SEGMENT 28 - GC#1 - INSTALL LAUNCHER AND RECEIVER – UPDATE #3
Due to difficulties with ground stabilization the completion date for this outage has changed, as noted below. This notice was last posted on June 10, 2022, “SEG 28 – GC#1 – INSTALL LAUNCER/RECEIVER – UPDATE #2”.
As previously posted on Natural's Outage Impact Report (X21-1162611), on the dates noted below, Natural is performing pipeline maintenance to install pigging facilities on the GC#1 line near Compressor Station 312 (CS 312) located in Livingston County, Illinois (Segment 28 of Natural's IOWA-ILL Zone). As a result, Natural is required to temporarily reduce the capacity at LOC 37207 Alliance Jolliet #1 to 200,000 Dth for the duration of this outage.
INSTALL DATES:
Gas Day Tuesday, April 26, 2022, and continuing through gas day Thursday, June 30, 2022 (Previously Saturday, June 25, 2022)
Continue to monitor Natural's interactive website for any updates to the end date and/or scheduling percentages during this outage.
Please contact your Account Director or Scheduling Representative if you have any questions.