DATE: September 26, 2016 TIME: 1:00 PM CCT
TO: ALL TENNESSEE GAS PIPELINE COMPANY CUSTOMERS
RE: RESERVATION OF CAPACITY FOR CONNECTICUT EXPANSION PROJECT -
UPDATE TO JULY 16, 2013 POSTING
Pursuant to Article XXVI, Section 5.8 of the General Terms and Conditions of its FERC Gas Tariff, Tennessee Gas Pipeline Company, L.L.C. ("Tennessee") updates the Reservation of Capacity Postings dated July 16, 2012 and July 16, 2013 for the Connecticut Expansion Project. The July 16, 2013 posting stated that the estimated in-service date for the Connecticut Expansion Project was November 1, 2016. Tennessee is updating the July 16, 2013 posting to revise the estimated in-service date of the Connecticut Expansion Project to November 1, 2017.
As provided in the July 16, 2013 posting, the following capacity is currently reserved for the Connecticut Expansion Project:
· 32,000 Dth/d of capacity from Main Line Valve 249 to Main Line Valve 261, including 32,000 Dth/d at the receipt meter at Wright, New York (412181).
For further information, please contact:
Alison Stringer
(713) 420-5176
Alison_Stringer@KinderMorgan.com
Preston Troutman
(713) 420-3022