previously scheduled 9/7/16 to 10/30/16.
"***MLV 121-2A to 114-3: ILI/Cleaning Pig: 11/5 & 11/7
--11/5/16 through 11/7/16: This outage will require the pipeline to be taken out of service. For the duration of the project, TGP will only be able to deliver gas to the listed meter. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date Change, Previously scheduled 11/9/16.
200 Line Outages
"***MLV 200-1S to MLV 106-3: 11/8: ILI/Cleaning Pig
--9/27/16 through 11/8/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date Change, Previously scheduled 9/27/16 to 11/9/16.
"Sta. 200-1B: Unit Maintenance
--10/25/16 through 10/29/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta 204: Station Outage
--11/15/16 through 11/18/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 204-10A: Unit Maintenance
--10/24/16 through 10/28/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 204-7A: Foundation Repair
--10/10/16 through 12/2/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 214: Station Outage
--11/15/16 through 11/20/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 214-2A: Unit Maintenance
--10/1/16 through 11/18/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 237: ESD Test
--10/28/16 through 10/28/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 10/25/16 to 10/25/16.
"***Sta 241-2A: Unit Maintenance
--11/7/16 through 11/9/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 251-2 & 251-3: Tie-In
--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 251-1 & 251-3: Tie-In
--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 254-2B: Unit Maintenance
--11/1/16 through 11/1/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP)
***Date Change, Previously scheduled 10/26/16 to 10/26/16.
"MLV 257-3: Tie-In
"MLV 260-1 to 261-1: Line Tie-Ins
"MLV 260-1 to 261-1A: Tie-In
"MLV 261-1 to 261-1A: Line Tie-Ins
"MLV 261-1 to 261-1A: Tie-In
"Sta. 265E: Station Maintenance
--11/5/16 through 11/12/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
300 Line Outages
"Sta. 307-1 to Sta. 219-1: Efficiency Pigging
-(November/December 2017 – Exact Dates TBD): This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations. The listed meters will be shut-in during the pig run only. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420730 - NFG/TGP CRANBERRY SMS VENAGO
"Sta. 307-2 to Sta. 219-2: Efficiency Pigging
-(November/December 2017 – Exact Dates TBD): This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 313: Hot Tap
--10/29/16 through 10/31/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Ellisburg Storage: Storage
--10/31/16 through 11/4/16: This project will require a storage outage, which will limit throughput and may result in restrictions based on customer nominations.
"Sta. 317: Ancillary Piping Relocation
--12/10/16 through 12/12/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Sta. 323-1A: Unit Maintenance
--9/12/16 through 10/28/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/12/16 to 10/31/16.
"MLV 333A-100: Hydrotest
--10/18/16 through 10/26/16: This project will require taking the pipeline section out of service. The listed meter will be shut-in for the entire length of the outage. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420477 - CON ED/TGP KNOLLWOOD NY WESTCHESTER
"345A-101: DERBY DELIVERY LINE ECDA
--10/20/16 through 10/27/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 354-1: Tie-In
500 Line Outages
"MLV 355-1: Tie-In
--4/1/17 through 9/30/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 513-1: Pipe Replacement
--10/19/16 through 10/28/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 10/19/16 to 10/29/16.
"Meter 420291: Meter Maintenance
--10/25/16 through 10/25/16: This activity will require a meter station outage. The listed meter below will be shut-in for the entire duration of the outage. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
TGP Transco Heidelberg (020291)
"***MLV 538-1 to 542-1: ILI/Cleaning Pig: 11/2, 11/7 & 11/9
--12/8/16 through 12/15/16: This activity will require operating at controlled flow rates. The meters listed below will be shut-in for a couple of hours until the pig passes. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420807 – ATMOS-MS/TGP PINE SPRINGS ROAD LEAK
420291 – TRNSCO/TGP HEIDELBERG MISSISSIPPI JA
412060 – AMMID MD/TGP UDP HEIDELBURG TRANSPO
***Date Change, Previously scheduled 11/2/16 to 11/9/16.
"545-1 & 545-2: Meter Install (Hot Taps)
--11/15/16 through 11/17/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 550: Trap Modifications
--9/15/16 through 11/8/16: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/15/16 to 10/28/16.
800 Line Outages
"***820-1 & 821-1: Pipe Painting
--9/21/16 through 11/1/16: This project involves inspecting and making repairs at multiple pipeline sites within the noted valve sections. We anticipate being able to make repairs while the line is in-service; however, there is a potential that the pipe repair may require replacement. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412013 ENTRPRSE/TGP SABINE RIVER TRANS NEW
412737 LBERTYGS/TGP UDP DE QUINCY GAS STOR
420581 VARIBUS/TGP BECKWITH CREEK CALCASIE
401366 TRNSCO/TGP UDP UTOS EXCH CAMERON
412015 HEC/TGP STARKS HANKAMER 1 CALCASIE
412461 NEUMIN/TGP NEUMIN DEHYDRATION CALCA
412690 HPL/TGP SABINE NEWTON
412768 GLDNPASS/TGP STARKS LNG: RIP 820 10
412839 DUNCAN/TGP LABOKAY NO. 1: RIP 820P
420550 ENTRPRSE/TGP SABINE RIVER (1 6179
412597 COKINOS/TGP TEMPLE INLAND NO 1 CALC
411211 Starks Louisiana Transport
412493 Lawthon Dehyd
412717 Burlington (Duncan)
***Date Change, Previously scheduled 9/21/16 to 10/29/16.
"***MLV 821-1: Pipe Replacement
--9/14/16 through 11/1/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in for the entire length of the outage. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
The outage mentioned above will sever TGP 800-1 line (segment 820). The meters listed below are located upstream of the outage, however, they will be isolated from the remainder of the TGP System. For this reason, scheduled receipt volumes must equal scheduled delivery volumes in this area.
412690 – HPL/TGP Sabine Newton
412013 – Enterprise/TGP Sabine River
411586 TRNSCO/TGP STARKS LA TRANSPORT CALC
***Date Change, Previously scheduled 9/14/16 to 11/5/16.
"Sta 834: Station Outage
--6/1/16 through 9/9/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 871: ESD Test
--10/26/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date Change, Previously scheduled 10/25/16.
If you have any questions, please contact your Scheduler.