June 23, 2016
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2016 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***MLV 82-3C to 87-3S: ILI/Cleaning Pig
***Completed
………………………………"
100 Line Outages
"MLV 404-2 to 404-2: Hydrotest
--9/19/16 through 10/31/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 402-2 to 402-2: Hydrotest
"MLV 1-1D to 9-1S: ILI/Cleaning Pig: 9/7 & 9/9
--9/7/16 through 9/9/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta 9: Unit Work
--3/19/16 through 7/31/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 3/19/16 to 6/30/16.
"9-1 to 10-1: Drip Removal
--8/1/16 through 10/31/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 9-1D to 17-1S: ILI/Cleaning Pig: 9/12 & 9/14
--9/12/16 through 9/14/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"9-2 to 10-2: Drip Removal
"9-3 to 10-3: Drip Removal
"10-2 to 12-2: Spike Test
--6/6/16 through 8/1/16: This project will require taking the pipeline section out of service. The listed meter will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
412878 BRDWLK/TGP FLAG CITY: RIP 11J 101.2
"Sta 17: Station Reversal
--5/31/16 through 8/31/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 17-1D to 20-1A: ILI/Cleaning Pig: 9/16 & 9/19
--9/16/16 through 9/19/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 9/1/16 to 9/30/16.
"MLV 17-4: Pipe Replacement
--7/11/16 through 8/13/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"19-2: Pipe Replacement
--6/9/16 through 7/6/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"19-3: Pipe Replacement
--7/6/16 through 8/1/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
421085 Centerpoint/Love's Truckstop
"MLV 24-1A to 25-1S: ILI/Cleaning Pig: 9/21 & 9/22
--9/21/16 through 9/22/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 25: Station Reversal
--2/22/16 through 5/31/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 25-1D to 32-1S: ILI/Cleaning Pig: 9/27 & 9/29
--9/27/16 through 9/29/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 25-4: Hydrotest
--8/15/16 through 9/17/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"28-3: Hydrotest
--5/16/16 through 7/9/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412738 TECOGATH/TGP TECO INDIAN SPRINGS PO
"MLV 29-1 to 31-1: Pressure Weld Replacement
--6/17/16 through 8/26/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
421071 – VART/TGP WOODVILLE PLANT: DIP 30C 10
412632 – ANADARKO/TGP WOODVILLE DEHYD TYLER
"Sta 40: Station Reversal
--7/1/16 through 7/22/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 40-4S: Hydrotest
--8/1/16 through 9/3/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in during this time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 42-4 to 43-4: Anomaly Remediation
--7/25/16 through 7/31/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Added
"***MLV 43-4 to 44-4: Anomaly Remediation
--8/1/16 through 8/14/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 47: Station Reversal
--5/23/16 through 9/1/16: This project will require building outages, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Bear Creek: Storage
--10/18/16 through 10/24/16: This project will require a storage outage, which will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"47-2A: Tap Relocation
--5/23/16 through 6/16/16: This project will require pressure reductions. The listed meters will be shut-in for approximately eight hours within the scheduled time frames listed below. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
5/23/16 – 5/27/16
421062 - ENTRGYLA/TGPPERRYVILLEPOWEROUACHITA
6/16/16
"***47-3D to 50-3: Pipe Outage
--5/16/16 through 7/7/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 5/16/16 to 6/30/16.
"***MLV 54-3D to 56-4: Hydrotest
--10/3/16 through 11/23/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Other Change
"54-2D to 63-2S: Anomaly Remediation
--6/22/16 through 7/2/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"54-4D to 63-4S: Anomaly Remediation
--6/11/16 through 6/21/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"58-3: Hydrotest
--5/9/16 through 7/9/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"60-3: Hydrotest
--5/16/16 through 7/9/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***63-2D to 69-2: 5/16, 8/16 & 8/18: ILI Pig
--5/16/16 through 8/18/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 5/16/16 to 7/21/16.
"MLV 78-2: Pipe Replacement
--8/22/16 through 9/1/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
There are two taps in this section: Lick Creek Meter Station and Lobelville Sales Meter Station, but operations has informed me that they are tapped on lines 1 and 2.
