Mojave Pipeline Company
Update Notice of October 2017 Maintenance
October 9, 2017
The following is the current projection of maintenance that will occur on the
Mojave Pipeline Company pipeline during the month of October. If these scheduled activities change, updated notices will be posted as soon as possible. Changes are denoted by asterisks**.
**MOJAVE MAINTENANCE
**Mojave Unit 3 mechanical repair; Oct 5 thru Oct 10 completed early
Mojave Unit(s) mechanical maintenance; Oct 17 thru Oct 19
Daggett Station reliability Run Test for 4 hrs; Oct 17 informational only
From an estimated base capacity of 460 MDthd at TOPOCKM (EPMOJAVE), the estimated capacity reductions are as follows:
Reduction Net
MDthd MDthd
Oct 5 thru Oct 9 77 383
**Oct 10 0 460
Oct 17 thru Oct 19 25 435
For scheduling questions, please call your Scheduling Representative at
(800)238-3764.
For operational information, call Dan English (719)520-4722
For capacity information, call Vic Villalva at (719)520-4251
For press inquiries, please call Media Relations at (713) 420-6828