Notice Detail
           
Return To Results
TSP/TSP Name:  808150895-MIDCONTINENT EXPRESS PIPELINE Critical: Y
Notice Type Desc (1):  FORCE MAJEURE Notice Type Desc (2):  FORCE MAJEURE
Notice Eff Date/Time:  07/31/2020 3:56:57PM Notice End Date/Time:  08/30/2020 9:00:00am
Post Date/Time:  7/31/2020 3:56:57 PM Notice ID: 119433
Reqrd Rsp:  1 Rsp Date:  07/31/2020
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  FORCE MAJEURE - ATLANTA CS (MEP 2)
Notice Text:
AUGUST 2006 – SCHEDULED MAINTENANCE PROJECTS ON NATURAL

FORCE MAJEURE – ATLANTA COMPRESSOR STATION (MEP 2)

 

MEP has experienced mechanical issues with unit #4 at its Atlanta Compressor Station (MEP 2), located in Cass County, Texas in Zone 1 of MEP's system (MEP 2 - Segment 120).  This is a Force Majeure event that will require MEP to temporarily restrict throughput capacity eastbound on its system in Segment 120.  All deliveries downstream of the constraint in Zone 1 will be impacted, including deliveries in Zone 2.  This outage will also impact Park and Loan Services (PALS) in Zone 2, as noted below.

 

As such, effective for gas day Saturday, August 1, 2020, Evening Cycle, and anticipated to continue through gas day Tuesday, August 4, 2020, MEP will schedule Primary Firm and Secondary-in-path Firm transports to no less than 94% of contract MDQ eastbound through Segment 120 during this outage.  The actual scheduling percentage will depend on the level of nominations received during this outage.  AOR/ITS and Secondary out-of-path Firm transports will not be available.

 

In addition to the impact in Segment 120, this outage will restrict loan transactions as part of PALS in Zone 2, only.  Therefore, loan transactions will not be available for the duration of this outage in Zone 2.

 

Please contact your Account Director or Scheduling Representative if you have any questions.

..