TGP - Outage Impact Report
Seven Day Forecast (updated 09/22/16)
-Major impact restrictions may be necessary
-Minor impact restrictions may be necessary depending on flow conditions
-Little to no impact, though minor outages may cause incremental reductions
Station # / Lateral (FH)=forward haul (BH)=backward haul
Est Nominal Design Capacity (Thousand Dth)
Saturday
(9/24)
Sunday
(9/25)
Monday
(9/26)
Tuesday
(9/27)
Wednesday
(9/28)
Thursday
(9/29)
Friday
(9/30)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Station 409 (Donna Line) (segment 490
FH)
541
MLV 404 (segment 409
BH)
242
180 (62)
MLV 404-2 to 404-2: Hydrotest (9/27/2016 - 10/31/2016)
Station 9 (segment 109
698
580 (118)
430 (268)
MLV 9-1S to 1-1D: xILI/Cleaning Pig: 9/22 & 9/24 (9/22/2016 - 9/24/2016)
9-2 to 10-2: Drip Removal/Hydrotest (8/29/2016 - 9/26/2016) Sta. 9: Emergent Repair (9/25/2016 - 9/26/2016)
Sta. 47 (segment
143 FH)
1,652
1,370
MLV 843 (segment 834
223
Station 546 (segment 542
1,504
1,222
Station 860 (segment 548
1,547
1,265
1200 (65)
Sta. 550: Trap Modifications (9/15/2016 - 10/20/2016) Sta. 555: Valve Replacement (9/28/2016 - 10/5/2016)
Sta. 555-1A & 2A: Unit Maintenance (9/26/2016 - 9/27/2016)
Station 110 (segment 187
BH) (south thru Kentucky)
2,363
2250 (33)
1850 (433)
MLV 96-2B to 100-2 & MLV 100-2 to 102-2: Hydrotest (7/11/2016 - 12/10/2016)
96-3D to 98-3: Spike Test (8/22/2016 - 10/1/2016)
MLV 200-1S to MLV 106-3: ILI/Cleaning Pig (9/27/2016 - 9/27/2016)
Station 114 (segment BH)
714
450 (184)
MLV 114-3 to 117-3: Emergent Repair (8/24/2016 - 10/31/2016) MLV 121-1 to 122-1: Trap Modifications (M) (9/7/2016 - 9/29/2016)
Station 204 (Segment 204
1,846
1746 (146)
1800 (46)
Sta. 200-10A & 5A: Unit Maintenance (9/6/2016 - 10/5/2016) Sta. 200-10A - Emergent Repair (9/8/2016 - 9/24/2016)
Niagra Spur
(segment 296
743
550 (193)
Sta. 229: Jacket Water MCC Replacement (9/13/2016 - 9/26/2016)
Station 224 (Segment 224
FH) / HC Zone 5 (Segment 299
1,194
1094 (100)
Sta. 229: Jacket Water MCC Replacement (9/13/2016 - 9/26/2016) Sta. 405A-1A: Unit Maintenance (9/28/2016 - 9/29/2016)
Station 237 (segment 237
1,004
988
Station 245 (segment 245
1,014
960 (38)
890 (108)
241-3A,1B,2B: Control Panel Replacement (8/15/2016 - 10/21/2016) Sta 241: Control Panel Replacement (9/7/2016 - 10/21/2016)
Sta. 249-1A: Unit Maintenance (9/26/2016 - 9/30/2016)
Station 254 (segment 249
1,239
1,223
Station 261 (segment 260
1,121
1000 (110)
Sta. 261-1C: Control Panel Replacement (9/5/2016 - 10/3/2016)
Station 307 (segment 307
1,191
1,151
Station 315 (segment 315
1,774
1680 (94)
1120 (654)
MLV 313-2A to 315-2: 9/28 & 9/29: ILI/Cleaning Pig (M) (9/28/2016 - 9/29/2016) Sta. 317: Station Maintenance (9/7/2016 - 9/26/2016)
