March 23, 2017
In a notice posted July 18, 2016, Kinder Morgan notified their customers of a temporary shut in due to a natural gas release and fire at Energy Transfer Partner's King Ranch Gas Plant in Kleberg County, Texas. Kinder Morgan was able to resume service by installing a temporary pipeline above ground. At this time, Kinder Morgan is required to remove the temporary pipeline in order to install new pipeline underground. To complete the necessary work, Kinder Morgan is required to shut in the interconnect with Energy Transfer Partner's King Ranch Gas Plant, 350562.
The shut in will begin on Tuesday, April 4, 2017 and is anticipated to be complete on or around Friday, April 7th, barring unforeseen difficulties. You will be contacted by a Kinder Morgan representative regarding the progress and completion of work and resumption of full service.