TGP - Outage Impact Report
Seven Day Forecast (updated 06/23/16)
-Major impact restrictions may be necessary
-Minor impact restrictions may be necessary depending on flow conditions
-Little to no impact, though minor outages may cause incremental reductions
Station # / Lateral (FH)=forward haul (BH)=backward haul
Est Nominal Design Capacity (Thousand Dth)
Saturday
(6/25)
Sunday
(6/26)
Monday
(6/27)
Tuesday
(6/28)
Wednesday
(6/29)
Thursday
(6/30)
Friday
(7/1)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Station 409 (Donna Line) (segment 490
FH)
541
Station 1 (segment 409
BH)
242
Station 9 (segment 109
698
620 (78)
Sta 9: Unit Work (3/19/2016 - 6/30/2016)
10-2 to 12-2: Spike Test (M) (6/6/2016 - 8/1/2016)
Sta. 47 (segment
143 FH)
1,652
1,370
MLV 843 (segment 834
223
Station 546 (segment 542
1,545
1050 (213)
Sta. 542-1A: Unit Maintenance (6/16/2016 - 7/15/2016) Sta. 542-2A: Unit Maintenance (6/16/2016 - 8/31/2016) Sta. 542: Trap Modifications (7/1/2016 - 8/15/2016)
545-1 & 545-2: Meter Install (Hot Taps) (6/1/2016 - 6/30/2016)
MLV 555 (segment 548
1,588
1260 (46)
1220 (86)
Sta. 860 -7A, 8A, 9A & 10A: Unit Maintenance (6/6/2016 - 7/3/2016) Sta. 860: ESD (6/29/2016 - 6/29/2016)
MLV 865 (Segment 860
1,801
1120 (399)
1,519
Sta 87: Hydrotest (M) (5/25/2016 - 6/27/2016)
Station 110 (segment 187
BH) (south thru Kentucky)
2,363
2000 (118)
96-3D to 98-3: Spike Test (6/27/2016 - 8/6/2016)
96-5D to 98-5: Spike Test (6/1/2016 - 7/22/2016)
97-5: Pipe Replacement (6/1/2016 - 7/22/2016)
Station 114 (segment BH)
714
649
Station 204 (Segment 204
1,846
1520 (146)
209-13A: Unit Work (8/10/2015 - 8/15/2016)
Station 237 (segment 237
1,021
820 (185)
1,005
Sta 237: Control Panel Replacement (5/18/2016 - 7/15/2016)
237-3A: Control Panel Replacement (5/2/2016 - 6/27/2016)
Station 245 (segment 245
1,030
1,015
820 (195)
Sta. 241: ESD Test (6/28/2016 - 6/30/2016)
Station 254 (segment 249
1,239
1,223
950 (273)
254-1 to 261-1: 6/16, 6/21, 6/24 & 6/28: ILI Pig (6/16/2016 - 6/28/2016)
Station 261 (segment 260
1,136
1,125
Station 307 (segment 307
1,191
1,011
Station 315 (segment 315
1,774
1650 (124)
1350 (424)
Sta. 315-1B: Unit Maintenance (6/27/2016 - 6/28/2016)
317-1 to 313-1: ILI Pig Run (6/28/2016 - 6/28/2016)
Sta. 325 (segment 321
1,617
Sta. 405
HC Line
(segment 299
829
813
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report. The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
Outage Capacity Impact Report
July 2016 (updated 06/23/16)
Station # / Lateral
Week 1 (7/4 - 7/10)
Week 2 (7/11 - 7/17)
Week 3 (7/18 - 7/24)
Week 4 (7/25 - 7/31)
Primary Outage(s)
550 (148)
Sta. 47 (segment 143
