April 24, 2014
TO: ALL TENNESSEE CUSTOMERS
RE: UPDATED TGP SCHEDULED OUTAGES
This notice is an update of planned outages and maintenance
activities on Tennessee Gas Pipeline.
The Outage and Maintenance schedule is available in an Excel
spreadsheet format which may be found in DART under Presentations
(Found under the Customer Information tab).
Some projects may reduce capacity to a level below anticipated
demand (nominations), or require taking individual meters out of
service.
For each project, based upon anticipated demand, the highest
level of service Tennessee expects to be impacted is noted.
Unless noted otherwise, all impacts are in the Supply to Market
direction.
Projects may be added, altered, delayed or canceled. Tennessee
will provide updates by posting revisions on a weekly basis or
more often if necessary.
Projects revised or added since the last posting are preceded
by ***. Within the Excel Spreadsheet and Adobe Files, revisions
are highlighted and an asterisk has been added to the "Revised"
column.
Unless otherwise noted, all listed meters will be physically shut
-in for the duration of the project.
Unless otherwise noted, all scheduled dates represent gas days
as defined in the Tennessee Gas Pipeline tariff to mean a period
of twenty-four consecutive hours, beginning and ending at 9:00
a.m. (Central Clock Time).
=========================
Completed Outages
"***MLV 110-2 to 114-2S: Anomaly Remediation
***Project Completed
The following meters are available for nominations:
412742 GLANCY FORK
………………………………"
"***MLV 245-2 to 249 -2: Anomaly Remediation
"***MLV 256C-101.1 to 256C-102: Anomaly Remediation
"*** MLV 542-1 to 546-1: ILI/Cleaning Pig
100 Line Outages
"MLV 1-2D to 2-2: Hydrotest
--4/6/14 through 5/18/14: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412669 ETP/TGP SHOUP NUECES
411306 ENTRPRSE/TGP AGUA DULCE NUECES
412603 Magnus/TGP Wildcat Welder Heirs 5H
412221 AROC TX/TGP ODEM DEHYDRATION SAN PA
412270 TRANSAMERICAN INTERCONNECT
412062 BANQUETE TRANSPORT
412196 NORTH BRAYTON DEHYDRATION
"MLV 1-2D to 5-2: Anomaly Remediation
--10/1/14 through 10/31/14: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 9: ESD Test
--8/27/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 14E-101.3 to 14E-103: Anomaly Remediation
--TBD: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 17-1D to 20-1A: Anomaly Remediation
--9/1/14 through 10/31/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 17-2D to 20-2A: Anomaly Remediation
"MLV 17-3D to 20-3A: Anomaly Remediation
"MLV 19-2: Class Change
--3/20/14 through 5/7/14: This project will require taking the pipeline section out of service and for the listed meter to be physically shut-in for the listed dates. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
411788 - DCP GLP/TGP KATY TRANSPORT WALLER
" MLV 24-2 to 25-2S: ILI/Cleaning Pig Re-run
--5/13/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412361 FAULCONER TAP
420768 NECHES TGP DELIVERY
"Station 25: ESD Test
--TBD: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 25-2D to 32-2S: ILI/Cleaning Pig
--5/12/14 through 5/15/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 25-3D to 32-3S: ILI/Cleaning Pig
--5/8/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 32: ESD Test
--9/9/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 40-3 to 47-3: Anomaly Remediation
--4/17/14 through 5/4/14: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 47-1D to 54-1S: Anomaly Remediation
--4/14/14 through 5/9/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 53-4: Class Change
--5/8/14 through 6/27/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 54: ESD Test
--8/13/14 through 8/14/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 54-2 to 56-2: Hydrotest/Valve Installation
--7/15/14 through 9/15/14: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 54-2D to 63-2S: ILI/Cleaning Pig
--5/6/14 through 5/29/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 54-4D to 63-4S: ILI/Cleaning Pig
--5/20/14 through 6/4/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 59-1: Class Change
--6/23/14 through 7/11/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 63-3D to 71-3S: ILI/Cleaning Pig
--4/17/14 through 4/24/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 67-2: Hydrotest
--9/8/14 through 10/3/14: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 77-1B to 78-1: Anomaly Remediation
--3/31/14 through 5/2/14: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 84-3: Class Change
--8/18/14 through 8/29/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 84-4: Class Change
--8/4/14 through 8/15/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 87: ESD Test
--9/17/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 87-2 to 88-2: Hydrotest
--6/2/14 through 8/5/14: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 97-3: Class Change
--6/2/14 through 7/1/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 97-4: Class Change
--7/7/14 through 8/6/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 106-2D to 110-2: Anomaly Remediation
--8/11/14 through 9/19/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 107: ESD Test
--10/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Valve 114-CS1 to MLV 114-3A: Abandonment
