October 1, 2015
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2015 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***MLV 200-4 to 200-4A: Anomaly Remediation
***Project Completed
………………………………"
"***Station 237: Station Maintenance
"***Station 261 Bldg D: Building Maintenance
"***Station 310: Station Maintenance
"***Station 550: Station Maintenance
100 Line Outages
"MLV 1-1D to 9-1S : ILI/Cleaning Pig
--TBD: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 4-3 to 9-3S: Hydrotest
--8/16/15 through 10/19/15: This project will require taking the pipeline section out of service. The listed meters will be shut in during the outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412530 GAITHER/TGP WISER DEHYD REFUGIO
412473 HEC/TGP SOUTH PHIL TOWER REFUGIO
***Date change. Previously scheduled 8/16/15 to 10/10/15.
"***MLV 5-1 to 6-1: Hydrotest
--10/13/15 through 11/30/15: This project will require taking the pipeline section out of service. The listed meters will be shut in during the outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
410063 ROCHE DEHYDRATION
***Date change. Previously scheduled 10/10/15 to 11/30/15.
"***MLV 7-1 to 9-1: Hydrotest
412490 Charro
421083 Eagle Ford Field Service
"***Station 9: Station Maintenance
--3/15/15 through 10/9/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 3/15/15 to 9/30/15.
"MLV 25-1D to 26-1: Hydrotest
--9/8/15 through 10/23/15: This project will require taking the pipeline section out of service. The listed meters will be shut-n during this outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
410826 COLD SPRINGS DEHYDRATION
410612 COLD SPRING DEHYDRATION
412862 COLD SPRINGS DEHYDRATION
"***MLV 31-3 to 33-3: Hydrotest
--9/1/15 through 10/9/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 9/1/15 to 10/2/15.
"Station 32: Station Maintenance
--7/1/15 through 11/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 32-2D to 33-2: Hydrotest
--6/22/15 through 10/9/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 6/22/15 to 10/2/15.
"***MLV 32-1D to 33-1: Hydrotest
--10/9/15 through 12/20/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 10/5/15 to 12/20/15.
"MLV 46-1: Pipe Replacement
--8/18/15 through 11/16/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 46-2: Pipe Replacement
--8/21/15 through 1/14/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 63: Station Maintenance
--6/15/15 through 11/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 6/15/15 to 10/22/15.
"Station 87: Unit Maintenance
--TBD: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Station 96: Station Maintenance
--4/15/15 through 10/9/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date change. Previously scheduled 4/15/15 to 9/30/15.
"MLV 96-1D to 106-1S: Anomaly Remediation
--5/4/15 through 11/30/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 86-3D to 96-3S: ILI/Cleaning Pig
--10/5/15 through 10/24/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 106: Station Maintenance
--11/1/15 through 1/31/16: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 110: Station Maintenance
--3/15/15 through 10/31/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MS #450261 Pemex: Meter Station
--TBD: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
450621 Pemex
"***MS #412494 DCP Warren: Meter Station
--10/9/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412494 DCP Warren
***Project Added
--11/24/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MS #412400 King Ranch: Meter Station
--10/10/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412400 King Ranch
--11/25/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MS #410539 Duvak Gas Gathering: Meter Station
--10/12/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
410539 Duvak Gas Gathering
--11/30/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MS #412356 DCP LaGloria: Meter Station
--10/13/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412356 DCP LaGloria
--12/1/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MS #410173 Enterprise LaReforma: Meter Station
--10/14/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
410173 Enterprise LaReforma
--12/2/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MS #411903 Enterprise El Benito: Meter Station
--10/15/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
411903 Enterprise El Benito
--12/3/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MS #412088 Enterprise Sullivan: Meter Station
--10/16/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412088 Enterprise Sullivan
--12/4/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MS #412683 HESCO: Meter Station
--10/17/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412683 HESCO
--12/5/15: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
200 Line Outages
"MLV 200-1 to 204-1: ILI/Cleaning Pig
--10/15/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 200-2 to 204-2: ILI/Cleaning Pig
--10/20/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Station 204: Station Maintenance
--10/21/15 through 10/25/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 204-2 to 209-2: ILI/Cleaning Pig
--10/13/15 through 10/15/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 204-4 to 209-4: ILI/Cleaning Pig
--10/27/15 through 10/29/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***MLV 209-4 to 214-4: ILI/Cleaning Pig
--10/7/15: This activity will require operating at controlled flow rates. Meter 47652 will be physically shut in on 10/7. This will limit flow to 600 k/d during this outage. Customers may experience pressure fluctuations. TGP will allow nominations to remain in place during this outage.
47652 Leesville
12868 Kensington
"MLV 212-2 & 212-4: Interconnect
--10/2/15 through 10/16/15: This project will require taking the pipeline section out of service. The listed meter will be shut in from 10/12 to 10/16. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 214-4 to 219-4: ILI/Cleaning Pig
--9/29/15 through 10/1/15: This activity will require operating at controlled flow rates. The listed meters will be limited to 700 k/d from 9/28 to 10/2. TGP will allow nominations to remain in place during this outage
"Station 241: Station Maintenance
--10/12/15 through 10/16/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 241: Unit Maintenance
--9/14/15 through 10/2/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 245: Station Maintenance
--9/1/15 through 10/5/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
--10/20/15 through 10/22/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 249: Unit Maintenance
--10/5/15 through 10/6/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 261 Bldg A: Building Maintenance
--TBD: This project will require a building outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
#420901 Berkshire
***Date change. Previously scheduled 9/28/15 to 10/2/15.
"Station 261: Unit Maintenance
--9/29/15 through 10/2/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
--10/5/15 through 10/9/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 261-1 to 267-1: Anomaly Remediation
--4/20/15 through 10/21/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 4/20/15 to 10/15/15.
