TSP/TSP Name:  938939154-TRANSCOLORADO GAS TRANS CO LLC Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  03/21/2017 2:06:48PM Notice End Date/Time:  04/20/2017 9:00:00am
Post Date/Time:  3/21/2017 2:06:48 PM Notice ID: 116455
Reqrd Rsp:  1 Rsp Date:  03/21/2017
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  Operations Planning Report, April 2017
Notice Text:

TRANSCOLORADO Pipeline Company

Operations Planning Report for April 2017

Issued March 21, 2017

TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE

1. Olathe Compressor Station (Segment 220): Olathe Compressor Station, TransColorado will be performing Station DOT/ESD Test and unit mechanical inspection April 25. This outage will result in the following impacts.

Operating Capacity

Capacity Reduction

Limit MDth/d

Limit MDth/d

April 25 Cycles 1 thru 4

368

337

April 25 Cycle  5

368

    351**

** The nomination limit for this cycle has been prorated for the remaining time in the gas day.

2. Conn Creek Compressor Station (Segment 190): Conn Creek Compressor Station, TransColorado will be performing Station DOT/ESD Test April 26 .This outage results in the following impacts.

Operating Capacity

Capacity Reduction

Limit MDth/d

Limit MDth/d

April 26 Cycles 1 thru 4

368

312

April 26 Cycle 5

368

     337**

** The nomination limit for this cycle has been prorated for the remaining time in the gas day.

Any comments or questions about this report should be directed to Glen Petty (719) 520-4704 or Bill McMillan (719) 520-4389.

 

..