Notice Detail
           
Return To Results
TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/25/2016 2:16:30PM Notice End Date/Time:  10/25/2016 9:00:00am
Post Date/Time:  9/24/2016 2:16:30 PM Notice ID: 360929
Reqrd Rsp:  1 Rsp Date:  09/24/2016
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 9-25-16 TIMELY CYCLE
Notice Text:
Effective Timely Cycle (9:00) for the gas day of February 9, 2014

Effective Timely Cycle (9:00) for the gas day of September 25, 2016 Tennessee restricted the following:

 

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO Action Alert for Zones 0, L, 1 and 2 for underdeliveries/ overtakes

OFO Daily Action Alert for Zones 5 and 6 for overdeliveries/undertakes

OFO Monthly Action Alert Zones 5 and 6 for overdeliveries/undertakes

OFO Monthly Action Alert Zone 4 for LMS-PA for overdeliveries

 

RESTRICTIONS

STA 1 M/S (Segment 409 BH) – through approx 41% of SOP due to nominations in excess of operational capacity; 11,356 Dths

 

STA 9 M/S (Segment 109 BH) – through 100% of SOP due to the emergent repair at STA 9; 65,269 Dths

 

MLV 834 M/S (Segment 834 BH) - through approx 21% of SOP due to nominations in excess of operational capacity; 45,500 Dths

 

STA 110 M/S (Segment 187 BH) – through 100% of SOP due to scheduled maintenance; 98 Dths

 

STA 204 M/S (Segment 204 BH) – through 100% of SOP due to scheduled maintenance; 22 Dths

 

STA 224 S/M (Segment 224 FH) / HC Zn 5 S/M (Segment 299 FH) – through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 112,477 Dths

 

STA 245 S/M (Segment 245 FH) – through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 694,378 Dths

 

STA 307 M/S (Segment 307 BH) – through 100% of SOP due to nominations in excess of operational capacity; 839,918 Dths

 

MLV 314 M/S (Segment 314 BH) – through approx 99% of SOP due to nominations in excess of operational capacity; 850,199 Dths

 

STA 315 M/S (Segment 315 BH) – through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 46,540 Dths

 

STA 325 S/M (Segment 321 FH) – through approx 26% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 129,284 Dths

 

Mahwah Delivery Meter (Pin 420207) – through approx 23% of SOP due to nominations in excess of operational capacity; 48,037 Dths

 

LINEPACK RESTRICTIONS

Not accepting PALD or PALAO Parks/Payback to the Pipe System Wide

 

STORAGE RESTRICTIONS

Not accepting IS Injections at Northern (460018) or Portland MA (460025)

Not accepting FS-AO Injections at Northern (460018) or Portland MA (460025)

Not accepting nominations for injections above MDIQ at Northern (460018) or Portland MA (460025)

No transfers will be allowed into TGP ISMA contracts from storage partners at Northern MA (460018)

No transfers from TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA)

Transfers into TGP Bear Creek from SNG Bear Creek will be allowed with partner approvals

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR

CONFIRMATION REDUCTIONS.

 

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND

ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED

SERVICE OUTAGES.

 

If you have any questions, please contact your Scheduler.

 

...