TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  07/21/2017 2:53:06PM Notice End Date/Time:  08/20/2017 9:00:00am
Post Date/Time:  7/21/2017 2:53:06 PM Notice ID: 37622
Reqrd Rsp:  1 Rsp Date:  07/21/2017
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  SEG 11-AM#2 (CS105/106) LAUNCH&REC-UPD#3
Notice Text:
MAY 2012 – SCHEDULED MAINTENANCE PROJECTS

SEGMENT 11 – AMARILLO #2 (CS 105/106) – INSTALL LAUNCHER & RECEIVER – UPDATE #3

 

The project dates have been changed for all three phases, as noted below.  This notice was last posted on July 14, 2017, entitled “SEGMENT 11 – AMARILLO #2 (CS 105/106) – INSTALL LAUNCHER & RECEIVER – UPDATE #2”.

 

On gas day Monday, July 10, 2017, and continuing through gas day September 6, 2017 (previously continuing through gas day Thursday, August 31, 2017), Natural will be performing pipeline maintenance to install pigging facilities on the Amarillo #2 mainline between Compressor Station 105, located in Cloud County, Kansas, and Compressor Station 106, located in Gage County, Nebraska (Segment 11 of Natural's Midcontinent Zone).  This maintenance work will now have an impact and will also be performed in three phases to minimize the duration of the impact.  The Black Hills Beatrice Gage CDP delivery location (LOC 48273) will be shut-in for the duration of each phase as listed below.  No transport services will be available.  No other receipt or delivery locations in this area will be impacted.

 

Phase I – will begin on gas day Thursday, July 27, 2017 and anticipated to continue through gas day Monday, July 31, 2017 (previously Tuesday, July 25, 2017, and anticipated to continue through gas day Saturday, July 29, 2017).

 

Phase II – will begin on gas day Tuesday, August 8, 2017, and anticipated to continue through gas day Saturday, August 12, 2017 (previously Tuesday, August 1, 2017, and anticipated to continue through gas day Saturday, August 5, 2017).

 

Phase III – will begin on gas day Wednesday, August 30, 2017, and anticipated to continue through gas day Tuesday, September 5, 2017 (previously Thursday, August 24, 2017, and anticipated to continue through gas day Wednesday, August 30, 2017).

 

Please continue to monitor Natural's interactive website for any updates to this outage.

 

Please contact your Account Director or Scheduling Representative if you have any questions.

 

....