TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  FORCE MAJEURE Notice Type Desc (2):  FORCE MAJEURE
Notice Eff Date/Time:  07/29/2020 10:20:19AM Notice End Date/Time:  08/28/2020 9:00:00am
Post Date/Time:  7/29/2020 10:20:19 AM Notice ID: 41253
Reqrd Rsp:  1 Rsp Date:  07/29/2020
Notice Stat Desc:  SUPERSEDE Prior Notice:  41230
Subject:  FORCE MAJEURE-SEG 11-AM#3-PIPE REMED-UP2
Notice Text:

FORCE MAJEURE – SEGMENT 11 – AM #3 M/L – PIPELINE REMEDIATION – UPDATE #2

 

Due to inclement weather, the end date for this force majeure has been extended, as noted below.  This notice was last posted on July 21, 2020, entitled “FORCE MAJEURE – SEGMENT 11 – AM #3 M/L – PIPELINE REMEDIATION – UPDATE #1”.

 

As previously posted on Natural's interactive website, as part of its ongoing pipeline Integrity Management Program and the final graded results of an ILI AFD tool run, Natural is required to perform pipeline remediation work on the Amarillo #3 mainline between Compressor Station 103 (CS 103) located in Ford County, Kansas and Compressor Station 104 (CS 104) located in Barton County, Kansas (Segment 11 of Natural's Midcontinent Zone).  This is a Force Majeure event that limits Natural's throughput capacity northbound out of the Midcontinent Zone.  As a result of this force majeure event, Natural will temporarily reduce the maximum operating pressure in the area.

 

The scheduling constraint will be at CS 104; therefore, any gas received south of CS 104 for delivery north of CS 104 will be impacted for the duration of this outage.  For scheduling purposes, the Midcontinent Pool (LOC 25078) is located south of the constraint.  Firm transportation nominated from receipt points south of CS 104 (including the Midcontinent Pool) for injection at any Amarillo storage point will be impacted.

 

As such, effective for gas day, Tuesday, July 7, 2020, Timely Cycle, and anticipated to continue through gas day Wednesday, August 5, 2020, (previously Friday, July 31, 2020), Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 43% of contract MDQ through CS 104.  Actual nomination levels and changes in pipeline conditions could result in changes to the percentages scheduled (lower or higher) on subsequent gas days.  AOR/ITS and Secondary out-of-path Firm transports will not be available.

 

The stated scheduling percentage is based upon the current level of firm capacity contracted for during this outage and is subject to change based upon operational conditions and Shipper utilization.

 

Continue to monitor Natural's interactive website for any updates to the end date and/or scheduling percentages during this outage.

 

Please contact your Account Director or Scheduling Representative if you have any questions.

....