Subject:  Updated TGP Scheduled Outages
Notice Text:

July 30, 2015

 

TO:  ALL TENNESSEE CUSTOMERS

 

RE:  UPDATED TGP SCHEDULED OUTAGES

 

This notice is an update of the 2015 planned outages and maintenance

activities on Tennessee Gas Pipeline.

 

The Outage and Maintenance schedule is available in an Excel

spreadsheet format which may be found in DART.

 

Some projects may reduce capacity to a level below anticipated

demand (nominations), or require taking individual meters out of

service. 

 

For each project, based upon anticipated demand, the highest

level of service Tennessee expects to be impacted is noted. 

Unless noted otherwise, all impacts are in the Supply to Market

direction.

 

Projects may be added, altered, delayed or canceled.  Tennessee

will provide updates by posting revisions on a weekly basis or

more often if necessary.

 

Projects revised or added since the last posting are preceded

by ***.  Within the Excel Spreadsheet and Adobe Files, revisions

are highlighted and an asterisk has been added to the "Revised"

column.

 

Unless otherwise noted, all listed meters will be physically shut

-in for the duration of the project.

 

Unless otherwise noted, all scheduled dates represent gas days

as defined in the Tennessee Gas Pipeline tariff to mean a period

of twenty-four consecutive hours, beginning and ending at 9:00

a.m. (Central Clock Time).

 

=========================

Completed Outages

=========================

"***MLV 4-2 to 6-2:  Pig Trap Modifications

***Project Completed

………………………………"

"***MLV 71-4D to 79-4S:  ILI/Cleaning Pig

***Project Completed

………………………………"

"***Riverside #420924:  Meter Station

***Project Completed

The following meters are available for nominations:

420924 RIVERSID/TGP LAWERENCE BOYD

………………………………"

"***MLV 230-1 to 237-1:  Anomaly Remediation

***Project Completed

The following meters are available for nominations:

412856 EMPIREPL/TGP CANANDAIGUA ONTARIO

412870 DOMINION/TGP CRAIGS: RIP 232G 101.1

420526 HONEOYE/TGP HONEOYE NEW YORK ONTARI

420690 DOMINION/TGP NORTH SHELDON SALES WY

420688 DOMINION/TGP LAKEVILLE SALES LIVING

420617 DOMINION/TGP HOPEWELL SALES ONTARIO

………………………………"

"***Station 241:  Unit  Maintenance

***Project Completed

………………………………"

"***Station 241:  Unit  Maintenance

***Project Completed

………………………………"

"***MLV 321-2 to 325-2:  ILI/Cleaning Pig

***Project Completed

The following meters are available for nominations:

47768 Gibson

420203 UGIPENN/TGP UNIONDALE PA SUSQUEHANN

421014 UGI/TGP WAYMART WAYNE

420277 UGIPENN/TGP HONESDALE PA SALES WAYN

420245 COL GAS/TGP MILFORD PA BIG PIKE

420319 UGIPENN/TGP MILFORD PA PIKE

………………………………"

"***Station 323:  Unit  Maintenance

***Project Completed

………………………………"

"***Station 323:  Unit  Maintenance

***Project Completed

………………………………"

"***Station 555:  Station Maintenance

***Project Completed

………………………………"

"***Station 820C1:  Station Maintenance

***Project Completed

The following meters are available for nominations:

411586 Transco Stark

………………………………"

 

=========================

100 Line Outages

=========================

"MLV 1-1D to 9-1S :  ILI/Cleaning Pig

--TBD:  This activity will require operating at controlled flow rates.   Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 4-3 to 9-3S:  Hydrotest

--9/8/15 through 10/22/15:  This project will require taking the pipeline section out of service.  The listed meters will be shut in during the outage.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

412530 GAITHER/TGP WISER DEHYD REFUGIO

412473 HEC/TGP SOUTH PHIL TOWER REFUGIO

………………………………"

"MLV 7-1 to 9-1:  Hydrotest

--7/21/15 through 9/8/15:  This project will require taking the pipeline section out of service.  The listed meters will be shut in during the outage.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

412490 Charro

421083 Eagle Ford Field Service

………………………………"

"MLV 5-1 to 6-1:  Hydrotest

--7/28/15 through 9/8/15:  This project will require taking the pipeline section out of service.  The listed meters will be shut in during the outage.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

410063 ROCHE DEHYDRATION            

………………………………"

"***Station 9:  Station Maintenance

--3/15/15 through 7/31/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

***Date change. Previously scheduled 3/15/15 to 7/24/15.

………………………………"

"***MLV 25-1D to 26-1:  Hydrotest

--8/31/15 through 10/23/15:  This project will require taking the pipeline section out of service.  The listed meters will be shut-in during this outage. This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

