SEGMENT 27 SOUTHBOUND – GULF COAST #2 & #3 M/L (CS 305) – INSTALL LAUNCHER & RECEIVER – UPDATE #3
The project dates have been changed, as noted below. This notice was last posted on December 21, 2018, entitled “JANUARY 2019 – SCHEDULED MAINTENANCE PROJECTS”.
On gas day Thursday, January 31, 2019, and continuing through gas day Friday, March 8, 2019, (previously Tuesday, January 22, 2019 through Sunday, January 27, 2019) Natural will be performing pipeline maintenance to install pigging facilities on the Gulf Coast #2 and #3 lines near Compressor Station 305, located in Miller County, Arkansas (Segment 27 of Natural's Gulf Coast Mainline Zone). AOR/ITS and Secondary out-of-path Firm transports may not be available during this work. Primary Firm and Secondary in-path Firm transports may also be at risk of not being fully scheduled.
Please contact your Account Director or Scheduling Representative if you have any questions.