July 25, 2014 TO: ALL TENNESSEE CUSTOMERS PROJECT UPDATE: MLV 200-2B Anomaly Remediation
This notice is to inform customers of an update for the MLV 200-2B Anomaly Remediation as detailed below. "***MLV 200-2B: Anomaly Remediation
--7/14/14 through 8/1/14: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in on 7/31 and 8/1. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
421018 - DUKE AM/TGP HANGING ROCK SCIOTO
***Date change. Previously scheduled 7/14/14 to 7/29/14.
………………………………"
If you have any questions, please contact your Scheduler