410826 COLD SPRINGS DEHYDRATION

410612 COLD SPRING DEHYDRATION

412862 COLD SPRINGS DEHYDRATION

***Date change. Previously scheduled 8/10/15 to 10/2/15.

………………………………"

"***MLV 32-2D to 33-2:  Hydrotest

--6/22/15 through 8/30/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

***Date change. Previously scheduled 6/22/15 to 8/9/15.

………………………………"

"MLV 32-1D to 33-1:  Hydrotest

--8/10/15 through 10/31/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 32:  Station Maintenance

--7/1/15 through 11/15/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 40-4D to 47-4S:  ILI/Cleaning Pig

--6/24/15 through 7/30/15:  This activity will require operating at controlled flow rates.   Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 46-1:  Pipe Replacement

--8/18/15 through 11/16/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 46-2:  Pipe Replacement

--8/21/15 through 1/14/16:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 63:  Station Maintenance

--6/15/15 through 10/22/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 71-3D to 79-3S:  Anomaly Remediation

--6/22/15 through 8/8/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 87:  Unit  Maintenance

--TBD:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"Station 96:  Station Maintenance

--4/15/15 through 9/30/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 96-3D to 106-3S:  ILI/Cleaning Pig

--TBD:  This activity will require operating at controlled flow rates.   Customers may experience pressure fluctuations, however, no other service impact is anticipated.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 90-4 to 106-4S:  Anomaly Remediation

--7/6/15 through 7/30/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 96-1D to 106-1S:  Anomaly Remediation

--5/4/15 through 11/30/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"***Station 106:  Station Maintenance

--9/30/15 through 12/15/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

***Date change. Previously scheduled 8/1/15 to 12/15/15.

………………………………"

"Station 110:  Station Maintenance

--3/15/15 through 9/30/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"***MLV 113-3:  Hydrotest

--8/17/15 through 8/31/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

***Date change. Previously scheduled 8/10/15 to 8/24/15.

………………………………"

"***Station 114:  Station Maintenance

--4/15/15 through 8/17/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations.  Customers may experience varying pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

***Date change. Previously scheduled 4/15/15 to 7/31/15.

………………………………"

"Columbia Gas  BR Cobb Meter # 400459:  Meter Station Piping Modifications

--6/10/15 through 8/15/15:  Capacity at this meter will vary depending on the number of meter tubes in service  See approximate dates and capacities below:

6/10 – 6/22:  540k/d

6/22 – 7/20:  270k/d

7/20 – 7/30:  tbd

7/30 – 8/15:  270K/d

8/20 after:  810k/d 

No other service impact is anticipated.

Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

400459 COL GAS/TGP BROAD RUN COBB WV KANAW

………………………………"

"Station 409:  Station Maintenance

--8/3/15 through 8/6/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MS #450261 Pemex:  Meter Station

--TBD:  This project will require isolating the pipeline section.  Physical flow will be suspended.  No other service impact is anticipated.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

450621 Pemex

………………………………"

"MLV 705-1 to 706-1:  Pipe Inspection/Repair

--2/9/15 through 8/28/15:  This project involves inspecting and making repairs at multiple pipeline sites within the noted valve section.   We anticipate being able to make repairs while the line is in-service, however there is a potential that the pipe repair may require replacement which will require isolation of the pipe.  The listed meters may require shut-in, if isolation is needed.  This may limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.

412688 Panola 2

410031 ETX GAS/TGP EAST TX PLANT DEHY PANO

412033 MARLIN/TGP CARTHAGE TRANSPORT PANOL

411200 Panola

412141  Enterprise

420723 ETP/TGP CARTHAGE GAS UNIT 13 PANOLA12141

411525 CHAPARRA/TGP BELLE BOWER DEHY PANOL

 

 

………………………………"

 

=========================

200 Line Outages

=========================

"MLV 200-4 to 200-4A:  Anomaly Remediation

--TBD:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"MLV  200-1 to 204-1:  ILI/Cleaning Pig

--TBD:  This activity will require operating at controlled flow rates.   Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"MLV 200-2 to 204-2:  ILI/Cleaning Pig

--TBD:  This activity will require operating at controlled flow rates.   Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"Station 204:  Station Maintenance

--8/17/15 through 8/21/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 204-2 to 209-2:  ILI/Cleaning Pig

--10/13/15 through 10/15/15:  This activity will require operating at controlled flow rates.   Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"MLV 204-3 to 209-3:  ILI/Cleaning Pig

--8/25/15 through 8/27/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"MLV 204-4 to 209-4:  ILI/Cleaning Pig

--10/27/15 through 10/29/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"MLV 206-1:  Anomaly Remediation

--9/6/15 through 10/19/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 206-2 to 207-2:  Anomaly Remediation