"Station 79: Station Reversal
--1/1/17 through 12/31/17: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"82-2C to 87-2S: Anomaly Remediation
--4/18/16 through 6/29/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 82-2C to 87-2: ILI/Cleaning Pig
--7/21/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta 87: Hydrotest
--5/25/16 through 6/27/16: This project will require taking pipeline sections out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date Change, Previously scheduled 5/25/16 to 6/24/16.
"MLV 87-1D to 96-1S: ILI/Cleaning Pig
--8/24/16 through 8/30/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 96-2B to 100-2 & MLV 100-2 to 102-2: Hydrotest
--9/17/16 through 11/19/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 96-4D to 98-4D: Hydrotest
--8/8/16 through 9/17/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"96-3D to 98-3: Spike Test
--6/27/16 through 8/6/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"97-5: Pipe Replacement
--6/1/16 through 7/22/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"96-5D to 98-5: Spike Test
--6/1/16 through 7/22/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 105-2L (Begin Loop) to 106-2S: ILI/Cleaning Pig
--9/13/16 through 9/16/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 114: ESD Test
--(October Timeframe – Exact Dates TBD):: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420924 Riverside/Lawrence
***Date Change, Previously scheduled 7/12/16 to 7/13/16.
"***MLV 121-1 to 122-1: Trap Modifications
--9/5/16 through 9/23/16: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 121-2 to 122-2: Trap Modifications
--10/3/16 through 10/21/16: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
200 Line Outages
"MLV 200-3B to 204-3: Anomaly Remediation
--7/12/16 through 7/29/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 204: Station Outage
--10/3/16 through 10/17/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"209-13A: Unit Work
--8/10/15 through 8/15/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***MLV 213: Hot Taps
--(August/September Timeframe – Exact Dates TBD): This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 7/1/16 to 7/31/16.
"Sta 229: Station Outage
--9/13/16 through 9/26/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"237-1A,2A: Control Panel Replacement
--5/18/16 through 7/15/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"237-3A: Control Panel Replacement
--5/2/16 through 6/27/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 241: ESD Test
--6/28/16 through 6/30/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"241-3A,1B,2B: Control Panel Replacement
--8/15/16 through 10/31/16: This project will require a station and unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 241: Control Panel Replacement
--9/7/16 through 10/7/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 241-2B: Unit Maintenance
--8/15/16 through 9/30/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 245-1 to MLV 249-1: Maintenance Pig
--9/1/16 through 9/30/16: This activity will require operating at controlled flow rates for 1 day during the month of September. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 245-2 to MLV 249-2: Maintenance Pig
"MLV 251-2 & 251-3: Tie-In
--(September/October Timeframe – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 251-1 & 251-3: Tie-In
--(September/October Timeframe – Exact Dates TBD): This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"254-1 to 256-1: SCCDA
--6/3/16 through 6/17/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs, however if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"254-1 to 261-1: 6/16, 6/21, 6/24 & 6/28: ILI Pig
--6/16/16 through 6/28/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 257-3: Tie-In
"MLV 260-1 to 261-1 : Line Tie-Ins
"MLV 260-1 to 261-1A: Tie-In
"MLV 261-1 to 261-1A: Line Tie-Ins
"Sta. 261: Unit Maintenance
--10/3/16 through 10/7/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 261-5A: Unit Maintenance
--10/19/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 261-1C: Unit Maintenance
--10/18/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 261-1D: Unit Maintenance
--10/17/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
--6/13/16 through 6/17/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 261-1 to 261-1A: Tie-In
"Sta. 266A: Unit Maintenance
--9/12/16 through 9/16/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 264: Unit Maintenance
"Sta. 264-1C: Unit Maintenance
--10/10/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 264-2C: Unit Maintenance
--10/11/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 264A-101.1 to 264A-101.1: Pipe Inspection
--7/5/16 through 7/9/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 265E: Station Maintenance
--9/19/16 through 10/3/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 265E-201 to 265E-201: Pipe Inspection
--7/11/16 through 7/17/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 266A: Unit Maintenance
--8/2/16 through 8/3/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420285 – AGT/TGP MENDON MASS TIE OVER WORCHE
"Sta. 266A: Station Maintenance
--9/14/16 through 9/15/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 266a: Unit Maintenance
--8/15/16 through 8/19/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
--8/29/16 through 9/2/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 267: ESD
--8/9/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"270C-102 to 270C-104: Beverly Salem Lat ILI Pig
--6/13/16 through 6/14/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 270C-400: Anomaly Remediation
--6/13/16 through 6/25/16: This outage will require pressure reductions and possibly line isolations. Should line isolation be required, the listed meter will need to be shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
300 Line Outages
"MLV 313-2A to 315-2: ILI/Cleaning Pig
--9/28/16 through 9/29/16: This activity will require operating at controlled flow rates. The listed meters may be required to reduce their flows depending on the current system conditions. Customers may experience pressure fluctuations, however, no other service impact is antic Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420253 UGICNTRP/TGP WELLSBORO PA TIOGA
420914 DOMINION/TGP SABINSVILLE DELIVERY T
"Sta. 315-1B: Unit Maintenance
--6/27/16 through 6/28/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 315-2 to 317-2: ILI/Cleaning Pig
--9/14/16 through 9/15/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Sta. 317: Station Maintenance
--9/1/16 through 9/30/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date Change, Previously scheduled 7/19/16 to 7/29/16.
