September 22, 2016
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2016 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***MLV 9-1D to 17-1S: ILI/Cleaning Pig: 9/12 & 9/14
***Completed
………………………………"
"***MLV 17-1D to 20-1A: ILI/Cleaning Pig: 9/16 & 9/19
"***MLV 20-3 to 24-3: ILI/Cleaning Pig - 9/13 & 9/15
The following meters are available for nominations:
412485 - GAITHER/TGP UDP TOMBALL MARSHALL
421082 - CEGS/TGP MOORHEAD: DIP 23B 101
"***MLV 87-1D to 96-1S: ILI/Cleaning Pig
"***97-5: Pipe Replacement
"***MLV 213: Hot Taps
"***Sta. 249-2A: Unit Maintenance
"***MLV 264A-101.1 to 264A-101.1: Pipe Inspection
"***MLV 265E-201 to 265E-201: Pipe Inspection
"***Sta. 325: ESD Test
"***Sta. 550: Station Maintenance
100 Line Outages
"***MLV 404-2 to 404-2: Hydrotest
--9/27/16 through 10/31/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date Change, Previously scheduled 9/26/16 to 10/31/16.
"***MLV 9-1S to 1-1D: 9/22 & 9/24: ILI/Cleaning Pig: 9/21 & 9/22
--9/22/16 through 9/24/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/21/16 to 9/23/16.
"Sta 9: Unit Work
--3/19/16 through 8/31/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***9-2 to 10-2: Drip Removal/Hydrotest
--8/29/16 through 9/26/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 8/29/16 to 9/30/16.
"Sta 17: Station Reversal
--5/31/16 through 5/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 25-1D to 32-1S: ILI/Cleaning Pig: 9/27 & 9/29
--9/27/16 through 9/29/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 25-2BR to 26-2: Hydrotest
--9/21/16 through 11/5/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Added
"MLV 29-1 to 31-1: Pressure Weld Replacement
--6/17/16 through 8/26/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
421071 – VART/TGP WOODVILLE PLANT: DIP 30C 10
412632 – ANADARKO/TGP WOODVILLE DEHYD TYLER
"***MLV 29-3 to 31-3: Pipe Replacement
--9/23/16 through 10/1/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/1/16 to 10/1/16.
"***MLV 40-4S: Hydrotest
--8/1/16 through 10/13/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 8/1/16 to 10/1/16.
"MLV 40-4D to 42-4: Anomaly Digs
--9/6/16 through 9/30/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Bear Creek: Storage
--10/18/16 through 10/24/16: This project will require a storage outage, which will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 54-3D to 56-3: Hydrotest
--10/3/16 through 11/23/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. The listed meters will be shut-in for approximately eight hours during the scheduled dates listed below. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
10/3/2016 & 11/23/2016
412586 - ANR/TGP GREENVILLE
420941 - ANR/TGP GREENVILLE
***Meters Added.
"MLV 54-3A: New MLV Install
--10/3/16 through 12/9/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"54-2D to 63-2S: Anomaly Remediation
--6/22/16 through 7/2/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 71-1 to 77-1A: Anomaly Remediation
--9/12/16 through 11/15/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in for the entire length of the outage. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420761 - D2ENERGY/TGP ADAMSVILLE TN MC NAIRY
"Station 79: Station Reversal
--1/1/17 through 12/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 84-1 to 85-1: Line Outage
--8/2/16 through 8/13/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 87: ESD Test
--10/18/16 through 10/18/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 87-2C: Unit Maintenance
--9/12/16 through 9/16/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Sta. 96-1D: Unit Maintenance
--10/10/16 through 10/21/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 96-2B to 100-2 & MLV 100-2 to 102-2: Hydrotest
--7/11/16 through 12/10/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 96-2D: Unit Maintenance
--10/24/16 through 11/7/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"96-3D to 98-3: Spike Test
--8/22/16 through 10/1/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 105-2L (Begin Loop) to 106-2S: 9/8,9/13 & 9/16: ILI/Cleaning Pig
--9/8/16 through 9/16/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 110: Station Outage
--10/17/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 114: ESD Test
--10/12/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420924 Riverside/Lawrence
"***MLV 121-1 to 122-1: Trap Modifications
--9/7/16 through 9/29/16: This outage will require the pipeline to be taken out of service. For the duration of the project, TGP will only be able to receive gas from the listed meter. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420044 - DOMINION/TGP BROAD RUN CORNWELL KAN