--6/9/15 through 9/5/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"Station 209:  Station Maintenance

--8/7/15 through 8/9/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 209-4 to 214-4:  ILI/Cleaning Pig

--9/15/15 through 9/17/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"MLV 210-1:  Anomaly Remediation

--4/24/15 through 7/31/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 212-2 & 212-4:  Interconnect

--10/5/15 through 10/16/15:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 214-4 to 219-4:  ILI/Cleaning Pig

--9/29/15 through 10/1/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

Meters impacted to be determined

………………………………"

"MLV 217A-101:  Interconnect

--9/8/15 through 9/11/15:  This project will require taking the pipeline section out of service.   The listed meters will be shut-in.  This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

412863 SWEPI (AKA Little Beaver)

421075 Big Beaver

………………………………"

"MLV 217A-201:  Interconnect

--9/15/15 through 9/18/15:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"Hamburg Meter #420076:  Meter Station

--7/20/15 through 8/17/15:  This project will require isolating the meter station.  Physical flow will be suspended.  No other service impact is anticipated.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

420076 Hamburg Meter

………………………………"

"MLV  230B-101 to 230B-106:  Anomaly Remediation

--7/22/15 through 8/12/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"Station 237:  Station Maintenance

--9/29/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 241:  Station Maintenance

--10/12/15 through 10/16/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 241:  Unit  Maintenance

--9/14/15 through 9/25/15:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 245-1:  Interconnect

--7/27/15 through 7/31/15:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 245-2:  Interconnect

--9/14/15 through 9/18/15:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"***Station 245:  Station Maintenance

--9/1/15 through 9/22/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

***Date change. Previously scheduled 9/7/15 to 9/12/15.

………………………………"

"Station 249:  Unit  Maintenance

--7/27/15 through 7/31/15:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Northhampton Lateral (260A-100):  Cleaning Pig

--9/18/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 261-1 to 267-1:  Anomaly Remediation

--4/20/15 through 10/31/15:  This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 261-1 to 262-1:  Hydrotest

--8/3/15 through 10/1/15:  This project will require taking the pipeline section out of service.  The first listed meter (#420193)  will require a 6-8 hour outage on 8/25 and 9/30.  The second meter (420318) will be shut in from 8/25 to 9/30. This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

420193 BAY ST/TGP EAST LONGMEADOW MA HAMPD

420318  Yank Gas/TGP Thompsonville Ct EXCH

………………………………"

"Station 265E:  Station Maintenance

--9/19/15 through 11/9/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.

………………………………"

"Station 266A:  Unit  Maintenance

--8/10/15 through 8/14/15:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 266A:  Unit  Maintenance

--8/17/15 through 8/21/15:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 266A:  Station Maintenance

--9/15/15 through 9/16/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.

………………………………"

"Station 267:  Station Maintenance

--8/19/15 through 8/20/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.

………………………………"

"266C-102 (Blackstone Lateral):  Pipe Repair/Replacement

--TBD:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

Meters impacted to be determined

………………………………"

"270B-400:  ILI/Cleaning Pig

--9/9/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"***MLV  270C-300:  Anomaly Remediation

--8/15/15 through 9/15/15:  This project will require taking the pipeline section out of service.  The listed meters could be affected. This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

420848 WAKEFIELD SALES

420343 LYNN FIELD MASSACHUSETTS

420116 REVERE MASSACHUSETTS

412513 DISTRIGAS

***Project Added

………………………………"

 

=========================

300 Line Outages

=========================

"***MLV 307-1 to 219-2:  ILI/Cleaning Pig

--8/5/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

***Project Added

………………………………"

"***MLV 307-2 to 219-3:  ILI/Cleaning Pig

--8/7/15:  This activity will require operating at controlled flow rates.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

***Project Added

………………………………"

"Station 313:  Station Maintenance

--TBD:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 314:  Hot Taps (crossovers)

--TBD:  Customers may experience pressure fluctuations and may result in restrictions based on customer nominations.   Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

Meters impacted to be determined

………………………………"

"MLV 322:  Hot Taps (crossovers)

--TBD:  Customers may experience pressure fluctuations and may result in restrictions based on customer nominations.   Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

Meters impacted to be determined

………………………………"

"***MLV 325-1 to 329-1:  ILI/Cleaning Pig

--TBD:  This activity will require operating at controlled flow rates.   The listed meters may be required to reduce their flows depending on the current system conditions.  Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

420410 PIVOTAL/TGP SUSSEX NJ SUSSEX

420450 PIVOTAL/TGP VERNON NJ SUSSEX

420608 NJ NATGS/TGP NEW CLINTON ROAD NJ BE

420339 PSEG/TGP WEST MILFORD NJ PASSAIC

420207 AGT/TGP MAHWAH NEW JERSEY BERGEN

420226 PSEG/TGP RAMSEY NJ BERGEN

420516 PSEG/TGP RINGWOOD NJ PASSAIC

***Date change. Previously scheduled 8/4/15 to 8/6/15.

………………………………"