"***MLV 261-1 to 262-1: Hydrotest
--8/3/15 through 10/13/15: This project will require taking the pipeline section out of service. The first listed meter (#420193) will require a 6-8 hour outage on 8/25 and 10/2. The second meter (420318) will be shut in from 8/25 to 10/2. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420193 BAY ST/TGP EAST LONGMEADOW MA HAMPD
420318 Yank Gas/TGP Thompsonville Ct EXCH
***Date change. Previously scheduled 8/3/15 to 10/12/15.
"Station 264: Unit Maintenance
--10/6/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
--10/12/15 through 10/13/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 265E: Station Maintenance
--9/19/15 through 11/9/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Worcester Lateral (265A-100): ILI/Cleaning Pig
--10/20/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 11/3/15.
"266A-100 Lateral: Maintenance Pig
--10/13/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"266C-102 (Blackstone Lateral): Pipe Repair/Replacement
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
300 Line Outages
"Station 313: Station Maintenance
--TBD: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 314: Hot Taps (crossovers)
--TBD: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 317-1 to 313-1: Maintenance Pig
--10/20/15: This activity will require operating at controlled flow rates. The listed meters may experience higher than normal pressures for the duration of the pig run. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
20444 Troy
20216 Towanda
20213 Mansfield
20253 Wellsboro
12770Shedden I
12818 Shedden II
12858 Mason
12822 Hemlock Hill
12746 Hemlock Dehy
12797 Richmond
12781 Hollow Rd
12811 Mainesburg
12796 Sweeney
12791 Mt. Ridge
12827 Putnam
"MLV 317-2 to 313-2: Maintenance Pig
--10/22/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 319-1 to 317-1: Maintenance Pig
--10/13/15: This activity will require operating at controlled flow rates. The listed meters may experience higher than normal pressures for the duration of the pig run. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
21046 Owego Stagecoach
20443 Auburn
12732 Owego Stagecoach Rec
20652 Towanda
12834 Calkins
12784 Allen Meadow
12769 Evanchick
12785 Swain Rd
12780 Bailey's Corner
"MLV 319-2 to 317-2: Maintenance Pig
--10/15/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 319-1 to 321-1: Maintenance Pig
--10/6/15: This activity will require operating at controlled flow rates. The first three listed meters may experience higher than normal pressures as well as reduction in volumes for the duration of the pig. The last ten listed meters may experience higher than normal pressures for the duration of the pig run. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
12846 Shoemaker
12832 Latini
12833 Silvara
12835 Katy
12779 Cron
12841 Auburn Dehy
12845 Elk Lake
12821 Dimock
12854 Valentine
12782 Lott
"MLV 319-2 to 321-2: Maintenance Pig
--10/8/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 321: Station Maintenance
--10/1/15 through 10/8/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 321-1 to 325-1: Maintenance Pig
--10/1/15: This activity will require operating at controlled flow rates. The listed meters may experience higher than normal pressures for the duration of the pig run. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
20203 Uniondale
21014 Waymart Sale
20277 Honesdale
20245 Milford
20319 Little Milford
"MLV 322: Hot Taps (crossovers)
"Station 323A: Station Maintenance
--10/13/15 through 10/20/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 325: Station Maintenance
"***MLV 325-1 to 329-1: ILI/Cleaning Pig
--10/16/15: This activity will require operating at controlled flow rates. The listed meters may be required to reduce their flows depending on the current system conditions. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420410 PIVOTAL/TGP SUSSEX NJ SUSSEX
420450 PIVOTAL/TGP VERNON NJ SUSSEX
420608 NJ NATGS/TGP NEW CLINTON ROAD NJ BE
420339 PSEG/TGP WEST MILFORD NJ PASSAIC
420207 AGT/TGP MAHWAH NEW JERSEY BERGEN
420226 PSEG/TGP RAMSEY NJ BERGEN
420516 PSEG/TGP RINGWOOD NJ PASSAIC
***Date change. Previously scheduled TBD.
500 Line Outages
"***MLV 524-2 to 527-2: Anomaly Remediation
--10/19/15 through 10/31/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 550-1: Hydrotest
--8/20/15 through 9/25/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
" MLV 550-2 to 555-2 : Valve Replacment
--9/25/15 through 10/15/15: This project will require taking the pipeline section out of service. The listed meters could see reduction in volumes during this outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420307 AMMID AT/TGP BARTON AL COLBERT
420696 AMMID TN/TGP BARTON TRANSPORT COLBE
420942 AMMID BA/TGP BAMAGAS COLBERT
"MLV 551-1 to 554-1: Hydrotest
--10/30/15 through 11/30/15: This project will require taking the pipeline section out of service. The listed meters could see reduction in volumes during this outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 554-1 to 555-1: Hydrotest
--10/30/15 through 11/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 555: Unit Maintenance
--5/23/15 through 10/31/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 555: Station Maintenance
--10/16/15 through 11/30/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 558-1 to 559-1: Hydrotest
--9/15/15 through 10/3/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
800 Line Outages
"Station 823: Station Maintenance
--10/6/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 838-1: Pipe Repair/Replacement
--10/5/15 through 10/9/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 843-1B: Drip Removal/Hydro Test
--9/1/15 through 10/21/15: This project will require taking the pipeline section out of service. The listed meter will be shut in for the entire length of time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412762 TEX GAS/TGP ISOLA ROAD RIP 843B 101
"MLV 849-1: Interconnect
--12/31/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 860: Station Maintenance
--9/17/15 through 10/9/15: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 9/17/15 to 10/3/15.
If you have any questions, please contact your Scheduler.