--TBD: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
411347 Big Beech Fork Dehyd
***Date change. Previously scheduled 4/28/14 to 5/15/14.
"MLV 110-2 to 114-2S: Anomaly Remediation
"Station 114: ESD Test
--7/30/14 through 7/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 118-1 to 121-1: Anomaly Remediation
--9/29/14 through 10/4/14: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled TBD.
"MLV 406A-101.1 to 406A-102: Anomaly Remediation
--TBD: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 406B-101.2 to 406B-102: Anomaly Remediation
"MLV 406B-201 to 406B-502: Anomaly Remediation
--8/1/14 through 8/31/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 407A-103 to 407A-103A: Anomaly Remediation
--11/1/14 through 11/30/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 407D-101.2 to 407D-102: Anomaly Remediation
"Station 409: ESD Test
--4/25/14 through 4/27/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 700-1 to 707-1: Maintenance Pig
--5/6/14: This project will require controlled flows which could result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 700-1 to 707-1: Anomaly Remediation
--7/1/14 through 9/30/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
200 Line Outages
"***MLV 200 to 219 (Lines 1,2,3,4): Anomaly remediation/pipe replacement/Hydrotest
--6/1/13 through 5/30/14: These outages will require pressure reductions and/or pipeline isolations. These pressure reduction/valve isolations should not affect the capacity of the supply to market. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SIP) nominations.
***Date change. Previously scheduled 6/1/13 to 4/30/14.
"Station 200: Station Maintenance
--7/29/14 through 12/1/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 200-1B: Anomaly Remediation
--4/21/14 through 5/9/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 200-2D: Class Change
--7/14/14 through 7/25/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 200-2B: Anomaly Remediation
--5/12/14 through 5/23/14: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for 1-2 days within this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
421018 - DUKE AM/TGP HANGING ROCK SCIOTO
" MLV 200-3B to 204-3: ILI/Cleaning Pig
--TBD: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 200-3A: Anomaly Remediation
--5/26/14 through 6/9/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 200-3B to 204-3: Anomaly Remediation
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 203-1: Anomaly Remediation
--4/28/14 through 5/5/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 5/30/14 to 6/3/14.
"MLV 203-3: Anomaly Remediation
--6/6/14 through 6/11/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 203-4: Pipe Replacement
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 204-1 to 209-1: Anomaly Remediation
--4/28/14 through 5/12/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 6/3/14 to 6/6/14.
"MLV 204-2: Anomaly Remediation
--4/21/14 through 5/10/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 204-2 to 209-2: Anomaly Remediation
--6/9/14 through 6/13/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 204-3 to 209-3: Anomaly Remediation
--6/16/14 through 7/19/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 205-1: Anomaly Remediation
***Date change. Previously scheduled 5/11/14 to 6/3/14.
"MLV 205-1: Pipe Inspection
"MLV 205-2: Anomaly Remediation
--5/22/14 through 8/11/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 205-3: Anomaly Remediation
--8/13/14 through 9/11/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 206-1: Anomaly Remediation
--8/23/14 through 10/9/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 206-2: Anomaly Remediation
--5/12/14 through 7/12/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 206-3: Anomaly Remediation
--8/6/14 through 9/4/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 207-1: Anomaly Remediation
--10/4/14 through 10/9/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 207-2: Anomaly Remediation
--7/8/14 through 8/7/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 207-3: Anomaly Remediation
--8/11/14 through 10/3/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 208-1: Anomaly Remediation
--5/5/14 through 5/9/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 208-2: Anomaly Remediation
--5/12/14 through 6/19/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 208-3: Anomaly Remediation
--6/12/14 through 7/2/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Station 209: Station Maintenance
--6/16/14 through 6/18/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Project Added
"Station 209: ESD Test
--7/28/14 through 8/1/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 209-1: Anomaly Remediation
--6/28/14 through 7/3/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 209-2: Anomaly Remediation
--7/7/14 through 7/14/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 209-2: Pipe Repair
"MLV 209-3 to 214-3: Anomaly Remediation
--4/7/14 through 4/26/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 209-3: Anomaly Remediation
--7/17/14 through 7/21/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 210-3: Class Change
--3/17/14 through 5/23/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 3/17/14 to 5/15/14.