 

=========================

500 Line Outages

=========================

"MLV 507G-1010 to 507G-1011:  Anomaly Remediation

--8/4/15 through 8/9/15:  This project will require taking the pipeline section out of service.  The listed meter will need to be shut-in for  the entire time. This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

450105 AMMID SC/TGP QUIVIRA CHECK ST MARY

412594 NAUTILUS/TGP GARDEN CITY ST MARY

421080 /TGP ST MARY CARBON BLACK: DIP 507G

………………………………"

"MLV 541-1 to 542-1:  Hydrotest

--6/27/15 through 7/30/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"Station 542:  Station Maintenance

--6/26/15 through 7/30/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 543-1 to 546-1 :  Hydrotest

--6/6/15 through 8/17/15:  This project will require taking the pipeline section out of service.  The listed meter will need to be shut-in for  the entire time. This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

420294 PUGH MISSISSIPPI

………………………………"

"MLV 542-1 to 546-1:  ILI/Cleaning Pig

--9/4/15 through 9/8/15:  This activity will require operating at controlled flow rates.    Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"***MLV 546-2 to 550-2:  Anomaly Remediation

--7/21/15 through 8/18/15:  This project will require taking the pipeline section out of service.  The listed meter will need to be shut-in from 8/5 to 8/18. This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

48033 Southcross Fayette Vernon

20879 Southcross Mt. Zion

***Date change. Previously scheduled 7/21/15 to 8/15/15.

………………………………"

"MLV 547-1 to 549-1:  Hydrotest

--8/20/15 through 9/20/15:  This project will require taking the pipeline section out of service.  The listed meter will need to be shut-in for  the entire time. This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

411225  Pruitt Buttahatchie

412322 McKinley Creek

420765 Atmos MS/TGP Aberdeen Sales Monroe

420694 GA Gulf/TGP Mississippi Transport (Axiall Chemical Plant)

411675 Greenwood Springs

………………………………"

"MLV  549-1:  Hydrotest

--8/20/15 through 9/20/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 550-1:  Hydrotest

--8/20/15 through 9/20/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 551-1 to 554-1:  Hydrotest

--10/30/15 through 11/30/15:  This project will require taking the pipeline section out of service.  The listed meters could see reduction in volumes during this outage.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

420307 AMMID AT/TGP BARTON AL COLBERT

420696 AMMID TN/TGP BARTON TRANSPORT COLBE

420942 AMMID BA/TGP BAMAGAS COLBERT

………………………………"

" MLV 550-2 to 555-2 :  Valve Replacment

--9/25/15 through 10/15/15:  This project will require taking the pipeline section out of service.  The listed meters could see reduction in volumes during this outage.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

420307 AMMID AT/TGP BARTON AL COLBERT

420696 AMMID TN/TGP BARTON TRANSPORT COLBE

420942 AMMID BA/TGP BAMAGAS COLBERT

………………………………"

"MLV 554-1 to 555-1:  Hydrotest

--10/30/15 through 11/30/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"MLV 558-1 to 559-1:  Hydrotest

--9/15/15 through 10/3/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

"Station 550:  Station Maintenance

--8/20/15 through 9/20/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.

………………………………"

"Station 555:  Unit  Maintenance

--5/23/15 through 10/31/15:  This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 555:  Station Maintenance

--10/30/15 through 11/30/15:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.

………………………………"

 

=========================

800 Line Outages

=========================

"Sta. 823 to  Sta.40:  ILI/Cleaning Pig

--TBD  through TBD:  This activity will require operating at controlled flow rates.   The listed meters will need to be shut-in for the duration of the run (approx. 12 hours).Customers may experience pressure fluctuations, however, no other service impact is anticipated.    Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, EDS/ERS, Payback to Tennessee, PAL-T (Parks/ Loan Paybacks), SOP) nominations.

420373 Transco/Kinder

………………………………"

"Station 823:  Station Maintenance

--TBD:  This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"MLV 843-1B:  Drip Removal/Hydro Test

--9/1/15 through 10/16/15:  This project will require taking the pipeline section out of service.  This will limit throughput and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

412762 TEX GAS/TGP ISOLA ROAD RIP 843B 101

………………………………"

"MLV 849-1:  Interconnect

--8/24/15 through 9/15/15:  This project will require taking the pipeline section out of service.   This will limit throughput and will result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.

………………………………"

"Station 860:  Station Maintenance

--9/15/15 through 10/3/15:  This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time.  Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.

………………………………"

 

If you have any questions, please contact your Scheduler.

 

...