"317-1 to 313-1: ILI Pig Run
--6/28/16: This activity will require operating at controlled flow rates. The following meters may experience pressure fluctuations; however, no other service impact is anticipated.
420444 UGICNTRP/TGP TROY PA BRADFORD
420216 VALLEY/TGP TOWANDA PA BRADFORD
420213 UGICNTRP/TGP MANSFIELD PA TIOGA
The following meters will be shut-in for the entire length of the Pig Run (approximately 12 hours):
412841 UGI/TGP UDP AUBURN DEHY: RIP 320 1
412782 APPLACHA/TGP LOTT DEHY: RIP 320D 10
412845 REG NEPA/TGP ELK LAKE SUSQUEHANNA
412821 REG NEPA/TGP DIMOCK DEHY: RIP 320J
412751 WFS/TGP UDP HOP BOTTOM DEHY: RIP 32
412794 REG NEPA/TGP KORBAN DEHY: RIP 320E S
412858 EQT GATH/TGP MASON DEHY: RIP 315F1
412781 SWEPI LP/TGP UDP HOLLOW ROAD DEHY
412797 NFG/TGP UDP RICHMOND DEHY: RIP 315E
412822 MAINESBG/TGP UDP HEMLOCK HILL II DE
412811 SWEPI LP/TGP UDP MAINSBURG DEHY: R
412791 TALISMAN/TGP MOUNTAIN RIDGE DEHY: R
412827 TALISMAN/TGP PUTNAM DEHYD: RIP 316H
412796 SWEPI LP/TGP UDP SWEENEY DEHY: RIP
412770 TALISMAN/TGP UDP SHEDDEN DEHY: RIP
412818 TALISMAN/TGP SHEDDEN II DEHY: RIP 3
"321-1 to 325-1: ILI Pig Run
--6/23/16: This activity will require operating at controlled flow rates. The following meters may experience pressure fluctuations; however, no other service impact is anticipated.
47768 WFS/TGP UDP GIBSON SUSQUEHANNA
420203 UGIPENN/TGP UNIONDALE PA SUSQUEHANN
420245 COL GAS/TGP MILFORD PA BIG PIKE
420277 UGIPENN/TGP HONESDALE PA SALES WAYN
420319 UGIPENN/TGP MILFORD PA PIKE
421014 UGI/TGP WAYMART WAYNE
"Sta. 323-1A: Unit Maintenance
--9/1/16 through 9/30/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 325-4A: Unit Maintenance
--9/1/16 through 10/15/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 325 - 3A: Unit Work
--6/1/16 through 6/1/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***325-1 to 329-1: Anomaly Remediation
--7/11/16 through 8/1/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date Change, Previously scheduled 6/27/16 to 7/18/16.
