March 26, 2015
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of the 2015 planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART.
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***Station 1 (MLV 1-1 to 2-1): Pig Trap Modifications
***Project Completed
………………………………"
"***MLV 40-4D to 47-4S: ILI/Cleaning Pig
The following meters are available for nominations:
Meters impacted to be determined
"***Sta. 106 to Sta. 200: ILI/Cleaning Pig
"***Station 200: Station Maintenance
"***MLV 207-1: Anomaly Remediation
"***MLV 701-1: Pipe Inspection/Repair
412688 Panola 2 (currently shut-in)
410031 ETX GAS/TGP EAST TX PLANT DEHY PANO (currently shut-in)
412033 MARLIN/TGP CARTHAGE TRANSPORT PANOL (currently shut-in)
411200 Panola (currently shut-in)
412141 Enterprise (currently shut-in)
420723 ETP/TGP CARTHAGE GAS UNIT 13 PANOLA12141 (currently shut-in)
411525 CHAPARRA/TGP BELLE BOWER DEHY PANOL (currently shut-in)
412807 RGNCY FS/TGP LOGANSPORT B: RIP 704H
412706 LoganSport
412607 Desoto
412764 ENT GATH/TGP STATE LINE PROCESSING
412725 EAGLROCK/TGP DE SOTO
412759 UES/TGP BURFORD GATHERING: RIP 704
412081 EPE/TGP BETHANY LONGSTREET FIELD DE
412026 BEUSA/TGP GRAND CANE DE SOTO
412775 EOG/TGP TRENTON SALES: RIP 703H-1 5
412765 Trenton Field
412610 MAGNUMPL/TGP WEST MANSFIELD DE SOTO
412583 Pinnacle
412814 Blackstone No. 1
412819 Converse
411755 Grogan Fld
411330 TEXLA/TGP CHEMARD LAKE DEHY DE SOTO
411598 San Miguel
"***Station 860(MLV 559-1): Station Maintenance
"***Station 860 MLV 559-2): Station Maintenance
100 Line Outages
"MLV 1-1D to 9-1S : ILI/Cleaning Pig
--TBD: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 9 (MLV 8-1 to 10-1): Pig Trap Modifications
--5/8/15 through 6/11/15: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412490 Charro
421083 Eagle Ford Field Service
"Station 9 (MLV 8-2 to 10-2): Pig Trap Modifications
--4/17/15 through 5/8/15: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 9 (MLV 8-3 to 10-3): Pig Trap Modifications
--3/27/15 through 4/16/15: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 3/26/15 to 4/16/15.
"Station 9: Station Maintenance
--3/15/15 through 5/31/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 32: Station Maintenance
--7/1/15 through 10/31/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 47-4D to 54-4S: ILI/Cleaning Pig
--3/31/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 63: Station Maintenance
--5/6/15 through 11/2/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 63-4D to 71-4S: Anomaly Remediation
--5/4/15 through 5/26/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 71-3D to 79-3S: Anomaly Remediation
--5/26/15 through 7/12/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 79-3D to 82-3: Anomaly Remediation
--7/13/15 through 7/30/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 87: Station Maintenance
--4/6/15 through 4/10/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled TBD.
"Station 87: Unit Maintenance
--TBD: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations.
Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 90-5: Hydrotest
--4/20/15 through 5/1/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 96: Station Maintenance
--4/6/15 through 9/30/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 4/1/15 to 9/30/15.
"MLV 96-2D to 102-2R: Anomaly Remediation
--3/16/15 through 4/13/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 96-3D to 106-3S: ILI/Cleaning Pig
"MLV 96-4D to 106-4S: ILI/Cleaning Pig
"***MLV 96-1D to 106-1S: Anomaly Remediation
--5/4/15 through 11/30/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 4/14/15 to 5/4/15.
"***Station 106: Station Maintenance
--8/1/15 through 9/30/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 6/1/15 to 12/15/15.
"Station 110: Station Maintenance
--3/15/15 through 9/30/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 113-3: Hydrotest
--6/1/15 through 6/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 114: Station Maintenance
--4/1/15 through 6/30/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 117-2: Hydrotest
--3/26/15 through 4/22/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MS #450261 Pemex: Meter Station
--TBD: This project will require isolating the pipeline section. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
450621 Pemex
"***Station 409: Station Maintenance
--4/10/15 through 4/20/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 4/6/15 to 4/16/15.