"MLV 210-3: Anomaly Remediation
--7/24/14 through 8/4/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 211-2: Anomaly Remediation
--8/11/14 through 8/18/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 211-3: Anomaly Remediation
--8/6/14 through 8/11/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 212-2: Hot Tap
--5/13/14 through 5/19/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 4/30/14 to 5/5/14.
"MLV 212-3: Anomaly Remediation
--7/30/14 through 8/2/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 212-3: Pipe Repair
"***MLV 212-4: Hot Tap
***Date change. Previously scheduled 4/29/14 to 4/30/14.
"MLV 212-4: Pipe Repair
"Station 214: Station Maintenance
--4/14/14 through 4/28/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 214: ESD Test
--7/15/14 through 7/24/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 214-1: Anomaly Remediation
--7/21/14 through 7/26/14: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
420066 - DOMINION/TGP AUGUSTA OH CARROLL
"MLV 214-1 to 219-1: Anomaly Remediation
--7/21/14 through 7/29/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 214-2 to 219-2: Anomaly Remediation
--7/30/14 through 8/23/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 214-3: Anomaly Remediation
--7/14/14 through 7/17/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 214-3 to 219-3: Anomaly Remediation
--8/25/14 through 9/13/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 215-4: Hydrotest
--4/14/14 through 4/29/14: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 4/14/14 to 4/25/14.
"MLV 216-4: Hot Tap
--5/19/14 through 5/22/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412879 Hickory Bend
420932 E OH GAS/TGP PETERSBURG MAHONING
"MLV 217A-101.1 to 217A-104: Anomaly Remediation
"MLV 217-3: Anomaly Remediation
--7/7/14 through 7/10/14: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412873 - HEC/TGP PULASKI: RIP 217C 101.3 LAW
"MLV 218-2: Hot Tap
--6/9/14 through 6/22/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 218-4: Hot Tap
"Station 219: ESD Test
--9/8/14 through 9/15/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 229: ESD Test
--9/25/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 230C: Station Maintenance
--8/1/14 through 10/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 230C: ESD Test
"Station 233: ESD Test
--5/20/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 233: Station Inspection
--5/21/14 through 5/22/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 237: ESD Test
--9/24/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 237-2 to 245-2: ILI/Cleaning Pig
--5/14/14 through 6/3/14: This activity will require operating at controlled flow rates for two days in this time frame. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Primary In the Path (Loan, Park Withdrawal, IT-X, IT, AOT, PAT, Payback From Tennessee, EDS/ERS, PIP) nominations.
"Station 241: ESD Test
--5/7/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 245: ESD Test
--5/12/14 through 5/16/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Station 245: Unit Maintenance
--5/5/14 through 5/16/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Station 245: Station Maintenance
***Date change. Previously scheduled 5/5/14 to 5/16/14.
"Station 245: Unit Maintenance
--4/7/14 through 4/28/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 249: ESD Test
--5/22/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 249: Unit Maintenance
--5/19/14 through 6/6/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Station 249: Unit Maintenance
--6/16/14 through 6/20/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 249-2&3: Hot Tap/Meter Station
--6/1/14 through 6/31/2014: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412181 Wright Meter Station
***Date change. Previously scheduled 5/15/14 to 7/15/14.
" MLV 249-1 to 254-1: ILI/Cleaning Pig
--7/23/14 through 8/5/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 249-2 to 254-2: Anomaly Remediation
--7/28/14 through 9/12/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 249-3A to 251-3: Anomaly Remediation
--9/2/14 through 9/12/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 254: ESD Test
--5/13/14 through 5/14/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 254-2 to 261-2: Anomaly Remediation
--4/29/14 through 7/26/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 5/5/14 to 7/26/14.
