August 26, 2015
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2015 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***Station 204: Station Maintenance
***Completed
………………………………"
"***Station 555: Station Maintenance
"***MLV 705-1 to 706-1: Pipe Inspection/Repair
The following meters are available for nominations:
412688 Panola 2
410031 ETX GAS/TGP EAST TX PLANT DEHY PANO
412033 MARLIN/TGP CARTHAGE TRANSPORT PANOL
411200 Panola
412141 Enterprise
420723 ETP/TGP CARTHAGE GAS UNIT 13 PANOLA12141
411525 CHAPARRA/TGP BELLE BOWER DEHY PANOL
100 Line Outages
"MLV 1-1D to 9-1S : ILI/Cleaning Pig
--TBD: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 4-3 to 9-3S: Hydrotest
--8/16/15 through 9/30/15: This project will require taking the pipeline section out of service. The listed meters will be shut in during the outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412530 GAITHER/TGP WISER DEHYD REFUGIO
412473 HEC/TGP SOUTH PHIL TOWER REFUGIO
"***MLV 5-1 to 6-1: Hydrotest
--10/1/15 through 11/30/15: This project will require taking the pipeline section out of service. The listed meters will be shut in during the outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
410063 ROCHE DEHYDRATION
***Date change. Previously scheduled 10/1/15 to 10/30/15.
"***MLV 7-1 to 9-1: Hydrotest
412490 Charro
421083 Eagle Ford Field Service
"Station 9: Station Maintenance
--3/15/15 through 9/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 25-1D to 26-1: Hydrotest
--8/31/15 through 10/23/15: This project will require taking the pipeline section out of service. The listed meters will be shut-n during this outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
410826 COLD SPRINGS DEHYDRATION
410612 COLD SPRING DEHYDRATION
412862 COLD SPRINGS DEHYDRATION
"***MLV 31-3 to 33-3: Hydrotest
--9/1/15 through 9/25/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Project Added
"Station 32: Station Maintenance
--7/1/15 through 11/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 32-2D to 33-2: Hydrotest
--6/22/15 through 8/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 32-1D to 33-1: Hydrotest
--9/28/15 through 12/15/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 8/31/15 to 11/20/15.
"MLV 46-1: Pipe Replacement
--8/18/15 through 11/16/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 46-2: Pipe Replacement
--8/21/15 through 1/14/16: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 63: Station Maintenance
--6/15/15 through 10/22/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 71-3D to 79-3S: Anomaly Remediation
--6/22/15 through 8/27/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 87: Unit Maintenance
--TBD: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 90-4 to 106-4S: Anomaly Remediation
--7/6/15 through 8/30/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 96: Station Maintenance
--4/15/15 through 9/30/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 96-1D to 106-1S: Anomaly Remediation
--5/4/15 through 11/30/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 96-3D to 106-3S: ILI/Cleaning Pig
--10/5/15 through 10/9/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 106: Station Maintenance
--10/16/15 through 12/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 110: Station Maintenance
--3/15/15 through 10/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 114: Station Maintenance
--4/15/15 through 9/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience varying pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Columbia Gas BR Cobb Meter # 400459: Meter Station Piping Modifications
--6/10/15 through 8/31/15: Capacity at this meter will vary depending on the number of meter tubes in service See approximate dates and capacities below:
6/10 – 6/22: 540k/d
6/22 – 7/20: 270k/d
7/20 – 7/30: tbd
8/13 – 8/19: 225 K/d
8/19 - 8/31: 160 k/d
No other service impact is anticipated.