"***MLV 705-1 to 706-1: Pipe Inspection/Repair
--2/9/15 through 4/13/15: This project involves inspecting and making repairs at multiple pipeline sites within the noted valve section. We anticipate being able to make repairs while the line is in-service, however there is a potential that the pipe repair may require replacement which will require isolation of the pipe. The listed meters may require shut-in, if isolation is needed. This may limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412688 Panola 2
410031 ETX GAS/TGP EAST TX PLANT DEHY PANO
412033 MARLIN/TGP CARTHAGE TRANSPORT PANOL
411200 Panola
412141 Enterprise
420723 ETP/TGP CARTHAGE GAS UNIT 13 PANOLA12141
411525 CHAPARRA/TGP BELLE BOWER DEHY PANOL
***Date change. Previously scheduled 2/9/15 to 3/30/15.
200 Line Outages
"MLV 200-4 to 200-4A: Anomaly Remediation
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 200-1 to 204-1: ILI/Cleaning Pig
--7/16/15 through 7/22/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 200-2 to 204-2: ILI/Cleaning Pig
--6/4/15 through 6/10/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 200-4B to 204-4: ILI/Cleaning Pig
--6/11/15 through 6/17/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 204: Station Maintenance
--TBD: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 204-1 to 209-1: ILI/Cleaning Pig
--6/23/15 through 6/25/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 4/23/15.
"***MLV 204-2 to 209-2: ILI/Cleaning Pig
--9/14/15 through 10/1/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 4/30/15.
"***MLV 204-3 to 209-3: ILI/Cleaning Pig
--8/25/15 through 8/27/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 5/14/15.
"***MLV 204-4 to 209-4: ILI/Cleaning Pig
--8/11/15 through 8/13/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 8/20/15.
"***MLV 204-4: Trap Modifications
--5/15/15 through 5/29/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Project Added
"MLV 206-1: Anomaly Remediation
"***MLV 206-2 to 207-2: Anomaly Remediation
--6/1/15 through 9/5/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 206-4: Hydrotest
--4/1/15 through 5/31/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 209: Station Maintenance
"***MLV 209-2 : Trap Modifications
--4/22/15 through 5/6/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 209-4: Trap Modifications
--5/6/15 through 5/20/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 209-1 to 214-1: ILI/Cleaning Pig
--4/21/15 through 4/23/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 6/25/15.
"***MLV 209-2 to 214-2: ILI/Cleaning Pig
--6/2/15 through 6/12/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 6/4/15.
"***MLV 209-3 to 214-3: ILI/Cleaning Pig
--7/23/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 7/23/15.
"***MLV 209-4 to 214-4: ILI/Cleaning Pig
--9/15/15 through 9/17/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 9/17/15.
"***MLV 210-1: Anomaly Remediation
--6/1/15 through 7/31/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 212-2: Hot Taps
--5/18/15 through 5/19/15: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 214-4: Trap Modifications
--5/25/15 through 6/8/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***MLV 214-4 to 219-4: ILI/Cleaning Pig
--9/29/15 through 10/1/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
***Date change. Previously scheduled 10/1/15.
"MLV 230-1 to 237-1: Anomaly Remediation
--5/14/15 through 6/14/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 237: Unit Maintenance
--3/30/15 through 4/2/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 237-1 to 245-1: ILI/Cleaning Pig
--4/30/15 through 5/11/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 241: Station Maintenance
--TBD: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 241: Unit Maintenance
--4/14/15 through 4/28/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 241-1: Anomaly Remediation
"Station 249: Unit Maintenance
--5/4/15 through 5/8/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 254: Unit Maintenance
--5/11/15 through 5/20/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Northhampton Lateral (260A-100): Cleaning Pig
--9/18/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 261: Unit Maintenance
--5/18/15 through 5/22/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 261-1 to 267-1: Anomaly Remediation
--4/20/15 through 10/31/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 261-1 to 262-1: Hydrotest
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 265: Station Maintenance
--4/11/15 through 4/25/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 264: Unit Maintenance
--4/7/15 through 4/9/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
--4/13/15 through 4/15/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 266A: Unit Maintenance
--5/11/15 through 5/15/15: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"266C-102 (Blackstone Lateral): Pipe Repair/Replacement
"MLV 270A-101.1 to 270A-102 : ILI/Cleaning Pig
--4/13/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 270C-303 to 270C-401 : ILI/Cleaning Pig
--4/15/15 through 4/16/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 270C-301 to 270C-302 : ILI/Cleaning Pig
--4/27/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
300 Line Outages
"MLV 300-1(219D-2D): Drip Removal
"Station 313: Station Maintenance
"MLV 314: Hot Taps (crossovers)
--TBD: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 317: Station Maintenance
--4/14/15 through 4/18/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 317: Unit Maintenance
--TBD: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 318: Hot Taps(crossovers)
"Station 319: Unit Maintenance
"Station 321: Unit Maintenance
"MLV 321-2 to 325-2: ILI/Cleaning Pig
--7/9/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 322: Hot Taps (crossovers)
"Station 323: Unit Maintenance
"Station 325: Station Maintenance
"MLV 325-1 to 329-1: ILI/Cleaning Pig
--7/16/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 329-1 to 336-1: ILI/Cleaning Pig
"MLV 342-1 to 343-1: Hydrotest
--8/1/15 through 9/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"Station 405A: Station Maintenance
500 Line Outages
"***MLV 541-1 to 545-1: Hydrotest
--6/15/15 through 7/20/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date change. Previously scheduled 5/20/15 to 6/23/15.