"Station 260A: ESD Test
--10/8/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 261: ESD Test
--5/28/14 through 5/29/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 261: Unit Maintenance
--4/28/14 through 4/30/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 264: ESD Test
--9/15/14 through 9/18/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 264: Station Maintenance
--5/1/14 through 5/2/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Station 265: ESD Test/Maintenance
--4/21/14 through 5/24/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 4/21/14 to 4/25/14.
"MLV 265E-101.1 to 265E-104: Anomaly Remediation
--4/21/14 through 5/17/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 266A: ESD Test
--9/17/14 through 9/18/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 267: ESD Test
--8/20/14 through 8/21/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 269-1: Hot Tap
--7/15/14 through 7/18/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Concord Lateral (270B-100) and (273C-100): Hot taps: Hot Tap
--4/21/14 through 4/25/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 270B-601: Anomaly Remediation
--7/1/14 through 9/30/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 270B-501 to 270B-501D: ILI/Cleaning Pig
--8/12/14 through 8/13/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
300 Line Outages
"MS #021013: Meter Station
--TBD: This project will require isolating the pipeline section and for physical flow to be suspended at the listed meters. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"White Plains MS: Meter Outage
--6/11/14 through 6/13/14: This project will require isolating the pipeline section for approximately 10 days within this timeframe. Physical flow will be suspended. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
420093 CON ED/TGP WHITE PLAINS NY WESTCHES
"MLV 302-1 to 303-1: Anomaly Remediation
--9/17/14 through 11/1/14: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 303A: ESD Test
--7/2/14 through 7/3/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 303-1 to 304-1: Anomaly Remediation
"MLV 304-1 to 305-1: Anomaly Remediation
--9/17/14 through 11/1/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 305-1 to 306-1: Anomaly Remediation
"MLV 306-1 to 307-1: Anomaly Remediation
"***MLV 307-2 to 313-2: Anomaly Remediation
--4/28/14 through 5/12/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 4/28/14 to 5/10/14.
"Station 307: ESD Test
--8/13/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 310-1 & 2: Hot Tap
--6/23/14 through 7/3/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412808 - EOG/TGP CLERMONT DEHY: RIP 310C 101
***Date change. Previously scheduled 7/7/14 to 7/11/14.
"Station 313: ESD Test
--12/31/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 313-1: Hydrotest
--7/1/14 through 9/30/14: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary in the Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SIP) nominations.
"MLV 313G-101 to 313G-102: Anomaly Remediation
--5/13/14 through 5/16/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 315: Rose Lake Expansion Project
--7/15/14 through 10/1/14: This project will require a station outage, which could limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 317: Rose Lake Expansion Project
--4/1/14 through 7/14/14: This project will require a station outage, which could limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 317-2: Hot Tap
--5/19/14 through 5/25/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 319: Rose Lake Expansion Project
--4/21/14 through 10/1/14: This project will require a station outage, which could limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 320-2: Hot Tap
--6/15/14 through 6/20/14: Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 5/19/14 to 5/25/14.
"***Station 321: Station Maintenance
***Date change. Previously scheduled 4/29/14.
"Station 321: Station Maintenance
--7/7/14 through 7/14/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 322-1: Class Change
--10/15/14 through 11/1/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
420277 UGIPENN/TGP HONESDALE PA SALES WAYN
"***Station 323: Station Maintenance
--5/8/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 5/1/14.
"Station 323: Station Maintenance
--7/21/14 through 7/28/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 324-1A: Class Change/Hydrotest
--9/22/14 through 10/15/14: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 325: Unit Maintenance
--4/28/14 through 5/2/14: This project will require a unit outage, which could limit throughput through the station and result in restrictions based on customer nominations Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Station 325: Station Maintenance
--5/9/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 5/2/14.
"Station 325: Station Maintenance
--7/28/14 through 8/4/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 325: ESD Test
--9/14/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV334A-102 (from Meter) to end of line: ILI/Cleaning Pig
--6/23/14 through 6/27/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 334A-101.1 (Con Ed): Pipe Inspection
--6/2/14 through 6/6/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 6/23/14 to 6/27/14.