***Date Change, Previously scheduled 9/7/16 to 9/23/16.
"MLV 121-2 to 122-2: Trap Modifications
--10/3/16 through 10/21/16: This outage will require the pipeline to be taken out of service. For the duration of the project, TGP will only be able to deliver gas to the listed meter. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420044 – DOMINION/TGP BROAD RUN CORNWELL KAN
200 Line Outages
"Sta. 200-10A & 5A: Unit Maintenance
--9/6/16 through 10/5/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***MLV 200-1S to MLV 106-3: ILI/Cleaning Pig
--9/27/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 200-1B: Unit Maintenance
--10/6/16 through 10/13/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta 204: Station Outage
--10/18/16 through 10/24/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Sta. 209: ESD Test
--10/4/16 through 10/5/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 214-1A & 2A: Unit Maintenance
--10/10/16 through 10/14/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 214-2A: Unit Maintenance
--10/1/16 through 11/18/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 229: Station Outage
--9/13/16 through 9/26/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"241-3A,1B,2B: Control Panel Replacement
--8/15/16 through 10/21/16: This project will require a station and unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 241: Control Panel Replacement
--9/7/16 through 10/21/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 245-1 to MLV 249-1: Maintenance Pig
--9/19/16 through 9/23/16: This activity will require operating at controlled flow rates for 1 day during the month of September. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 245-1C: Unit Maintenance
"MLV 245-2 to MLV 249-2: Maintenance Pig
--10/17/16 through 10/21/16: This activity will require operating at controlled flow rates for 1 day during the month of September. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 251-2 & 251-3: Tie-In
--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 251-1 & 251-3: Tie-In
--(2nd/3rd Qtr. 2017 – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 257-3: Tie-In
"MLV 260-1 to 261-1 : Line Tie-Ins
"MLV 260-1 to 261-1A: Tie-In
"Sta. 261-1D,1C & 5A: Water Wash
--10/3/16 through 10/7/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 261-1 to 261-1A: Line Tie-Ins
"Sta. 261-5A: Boroscope
--10/19/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 261-1C: Boroscope
--10/18/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 261-1D: Boroscope
--10/17/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 261-1C: Control Panel Replacement
--9/5/16 through 10/3/16: This project will require an unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 261: Block Valve Installation
--9/15/16 through 9/23/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. During the outage the listed meter below may experience lower than normal pressures. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/15/16 to 9/22/16.
"MLV 261-1 to 261-1A: Tie-In
--4/1/17 through 9/30/17: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 264-1C & 2C: Water Wash
"Sta. 264-1C: Boroscope
--10/10/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 264-2C: Boroscope
--10/11/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 265E: Station Maintenance
--11/5/16 through 11/12/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 266A: Unit Maintenance
--9/12/16 through 9/16/16: This project will require a unit outage, which will limit throughput through the station and may result in restrictions based on customer nominations. The meter listed below will be limited to 150,000 dth/day of deliverability during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP,SIP) nominations.
"Sta. 266A: Station Maintenance
--9/14/16 through 9/15/16: This project will require a station outage (estimated 12 hrs per day), which will limit throughput through the station and may result in restrictions based on customer nominations. The meter listed below will be limited to 75,000 dth/day of deliverability during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP,SIP) nominations.
420285 – AGT/TGP MENDON MASS TIE OVER WORCHE
"***Sta. 267: Block Valve Installation
--9/23/16 through 10/4/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/23/16 to 9/30/16.
300 Line Outages
"302-1 & 302-2: Hot Tap
--10/10/16 through 10/13/16: This outage will require pressure reductions and possibly line isolations. Outage will take approximately 2 weeks within this time frame. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 303-1A: Unit Maintenance
--8/28/16 through 8/29/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 307-1 to Sta. 219-1: Efficiency Pigging
--10/3/16 through 10/17/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations. The listed meters will be shut-in during the pig run only. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420730 - NFG/TGP CRANBERRY SMS VENAGO
"Sta. 307-2 to Sta. 219-2: Efficiency Pigging
--10/3/16 through 10/17/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Sta. 307-6A: Unit Maintenance
--9/19/16 through 9/22/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Sta. 405A-1A: Unit Maintenance
--9/28/16 through 9/29/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Harrison Storage: Storage
--10/10/16 through 10/14/16: This project will require a storage outage, which will limit throughput and may result in restrictions based on customer nominations.