Sta. 325 (segment 321
1,594
1530 (64)
MLV 321-1 to 325-1: Anomaly Inspection (8/24/2016 - 9/30/2016) Sta. 323-1A: Unit Maintenance (9/12/2016 - 10/17/2016)
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
Outage Capacity Impact Report
October 2016 (updated 09/22/16)
Station # / Lateral
Est Nom inal Design Capacity (Thousand Dth)
Week 1 (10/3 - 10/9)
Week 2 (10/10 - 10/16)
Week 3 (10/17 - 10/23)
Week 4 (10/24 - 10/30)
Primary Outage(s)
425
180 (245)
Sta. 47 (segment 143
530-1 to 534-1: ILI Pig (10/1/2016 - 12/31/2016)
MLV 534-1A to 538-1: ILI/Cleaning Pig: date TBD (10/1/2016 - 11/30/2016) MLV 538-1 to 542-1: ILI/Cleaning Pig: date TBD (10/1/2016 - 11/30/2016)
545-1 & 545-2: Meter Install (Hot Taps) (10/24/2016 - 10/30/2016)
MLV 865 (Segment 860
1,759
1,477
2100 (183)
1800 (483)
Sta. 87: ESD Test (10/18/2016 - 10/18/2016)
Sta. 96-1D: Unit Maintenance (10/10/2016 - 10/21/2016)
MLV 96-2B to 100-2 & MLV 100-2 to 102-2: Hydrotest (7/11/2016 - 12/10/2016) Sta. 96-2D: Unit Maintenance (10/24/2016 - 11/7/2016)
Sta. 106-1C: Unit Maintenance (10/3/2016 - 10/7/2016) Sta. 110: Station Outage (10/17/2016 - 10/17/2016)
111-3 to 112-3: Drip Removal (10/18/2016 - 10/24/2016)
380 (254)
Sta. 114: ESD Test (M) (10/12/2016 - 10/12/2016)
MLV 114-3 to 117-3: Emergent Repair (8/24/2016 - 10/31/2016) MLV 121-2 to 122-2: Trap Modifications (M) (10/3/2016 - 10/21/2016)
1550 (296)
1670 (176)
1500 (346)
1820 (26)
Sta. 200-10A & 5A: Unit Maintenance (9/6/2016 - 10/5/2016) Sta. 200-1B: Unit Maintenance (10/6/2016 - 10/13/2016) Sta 204: Station Outage (10/18/2016 - 10/24/2016)
Sta. 209: ESD Test (10/4/2016 - 10/5/2016)
Sta. 214-1A & 2A: Unit Maintenance (10/10/2016 - 10/14/2016) Sta. 214-2A: Unit Maintenance (10/1/2016 - 11/18/2016)
Sta. 237: ESD Test (10/4/2016 - 10/4/2016)
Sta. 237-2A: Unit Maintenance (10/3/2016 - 10/3/2016)
950 (48)
770 (228)
998
Sta. 245-1C: Unit Maintenance (10/10/2016 - 10/14/2016)
MLV 245-2 to MLV 249-2: Maintenance Pig 1 Day TBD (10/17/2016 - 10/21/2016)
700 (410)
1,110
980 (130)
Sta. 261-1D,1C & 5A: Water Wash (10/3/2016 - 10/7/2016) Sta. 261-5A: Boroscope (10/19/2016 - 10/19/2016)
Sta. 261-1C: Boroscope (10/18/2016 - 10/18/2016) Sta. 261-1D: Boroscope (10/17/2016 - 10/17/2016)
Station 261 (segment 261
950
705 (240)
Sta. 264-1C & 2C: Water Wash (10/3/2016 - 10/7/2016) Sta. 264-1C: Boroscope (10/10/2016 - 10/10/2016) Sta. 264-2C: Boroscope (10/11/2016 - 10/11/2016)
540 (611)
302-1 & 302-2: Hot Tap (10/10/2016 - 10/13/2016)
Sta. 307-1 to Sta. 219-1: Efficiency Pigging 1 Day TBD (M) (10/3/2016 - 10/17/2016) Sta. 307-2 to Sta. 219-2: Efficiency Pigging 1 Day TBD (10/3/2016 - 10/17/2016)
Sta. 323-1A: Unit Maintenance (9/12/2016 - 10/17/2016)
Sta. 405
HC Line
(segment 299
829
813