TGP - Outage Impact ReportSeven Day Forecast (updated 1/28/2015)
-Major impact restrictions may be necessary
-Minor impact restrictions may be necessary depending on flow conditions
-Little to no impact, though minor outages may cause incremental reductions
Station # / Lateral
Est Nominal Design Capacity (Thousand Dth)
Saturday (1/31)
Sunday (2/1)
Monday (2/2)
Tuesday (2/3)
Wednesday (2/4)
Thursday (2/5)
Friday (2/6)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Station 409A (Alamo) (segment 492)
300
Station 409(Donna Line) (segment 490)
537
Station 1(segment 101) (backhaul)
240
Station 847 (segment 847)
650
455(195)
Sta. 860: Bi-directional Project (8/18/2014 - 3/2/2014)(500 lines 9/2 - 2/23)
Station 546 (segment 542) (backhaul)
940
870 (70)
871 (70)
872 (70)
873 (70)
874 (70)
870(70)
MLV 545-3 Class Change (1/16/2014 - 2/23/2015)
Station 860(segment 548) (backhaul)
996
890(106)
Station 110(segment 187) (south thru Kentucky)
1,737
1150(587)
1150 (587)
Sta. 200 Bi-directional/Filter (8/4/2014 - 2/28/2015)
Station 204 (200 line south thru Ohio)
-
1,200
Various Valve Sections from Sta. 200 to Sta. 219 Lines 1, 2, and 3 (4/28/2014 - 4/30/2015) Sta. 200 Bi-directional/Filter (8/4/2014 - 2/28/2015)
Station 237(segment 237)
1,069
515
Station 245 (segment 245)
1,067
Station 254 (segment 249)
1,243
Station 261 (segment 261)
961
Station 307(segment 307) (Backhaul)
1,153
Station 315(segment 315) (Backhaul)
1,710
Station 321 (segment 320)
1,795
Station 405A
800
650(150)
Emergent Repair Sta. 405A (12/8/2014 - 12/12/2014)