400459 COL GAS/TGP BROAD RUN COBB WV KANAW
***Date change. Previously scheduled 6/10/15 to 8/28/15.
"MS #450261 Pemex: Meter Station
--TBD: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
450621 Pemex
200 Line Outages
"MLV 200-1 to 204-1: ILI/Cleaning Pig
--9/21/15 through 10/15/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
Meters impacted to be determined
"MLV 200-2 to 204-2: ILI/Cleaning Pig
--9/21/15 through 10/20/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 200-4 to 200-4A: Anomaly Remediation
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 204-2 to 209-2: ILI/Cleaning Pig
--10/13/15 through 10/15/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 204-3 to 209-3: ILI/Cleaning Pig
--8/25/15 through 8/27/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 204-4 to 209-4: ILI/Cleaning Pig
--10/27/15 through 10/29/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***MLV 206-1: Anomaly Remediation
--8/29/15 through 10/19/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date change. Previously scheduled 8/25/15 to 10/19/15.
"MLV 206-2 to 207-2: Anomaly Remediation
--6/9/15 through 8/30/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 209-4 to 214-4: ILI/Cleaning Pig
--9/15/15 through 9/17/15: This activity will require operating at controlled flow rates. Meter 47652 will be physically shut in from 9/14 to 9/18. This will limit flow to 600 k/d during this outage. Customers may experience pressure fluctuations. TGP will allow nominations to remain in place during this outage.
47652 Leesville
12868 Kensington
"MLV 210-1: Anomaly Remediation
--4/24/15 through 9/11/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 212-2 & 212-4: Interconnect
--10/5/15 through 10/16/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 214-4 to 219-4: ILI/Cleaning Pig
--9/29/15 through 10/1/15: This activity will require operating at controlled flow rates. The listed meters will be limited to 700 k/d from 9/28 to 10/2. TGP will allow nominations to remain in place during this outage
"MLV 217A-101: Interconnect
--9/8/15 through 9/11/15: This project will require taking the pipeline section out of service. The listed meters will be shut-in. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
412863 SWEPI (AKA Little Beaver)
421075 Big Beaver
"MLV 217A-201: Interconnect
--9/15/15 through 9/18/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Hamburg Meter #420076: Meter Station
--7/20/15 through 9/3/15: This project will require isolating the meter station. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420076 Hamburg Meter
"Station 237: Station Maintenance
--9/29/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 241: Station Maintenance
--10/12/15 through 10/16/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 241: Unit Maintenance
--9/14/15 through 9/25/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 245: Unit Maintenance
--8/25/15 through 8/27/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
"Station 245: Station Maintenance
--9/1/15 through 9/22/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 245-2: Interconnect
--9/14/15 through 9/18/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 249: Unit Maintenance
--8/31/15 through 9/3/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
--9/8/15 through 9/10/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
"Northhampton Lateral (260A-100): Cleaning Pig
--9/18/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 261 Bldg D: Building Maintenance
--9/13/15 through 9/25/15: This project will require a building outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 261 Bldg A: Building Maintenance
--9/28/15 through 10/2/15: This project will require a building outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
#420901 Berkshire
"MLV 261-1 to 267-1: Anomaly Remediation
--4/20/15 through 10/31/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 261-1 to 262-1: Hydrotest
--8/3/15 through 10/1/15: This project will require taking the pipeline section out of service. The first listed meter (#420193) will require a 6-8 hour outage on 8/25 and 9/30. The second meter (420318) will be shut in from 8/25 to 9/30. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420193 BAY ST/TGP EAST LONGMEADOW MA HAMPD
420318 Yank Gas/TGP Thompsonville Ct EXCH
"Station 265E: Station Maintenance
--9/19/15 through 11/9/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 266A: Station Maintenance
--9/15/15 through 9/16/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 266A: Unit Maintenance
--8/10/15 through 8/28/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
--8/17/15 through 8/28/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
"266C-102 (Blackstone Lateral): Pipe Repair/Replacement