1180 (83)
1,306
1210 (96)
Sta. 550: Station Maintenance (7/11/2016 - 7/15/2016)
1600 (518)
MLV 871-1 to 866-1: ILI Cleaning Pig (7/12/2016 - 7/12/2016)
876-1 to 871-1: ILI Pig: 7/19 & 7/26 (7/19/2016 - 7/26/2016)
871-2 to 873-2A: 7/27 & 8/2: ILI Pig (7/27/2016 - 8/2/2016)
MLV 200-3B to 204-3: Anomaly Remediation (7/12/2016 - 7/29/2016)
1500 (117)
325-1 to 329-1: Anomaly Remediation (7/11/2016 - 8/1/2016)
August 2016 (updated 06/23/16)
Week 1 (8/1 - 8/7)
Week 2 (8/8 - 8/14)
Week 3 (8/15 - 8/21)
Week 4 (8/22 - 8/28)
Week 5 (8/29 - 9/4)
MLV 534-1A to 538-1: ILI/Cleaning Pig: 8/16, 8/17, 8/18 & 8/22 (8/16/2016 - 8/22/2016) MLV 538-1 to 542-1: ILI/Cleaning Pig: 8/23, 8/24, 8/25 & 8/29 (8/23/2016 - 8/29/2016) Sta. 542-2A: Unit Maintenance (6/16/2016 - 8/31/2016)
Sta. 542: Trap Modifications (7/1/2016 - 8/15/2016)
1300 (6)
1270 (36)
Sta. 546: Trap Modifications (8/15/2016 - 9/30/2016) Sta. 555: Valve Replacement (9/1/2016 - 9/30/2016)
2150 (133)
MLV 87-1D to 96-1S: ILI/Cleaning Pig (8/24/2016 - 8/30/2016) MLV 96-4D to 98-4D: Hydrotest (8/8/2016 - 9/17/2016)
111-3 to 112-3: Drip Removal (8/1/2016 - 10/31/2016)
634
1700 (146)
1580 (266)
MLV 213: Hot Taps - 2 days TBD (8/15/2016 - 9/15/2016)
960 (55)
770 (245)
241-3A,1B,2B: Control Panel Replacement (8/15/2016 - 10/31/2016) Sta. 241-2B: Unit Maintenance (8/15/2016 - 9/30/2016)
MLV 245-1 to MLV 249-1: Maintenance Pig (9/1/2016 - 9/30/2016) MLV 245-2 to MLV 249-2: Maintenance Pig (9/1/2016 - 9/30/2016)
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this report.
The impacts forecasted on this sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
September 2016 (updated 06/23/16)
Week 1 (9/5 - 9/11)
Week 2 (9/12 - 9/18)
Week 3 (9/19 - 9/25)
Week 4 (9/26 - 10/2)
359 (182)
MLV 404-2 to 404-2: Hydrotest (9/19/2016 - 10/31/2016) MLV 402-2 to 402-2: Hydrotest (9/19/2016 - 10/31/2016)
60 (182)
600 (98)
MLV 9-1D to 17-1S: ILI/Cleaning Pig: 9/12 & 9/14 (9/12/2016 - 9/14/2016)
1,263
Sta. 546: Trap Modifications (8/15/2016 - 9/30/2016) Sta. 550: Trap Modifications (9/15/2016 - 11/15/2016) Sta. 555: Valve Replacement (9/1/2016 - 9/30/2016)
MLV 96-2B to 100-2 & MLV 100-2 to 102-2: Hydrotest (9/17/2016 - 11/19/2016) MLV 96-4D to 98-4D: Hydrotest (8/8/2016 - 9/17/2016)
MLV 105-2L (Begin Loop) to 106-2S: ILI/Cleaning Pig (9/13/2016 - 9/16/2016)
MLV 121-1 to 122-1: Trap Modifications (9/5/2016 - 9/23/2016)
241-3A,1B,2B: Control Panel Replacement (8/15/2016 - 10/31/2016) Sta 241: Control Panel Replacement (9/7/2016 - 10/7/2016)
Sta. 241-2B: Unit Maintenance (8/15/2016 - 9/30/2016)
830 (181)
302-1 & 302-2: Hot Tap - 2 days TBD - (9/1/2016- 9/30/2016)