"***Station 542: Station Maintenance
--6/15/15 through 7/20/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 542-2 to 546-2 : Valve Replacment
--4/15/15 through 5/15/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***MLV 543-1 to 545-1 : Hydrotest
--6/15/15 through 8/3/15: This project will require taking the pipeline section out of service. The listed meter will need to be shut-in for the entire time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420294 PUGH MISSISSIPPI
***Date change. Previously scheduled 5/20/15 to 7/23/15.
"***MLV 545-3 : Pipe Replacement
--1/16/15 through 4/10/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.
Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 1/16/15 to 4/6/15.
"***MLV 545-2 : Pipe Replacement
--4/14/15 through 6/4/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 4/6/15 to 6/4/15.
"***MLV 546-2 to 550-2: Anomaly Remediation
--9/5/15 through 10/5/15: This project will require taking the pipeline section out of service. The listed meter will need to be shut-in for the entire time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
412134 FAYETTE
***Date change. Previously scheduled 4/1/15 to 4/14/15.
"MLV 547-1 to 548-1: Hydrotest
--10/10/15 through 11/10/15: This project will require taking the pipeline section out of service. The listed meter will need to be shut-in for the entire time. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
420765 DELTA PORTLAND BLACK (ABEERDEN - CHEMICAL PLANT)
411675 Greenwood Springs
"MLV 549-1: Hydrotest
--10/10/15 through 12/15/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 550-1: Hydrotest
--11/15/15 through 12/15/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 550-1 to 553-1: Hydrotest
--7/30/15 through 8/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
" MLV 550-2 to 555-2 : Valve Replacment
--5/20/15 through 6/20/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"MLV 554-1 to 555-1: Hydrotest
--9/5/15 through 10/5/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***MLV 558-1 to 559-1: Hydrotest
--5/27/15 through 6/24/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date change. Previously scheduled 5/20/15 to 6/20/15.
"***MLV 564-1 to 565-1: Hydrotest
--9/15/15 through 10/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
***Date change. Previously scheduled 4/15/15 to 5/15/15.
"Station 550: Station Maintenance
--9/5/14 through 3/31/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
--11/15/15 through 12/15/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"***Station 555: Station Maintenance
--4/20/15 through 4/24/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
"Station 555: Station Maintenance
--9/5/15 through 10/5/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP, SIP) nominations.
800 Line Outages
"Station 820: Station Maintenance
"MLV 820-1 to 823-1: ILI/Cleaning Pig
--4/29/15: This activity will require operating at controlled flow rates. The listed meters will need to be shut-in for the duration of the run (approx. 12 hours).Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, EDS/ERS, Payback to Tennessee, PAL-T (Parks/ Loan Paybacks), SOP) nominations.
412768 GLDNPASS/TGP STARKS LNG: RIP 820 10
412013 ENTRPRSE/TGP SABINE RIVER TRANS NEW
412737 LBERTYGS/TGP DE QUINCY GAS STORAGE
"Station 823: Station Maintenance
"MLV 823-1 and MLV 825-1 to 826-1: Pipe Inspection/Repair
--3/30/15 through 4/30/15: This project involves inspecting and making repairs at multiple pipeline sites within the noted valve section. We anticipate being able to make repairs while the line is in-service, however there is a potential that the pipe repair may require replacement which will require isolation of the pipe. The plan would be to identify the pipe replacement repairs, and come back at a later date to complete them. Most likely the replacements would occur in the late March – early April timeframe. The listed meters may require shut-in, if isolation is needed. This may limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 843-1B: Drip Removal/Hydro Test
--8/15/15 through 9/30/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"MLV 847-1: Hydrotest
--5/8/15 through 6/12/15: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
"***Station 860: Station Maintenance
--5/1/15 through 5/11/15: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
--5/27/15 through 6/24/15: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 860: Station Maintenance
--8/18/14 through 4/13/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 860(MLV 860-1): Station Maintenance
--3/21/15 through 3/27/15: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 860-1 to 866-1: ILI/Cleaning Pig
--5/19/15 through 5/21/15: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary out of the Path (PAL-D (Park Withdrawals/Loans), IT, AOT, EDS/ERS, Payback From Tennessee, PAL-T (Park Withdrawals/Loans), SOP) nominations.
If you have any questions, please contact your Scheduler.