Notice Detail
           
Return To Results
TSP/TSP Name:  6900518-SOUTHERN NATURAL GAS CO. Critical: Y
Notice Type Desc (1):  FORCE MAJEURE Notice Type Desc (2):  FORCE MAJEURE
Notice Eff Date/Time:  07/21/2017 9:19:59AM Notice End Date/Time:  08/20/2017 9:00:00am
Post Date/Time:  7/21/2017 9:19:59 AM Notice ID: 701321
Reqrd Rsp:  1 Rsp Date:  07/21/2017
Notice Stat Desc:  SUPERSEDE Prior Notice:  701231
Subject:  Force Majeure Update #12 - Segment 580
Notice Text:

Force Majeure Update #12 – Segment 580 

 

As set forth in Critical Notice 701231, and previous postings, Southern Natural Gas Company, L.L.C. (“SNG”) experienced a release of natural gas and damage to its 20” Wrens-Savannah 2nd Loop Line near Millen, GA on October 8, 2016. As stated in Notice 700811 on January 25, 2017, SNG is performing hydrostatic tests on segments encompassing the entire 20” Wrens-Savannah 2nd Loop Line in order to identify and make those repairs needed to be able to return the line to full pressure and capacity in a safe manner.  Until all such work is complete, operationally available capacity through Segment 580 will remain reduced as posted. SNG is working diligently with multiple crews to return this line to full service as soon as possible.  

 

Update #12:  SNG has made significant progress implementing its work schedule with multiple crews.  Based on the best information available, SNG estimates that the outage will continue into September 2017.  Some portions of this line have been put back in service and capacity adjusted as stated in Critical Notice 701251 to recognize the additions of the line that are now in service. Further SNG also estimates more portions of this line may be back in service in August. SNG will have more information available by its next update to customers on August 23, 2017.

 

As set forth in Critical Notice 700504, this unplanned outage constitutes an event of Force Majeure under Section 8.3 of the General Terms and Conditions of SNG's FERC Gas Tariff until further notice.   

 

We will continue to update you on the progress of the work. The next update will be posted by August 23, 2017.  If you have any questions regarding this notice, please contact your Account Manager or Scheduling Representative.

 

SNG Gas Control

..