"332-1: Anomaly Remediation
--6/20/16 through 6/21/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***334A-101.1 to 334A-102: Anomaly Remediation
--6/6/16 through 7/9/16: This outage will require pressure reductions and possibly line isolations. Should line isolation be required, the listed meter will need to be shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420093 CON ED/TGP WHITE PLAINS NY WESTCHES
***Date Change, Previously scheduled 6/6/16 to 6/25/16.
"***MLV 334A-101.1 to 334A-102: ILI/Cleaning Pig
--6/29/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. otential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"339A-101.1: ECDA
--6/27/16 through 7/1/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"340A-101.1: ECDA
--6/20/16 through 6/27/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"343A-100: Pressure Test
--7/8/16 through 8/8/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in for the entire length of the outage. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
The only meter that will be impacted (shut-in) the Bridgeport Meter (420126)
"345A-101: DERBY DELIVERY LINE ECDA
--5/30/16 through 6/11/16: This project involves inspecting multiple sites. We do not anticipate having to do any repairs; however, if a repair is needed, there is a potential that the pipe may require replacement which will require isolation of the pipe. This may limit throughput. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 354-1: Tie-In
"MLV 355-1: Tie-In
500 Line Outages
"MLV 513-1: Pipe Replacement
--9/6/16 through 9/27/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 534-1A to 538-1: ILI/Cleaning Pig: 8/16, 8/17, 8/18 & 8/22
--8/16/16 through 8/22/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 538-1 to 542-1: ILI/Cleaning Pig: 8/23, 8/24, 8/25 & 8/29
--8/23/16 through 8/29/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 542-1A: Unit Maintenance
--6/16/16 through 7/15/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 542-2A: Unit Maintenance
--6/16/16 through 8/31/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 542: Trap Modifications
--7/1/16 through 8/15/16: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"545-1 & 545-2: Meter Install (Hot Taps)
--6/1/16 through 6/30/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 546: Trap Modifications
--8/15/16 through 9/30/16: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 550: Station Maintenance
--7/11/16 through 7/15/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 550: Trap Modifications
--9/15/16 through 11/15/16: This outage will require the pipeline to be taken out of service. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
800 Line Outages
"820-1 & 821-1: Pipe Painting
--4/25/16 through 6/4/16: This project involves inspecting and making repairs at multiple pipeline sites within the noted valve sections. We anticipate being able to make repairs while the line is in-service, however there is a potential that the pipe repair may require replacement. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
400580 FGT/TGP SABINE EXCH CALCASIEU
412013 ENTRPRSE/TGP SABINE RIVER TRANS NEW
412737 LBERTYGS/TGP UDP DE QUINCY GAS STOR
420581 VARIBUS/TGP BECKWITH CREEK CALCASIE
450089 00 TRNSCO/TGP JOHNSON BAYOU DEHY P
401366 TRNSCO/TGP UDP UTOS EXCH CAMERON
411586 TRNSCO/TGP STARKS LA TRANSPORT CALC
412015 HEC/TGP STARKS HANKAMER 1 CALCASIE
412461 NEUMIN/TGP NEUMIN DEHYDRATION CALCA
412690 HPL/TGP SABINE NEWTON
412768 GLDNPASS/TGP STARKS LNG: RIP 820 10
412839 DUNCAN/TGP LABOKAY NO. 1: RIP 820P
420550 ENTRPRSE/TGP SABINE RIVER (1 6179
412597 COKINOS/TGP TEMPLE INLAND NO 1 CALC
411211 Starks Louisiana Transport
412493 Lawthon Dehyd
412717 Burlington (Duncan)
"MLV 821-1: Pipe Replacement
--8/29/16 through 11/1/16: This project will require taking the pipeline section out of service. The listed meters will be shut-in for the entire length of the outage. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
The outage mentioned above will sever TGP 800-1 line (segment 820). The meters listed below are located upstream of the outage, however, they will be isolated from the remainder of the TGP System. For this reason, scheduled receipt volumes must equal scheduled delivery volumes in this area.
412690 – HPL/TGP Sabine Newton
412013 – Enterprise/TGP Sabine River
"Sta 834: Station Outage
--6/1/16 through 9/9/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 851-1 to 856-1: Anomaly Remediation
--6/27/16 through 7/1/16: This outage will require pressure reductions and possibly line isolations. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta 860: Vibration Detection System Replacement
--5/2/16 through 5/31/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Sta. 860 -7A, 8A, 9A & 10A: Unit Maintenance
--6/6/16 through 7/3/16: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Sta. 860: ESD
--6/29/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 871-1 to 866-1: ILI Cleaning Pig
--7/12/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"871-2 to 873-2A: 7/27 & 8/2: ILI Pig
--7/27/16 through 8/2/16: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations; however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
If you have any questions, please contact your Scheduler.