"Ellisburg Storage: Storage
--10/31/16 through 11/4/16: This project will require a storage outage, which will limit throughput and may result in restrictions based on customer nominations.
"MLV 313-2A to 315-2: 9/28 & 9/29: ILI/Cleaning Pig
--9/28/16 through 9/29/16: This activity will require operating at controlled flow rates. The listed meters may be required to reduce their flows depending on the current system conditions. Customers may experience pressure fluctuations, however, no other service impact is antic Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420253 UGICNTRP/TGP WELLSBORO PA TIOGA
420914 DOMINION/TGP SABINSVILLE DELIVERY T
"***Sta. 317: Station Maintenance
--9/7/16 through 9/26/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/7/16 to 9/20/16.
"Sta. 323-1A: Unit Maintenance
--9/12/16 through 10/17/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 333A-100: Hydrotest
--10/18/16 through 10/26/16: This project will require taking the pipeline section out of service. The listed meter will be shut-in for the entire length of the outage. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420477 - CON ED/TGP KNOLLWOOD NY WESTCHESTER
"340A-101.1: ECDA
--9/19/16 through 9/30/16: We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"343A-100: Pressure Test
--7/8/16 through 8/31/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in for the entire length of the outage. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
The only meter that will be impacted (shut-in) the Bridgeport Meter (420126) MORTIMER
"***345A-101: DERBY DELIVERY LINE ECDA
--10/11/16 through 10/21/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/19/16 to 9/30/16.
"MLV 354-1: Tie-In
"MLV 355-1: Tie-In
500 Line Outages
"MLV 513-1: Pipe Replacement
--10/17/16 through 11/3/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 534-1A to 538-1: ILI/Cleaning Pig: (October/November Timeframe)
--10/1/16 through 11/30/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 538-1 to 542-1: ILI/Cleaning Pig: (October/November Timeframe)
"Sta. 542-1A: Unit Maintenance
--6/16/16 through 7/15/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"545-1 & 545-2: Meter Install (Hot Taps)
--10/24/16 through 10/30/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 546: Filter Change
--9/12/16 through 9/14/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 550: Trap Modifications
--9/15/16 through 10/20/16: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 555: Valve Replacement
--9/28/16 through 10/5/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
800 Line Outages
"820-1 & 821-1: Pipe Painting
--9/21/16 through 10/21/16: This project involves inspecting and making repairs at multiple pipeline sites within the noted valve sections. We anticipate being able to make repairs while the line is in-service; however, there is a potential that the pipe repair may require replacement. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412013 ENTRPRSE/TGP SABINE RIVER TRANS NEW
412737 LBERTYGS/TGP UDP DE QUINCY GAS STOR
420581 VARIBUS/TGP BECKWITH CREEK CALCASIE
401366 TRNSCO/TGP UDP UTOS EXCH CAMERON
412015 HEC/TGP STARKS HANKAMER 1 CALCASIE
412461 NEUMIN/TGP NEUMIN DEHYDRATION CALCA
412690 HPL/TGP SABINE NEWTON
412768 GLDNPASS/TGP STARKS LNG: RIP 820 10
412839 DUNCAN/TGP LABOKAY NO. 1: RIP 820P
420550 ENTRPRSE/TGP SABINE RIVER (1 6179
412597 COKINOS/TGP TEMPLE INLAND NO 1 CALC
411211 Starks Louisiana Transport
412493 Lawthon Dehyd
412717 Burlington (Duncan)
"MLV 821-1: Pipe Replacement
--9/14/16 through 11/1/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in for the entire length of the outage. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
The outage mentioned above will sever TGP 800-1 line (segment 820). The meters listed below are located upstream of the outage, however, they will be isolated from the remainder of the TGP System. For this reason, scheduled receipt volumes must equal scheduled delivery volumes in this area.
412690 – HPL/TGP Sabine Newton
412013 – Enterprise/TGP Sabine River
411586 TRNSCO/TGP STARKS LA TRANSPORT CALC
"***Sta. 823: Station Outage
--9/12/16 through 9/26/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. The listed meters may be impacted as a result of higher than normal pressures on TGP's system. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
450303 - TGP/TGP GRAND CHENIER STRADDLE PLAN
***Date Change, Previously scheduled 9/12/16 to 9/22/16.
"Sta 834: Station Outage
--6/1/16 through 9/9/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
If you have any questions, please contact your Scheduler.