"Station 405A: ESD Test
--4/29/14 through 5/1/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***Station 405A: Station Inspection
--5/13/14 through 5/15/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 405A: Valve Replacement
--8/18/14 through 9/18/14: This project will require taking the pipeline section out of service and for physical flow to be suspended at the listed meter. No other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
500 Line Outages
"Bear Creek Storage: Test
--4/22/14 through 4/28/14: This outage may require pressure reductions. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 507G-1010 to 507G-1011: Anomaly Remediation
--6/1/14 through 6/27/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 507G-101 to 507G-109A: Anomaly Remediation
--5/1/14 through 5/30/14: This outage will require pressure reductions that may limit flows from the listed meter, and possibly line isolations that would require the listed meter to be physically shut-in. However no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"***MLV 511-1: Class Change
--7/14/14 through 7/22/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
412398 JEFFSTOR/TGP JEFFERSON ISLAND IBERI
020915 Trans LA
050054 Kinder Coastal Check
410907 TRUNKLNE/TGP CENTERVILLE DEHY TRANS
412594 NAUTILUS/TGP GARDEN CITY ST MARY
011669
***Date change. Previously scheduled 6/9/14 to 6/17/14.
"***MLV 515-1: Class Change
"MLV 516-1 to 522-1: Pipe Replacement
--6/30/14 through 7/12/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
1-1807/2-0553 LIG-Centerville
412684 ANR/TGP SHADYSIDE ST MARY
2-0500-1 KOCH Centerville Sales
412705 MTBB/TGP MARTIN WELL 1 ST MARY
1-0527 E.I. Block 18
1-0397 Halter Island line
412843 CAB OIL/TGP PENCHANT CLF 34 1: RIP
412233 WHTOKOG/TGP BAYOU PENCHANT DEHY TER
1-0415 Apache Bayou Penchant
"Station 527: ESD Test
--6/30/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 538: ESD Test
--6/26/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 542: Station Maintenance
--8/26/14 through 10/28/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 542: ESD Test
--10/14/14 through 10/15/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 542-2 to 546-2: ILI/Cleaning Pig
--5/15/14: This activity will require operating at controlled flow rates for 2-3 days in the listed timeframe. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 546: Station Maintenance
--6/24/14 through 9/1/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 546-1: Class Change
--8/11/14 through 10/1/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 546-2: Class Change
--6/23/14 through 8/8/14: This project will require taking the pipeline section out of service. This will limit throughput and will result in restrictions based on customer nominations. Customers may experience pressure fluctuations during this timeframe. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 550: Station Maintenance
--9/5/14 through 11/7/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 551-2 to 552-2: Hydrotest/Pipe Inspection
--TBD: This project will require taking the pipeline section out of service. This will limit throughput and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
800 Line Outages
"Station 823: ESD Test
--10/2/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 827-1 to 834-1: Anomaly Remediation
--5/19/14 through 5/23/14: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 838: Station Maintenance
--6/11/14 through 6/25/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 838-1 to 843-1: ILI/Cleaning Pig
--6/5/14 through 6/10/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 847-1: Hydrotest/Valve Installation
--TBD: This outage will require the pipeline to be taken out of service and for the listed meter to be physically shut-in for the listed dates. For the duration of the project, pressures may be lower. This project may limit throughput and could result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
" MLV 851-1 to 856-1: ILI/Cleaning Pig
--4/16/14 through 4/23/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"MLV 856-1 to 860-1: Anomaly Remediation
--3/10/14 through 6/27/14: This outage will require pressure reductions/valve isolations. Customers may experience pressure fluctuations and may result in restrictions based on customer nominations. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"Station 860: Station Maintenance
--7/28/14 through 11/7/14: This project will require a station outage, which will limit throughput through the station and may result in restrictions based on customer nominations. Customers may experience an increase in pressures during this time. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
"*** MLV 860-1 to 866-1: ILI/Cleaning Pig
--5/2/14 through 5/8/14: This activity will require operating at controlled flow rates. Customers may experience pressure fluctuations, however, no other service impact is anticipated. Potential restrictions through a pro-rata portion of Secondary Out of Path (PAL-D (Parks/Loan Paybacks), IT, AOT, Payback From Tennessee, PAL-T (Parks/Loan Paybacks), EDS/ERS, SOP) nominations.
***Date change. Previously scheduled 5/1/14 to 5/8/14.
"Station 871: Station Maintenance
If you have any questions, please contact your Scheduler.