Revision:
RACCOON HOLLOW TO LOVE RANCH (Segment 190): Conn Creek Compressor Station, TransColorado is updating the Station maintenance August 1 through September 21 and extending through October 5.
1. RACCOON HOLLOW TO LOVE RANCH (Segment 190): Conn Creek Compressor Station, TransColorado will be performing Station maintenance August 1 through October 5. This outage results in the following impacts.
Northbound
Operating Capacity
Capacity Reduction
Limit MDth/d
August 1 thru October 5
441
308
Southbound
354
297
TRANSCOLORADO Pipeline Company
Operations Planning Report for September 2018
Issued August 21, 2018
Reissued September 10, 2018
TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE
2. OLATHE C.S. TO RED VALE C.S. (Segment 230): Redvale Compressor Station, TransColorado will be performing Unit mechanical inspection September 19. This outage results in the following impact.
Sept 19 Cycles 1 thru 3
250
200
Sept 19 Cycles 4 thru 5
231**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
3. DOLORES C.S. TO MANCOS C.S. (Segment 250): Mancos Compressor Station, TransColorado will be performing Unit mechanical inspections one unit at a time September 12 and September 13. This outage results in the following impacts.
Limit MDth/d*
Sept 12 Cycles 1 thru 3
225
Sept 12 Cycles 4 thru 5
241**
Sept 13 Cycles 1 thru 3
Sept 13 Cycles 4 thru 5
Any comments or questions about this report should be directed to Glen Petty (719) 520-4704 or Bill McMillan (719) 520-4389.