October 30, 2015Â Â Â
Â
TO:Â ALL TENNESSEE CUSTOMERS
RE:Â UPDATED TGP SCHEDULED OUTAGES
This notice is an update of planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART under Presentations
(Found under the Customer Information tab).
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.Â
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.Â
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***Meter #411525 Belle Bower :Â Meter Station
***Project Completed
………………………………"
"***Meter #411330 Chemard Lake Dehy:Â Meter Station
"***MLV 209-1 to 214-1:Â Anomaly Remediation
The following meters are available for nominations:
420091 NE OH NG/TGP LEESVILLE OH CARROLL
420065 LEESVILLE OHIOÂ
"***MLV 215-1 to 219-1:Â Anomaly Remediation
"***Station 245:Â Unit Maintenance
"***Station 315:Â Station Maintenance
"***Station 317:Â Station Maintenance
"***Station 319:Â Rose Lake Expansion Project
"***MLV 322-1:Â Class Change
420277 UGIPENN/TGP HONESDALE PA SALES WAYN
"***MLV 528 to 530 (lines 1 and 2):Â Station Abandonment
412629 Bayou Biloxi
100 Line Outages
"MLV 1-2D to 5-2:Â Anomaly Remediation
--11/10/14 through 11/21/14:  This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 9:Â ESD Test
--TBD: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 14E-101.3 to 14E-103:Â Anomaly Remediation
--TBD: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 17-3D to 20-3A:Â Anomaly Remediation
--TBD: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"21B-100 Lateral:Â Pipe Replacement
--12/19/14: This outage will require line isolation that will require the listed meter to shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
410306 TEXLA/TGP TOMBALL DEHY HARRIS
420898 EDFTRADE/TGP TOMBALL SALES NORTH MO
421028 CNTRPT/TGP DOWDELL ROAD HARRIS
"MLV 87-2 to 88-2:Â Hydrotest
--6/11/14 through 10/31/14: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 96:Â Station Maintenance
"MLV 108-2:Â Anomaly Remediation
--10/6/14 through 10/31/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 107:Â ESD Test
--10/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
200 Line Outages
"Station 200:Â Station Maintenance
--8/4/14 through 1/31/15: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 200-3A to 201-3:Â Anomaly Remediation
--11/3/14 through 11/25/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Project Added
"***MLV 204-2:Â Anomaly Remediation
--8/6/14 through 12/29/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 8/6/14 to 10/24/14.
"MLV 205-1:Â Pipe Inspection
--TBD: This project will require taking the pipeline section out of service.  This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 205-2:Â Anomaly Remediation
--5/24/14 through 12/29/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 5/24/14 to 10/24/14.
"***MLV 205-3:Â Anomaly Remediation
--8/27/14 through 11/24/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 8/27/14 to 10/24/14.
"***MLV 206-1:Â Anomaly Remediation
--12/1/14 through 12/25/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 11/1/14 to 12/18/14.
"MLV 206-2:Â Anomaly Remediation
--11/1/14 through 1/3/15: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 206-3:Â Anomaly Remediation
--9/8/14 through 11/24/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 9/8/14 to 10/24/14.
"***MLV 207-1:Â Anomaly Remediation
***Date change. Previously scheduled 11/8/14 to 11/13/14.
"***MLV 207-2:Â Anomaly Remediation
--11/1/14 through 12/29/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 11/1/14 to 12/2/14.
"MLV 207-3:Â Anomaly Remediation
--9/2/14 through 11/25/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 208-2:Â Anomaly Remediation
--7/21/14 through 12/29/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 7/21/14 to 10/24/14.
"***MLV 208-3:Â Anomaly Remediation
--9/2/14 through 11/24/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 9/2/14 to 10/24/14.
"***MLV 209-2:Â Anomaly Remediation
--8/11/14 through 10/31/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 8/11/14 to 10/24/14.
"MLV 209-2:Â Pipe Repair
"***MLV 211-2:Â Anomaly Remediation
--10/1/14 through 10/30/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 10/1/14 to 10/10/14.
"***MLV 212-2 &4:Â Hot Tap
--11/5/14 through 11/6/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations.  Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 10/13/14 to 10/16/14.
"MLV 212-3:Â Pipe Repair
"MLV 212-4:Â Pipe Repair
"***MLV 214-2 to 219-2:Â Anomaly Remediation
--10/29/14 through 11/17/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 10/15/14 to 11/11/14.
"***MLV 214-3 to 219-3:Â Anomaly Remediation
--11/17/14 through 11/25/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations.  Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 11/12/14 to 11/22/14.
"Station 224:Â Station Maintenance
--9/26/14 through 10/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 233:Â Station Maintenance
--11/3/14 through 11/4/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 241:Â Unit Maintenance
--11/10/14 through 11/14/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 245:Â Unit Maintenance
"Station 265:Â Station Maintenance
--10/20/14 through 11/5/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
300 Line Outages
"MS #021013:Â Meter Station
--TBD: This project will require isolating the pipeline section and for physical flow to be suspended at the listed meters for ~1 week. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 307:Â Station Maintenance
--11/10/14 through 11/12/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 313:Â ESD Test
--12/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 319:Â Station Maintenance
"Station 325:Â Station Maintenance
"Station 325:Â ESD Test
500 Line Outages
"MLV 507G-101 to 507G-109A:Â Anomaly Remediation
--3/1/14 through 12/31/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 542:Â Station Maintenance
--10/15/14 through 11/16/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 542(MLV 542-1):Â Station Maintenance
--11/6/14 through 11/16/14: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 542(MLV 542-2):Â Station Maintenance
--10/27/14 through 11/5/14: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 550:Â Station Maintenance
--9/5/14 through 11/25/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 550(MLV 550-1):Â Station Maintenance
--9/10/14 through 11/4/14: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 550(MLV 550-2):Â Station Maintenance
--11/5/14 through 11/19/14: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 551-2 to 552-2:Â Hydrotest/Pipe Inspection
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
800 Line Outages
"MLV 847-1:Â Hydrotest/Valve Installation
--TBD: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 860:Â Station Maintenance
--8/18/14 through 12/19/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 860(MLV 559-1):Â Station Maintenance
--9/2/14 through 11/15/14: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 860(MLV 559-2):Â Station Maintenance
"Station 860(MLV 860-1):Â Station Maintenance
--11/15/14 through 12/8/14: This project will require a station outage that requires tie-ins to the mainline, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 871:Â Station Maintenance
--9/2/14 through 12/1/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 871(MLV 871-1):Â Station Maintenance
--10/6/14 through 10/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
If you have any questions, please contact your Scheduler.