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"270B-400: ILI/Cleaning Pig
--9/9/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 270C-300: Anomaly Remediation
--8/27/15 through 9/15/15: This project will require taking the pipeline section out of service. The listed meters could be affected. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420848 WAKEFIELD SALES
420343 LYNN FIELD MASSACHUSETTS
420116 REVERE MASSACHUSETTS
412513 DISTRIGAS
300 Line Outages
"Station 303: Station Maintenance
--9/16/15 through 9/18/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 310: Station Maintenance
--9/2/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 313: Station Maintenance
--TBD: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 314: Hot Taps
(crossovers)
--TBD: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 315: Unit Maintenance
--8/23/15 through 8/27/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
--8/31/15 through 9/1/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
"Station 321: Station Maintenance
--9/30/15 through 10/7/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 322: Hot Taps
"Station 323A: Station Maintenance
--10/12/15 through 10/19/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 325: Station Maintenance
"***MLV 325-1 to 329-1: ILI/Cleaning Pig
--TBD: This activity will require operating at controlled flow rates. The listed meters may be required to reduce their flows depending on the current system conditions. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420410 PIVOTAL/TGP SUSSEX NJ SUSSEX
420450 PIVOTAL/TGP VERNON NJ SUSSEX
420608 NJ NATGS/TGP NEW CLINTON ROAD NJ BE
420339 PSEG/TGP WEST MILFORD NJ PASSAIC
420207 AGT/TGP MAHWAH NEW JERSEY BERGEN
420226 PSEG/TGP RAMSEY NJ BERGEN
420516 PSEG/TGP RINGWOOD NJ PASSAIC
***Date change. Previously scheduled 8/22/15 to 8/25/15.
"Station 405A: Station Maintenance
--9/8/15 through 9/9/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
500 Line Outages
"MLV 507F: Pig Trap Modification
--8/26/15 through 9/16/15: This project will require isolating the pipeline section. The listed meter will need to be shut-in for the entiere time. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
450302 Grand Chenier Inlet
"MS #420291, Transco Heidelberg: Meter Station
--9/16/15: This project will require isolating the meter station. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
420291 Transco Heidelberg.
"MLV 542-1 to 546-1: ILI/Cleaning Pig
--9/4/15 through 9/8/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 547-1 to 549-1: Hydrotest
--8/20/15 through 9/20/15: This project will require taking the pipeline section out of service. The listed meter will need to be shut-in for the entire time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
411225 Pruitt Buttahatchie
412322 McKinley Creek
420765 Atmos MS/TGP Aberdeen Sales Monroe
420694 GA Gulf/TGP Mississippi Transport (Axiall Chemical Plant)
411675 Greenwood Springs
"MLV 549-1: Hydrotest
--8/20/15 through 9/20/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 550: Station Maintenance
--8/20/15 through 9/20/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 550-1: Hydrotest
" MLV 550-2 to 555-2 : Valve Replacment
--9/25/15 through 10/15/15: This project will require taking the pipeline section out of service. The listed meters could see reduction in volumes during this outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420307 AMMID AT/TGP BARTON AL COLBERT
420696 AMMID TN/TGP BARTON TRANSPORT COLBE
420942 AMMID BA/TGP BAMAGAS COLBERT
"MLV 551-1 to 554-1: Hydrotest
--10/30/15 through 11/30/15: This project will require taking the pipeline section out of service. The listed meters could see reduction in volumes during this outage. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 554-1 to 555-1: Hydrotest
--10/30/15 through 11/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 555: Unit Maintenance
--5/23/15 through 10/31/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
--10/16/15 through 11/30/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date change. Previously scheduled 10/30/15 to 11/30/15.
"MLV 558-1 to 559-1: Hydrotest
--9/15/15 through 10/3/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
800 Line Outages
"Station 823: Station Maintenance
"MLV 843-1B: Drip Removal/Hydro Test
--9/1/15 through 10/16/15: This project will require taking the pipeline section out of service. The listed meter will be shut in for the entire length of time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412762 TEX GAS/TGP ISOLA ROAD RIP 843B 101
"MLV 849-1: Interconnect
--12/31/16: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 860 : Station Maintenance
--9/15/15 through 10/3/15: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
If you have any questions, please contact your Scheduler.