Open Season Notice of Available Firm Capacity on El Paso Natural Gas Company, L.L.C. (EPNG): Topock Open Season
Bid Deadline – 2:00 PM Mountain Time, June 20, 2018
Portable Document Format (.pdf) file of Open Season: https://pipeline2.kindermorgan.com/PortalWeb/PortalDocs.aspx?code=EPNG&parent=1600
EPNG is conducting a binding Open Season for existing available capacity as outlined below:
Rate Schedule:
FT-1
Volume / TCD:
50,000 Dth/day
Primary Receipt Point(s):
EPNG Blanco Pool 300714
Note: Shippers are encouraged to contact their customer service representatives or the individuals listed below to confirm the availability of capacity at specific points.
Primary Delivery Point(s):
DPG&ETOP 314604 up to 50,000 dth/day
Alternate Rec/Del:
The capacity offered in this Open Season will include the right to utilize the following points on an alternate basis at the same contracted rate:
Alternate Receipt Locations: All receipt points within EPNG's San Juan, Anadarko and Permian Production Areas (STML SJN PIN 302347; STML PER PIN 302346; and STML ANA PIN 302344)
Alternate Delivery Locations:
DPG&ETOP 314604
DSCALTOP 332503
SOCWR 332531
KRAMER 332554
IGRIFFTH 320614
INGPLMOR 314350
INNDUMAS 305421
IBIGBLUE 301360
IWESTARW 302075
IOASISWA 301701
ILONEWA 301621
IVALEROW 301945
IKEYSTOR 301595
IMCHRNCH 301641
LAPALOMA 302144
PASTORIA 332553
ITCOLBLA 301881
Recommended Term:
EPNG recommends that bids have a proposed term from July 1, 2018 through October 31, 2018, with no later starting date and no earlier or later ending dates. EPNG reserves the right to consider or reject any bid with other starting or ending dates or which otherwise fail to comport with the provisions of this open season.
Open Season Start:
End:
Award Notification Date:
10:00 AM MST, June 15, 2018
2:00 PM MST, June 20, 2018
10:00 AM MST, June 21, 2018
Email attached Bid Sheet to KMWestBids@KinderMorgan.com
NOTE: EPNG will rely upon the time the bid is received to determine whether the bid was timely. Bids that are received (as determined by the time stamp on the EPNG's email inbox) after the end date and time listed above will be considered invalid bids and will not be eligible for an award of capacity in this Open Season. EPNG recommends that bids be submitted well in advance of the closing time listed above to minimize the risk that any email delay could cause a bid to be excluded from consideration.
General Open Season Requirements:
Bids must include the bidding party's name, Open Season Name (EPNG Topock Open Season), quantity, term, and rate.
By submitting a bid, the bidding party certifies that:
(a) All information contained in the bid is complete and accurate.
(b) It satisfies, or will be able to satisfy, all the requirements of EPNG's FERC Gas Tariff.
(c) The person submitting the bid has full authority to bind the bidding party.
The bid rate must be presented as follows:
The reservation rate per Dth/month or stated as the maximum tariff rate.
There will be no contractual ROFR offered with this capacity.
In addition to the bid rate, each bidding party shall be subject to the applicable maximum usage rate and maximum usage surcharges, all other maximum rates, charges and surcharges, including ACA, Fuel and L&U, and any other authorized surcharges assessed under the applicable Rate Schedule of EPNG's FERC Gas Tariff as those amounts may be amended or superseded from time-to-time. This includes incremental lateral charges and any third party charges resulting from the use of capacity that EPNG may hold on other pipelines.
EPNG reserves the right to reject negotiated rate bids, bids that have rates less than the maximum recourse rate, bids stated as the dollar equivalent of the current maximum recourse rate, bids that are incomplete, contain offers of varying rates within the term, contain additional or modified terms or are inconsistent with the provisions of EPNG's FERC Gas Tariff. EPNG also reserves the right to reject bids for quantities that are not for the same quantity for the duration of the term.
EPNG notes that FERC Order No. 894, in some cases, prohibits multiple affiliates of the same entity from bidding in an Open Season for capacity in which the pipeline may allocate capacity on a pro rata basis. It appears to EPNG that the restrictions imposed by FERC Order No. 894 will be applicable in this Open Season and FERC recommends that potential bidders review and adhere to the requirements of that FERC Order.
Creditworthiness Criteria:
The successful bidder(s) must satisfy the creditworthiness requirements of EPNG's FERC Gas Tariff. Bidders that fail to satisfy such creditworthiness requirements within a reasonable time will have their capacity award withdrawn. EPNG will treat the financial statements provided by bidders as confidential.
Each successful bidder and EPNG shall enter into and execute a Transportation Service Agreement (TSA) reflecting the terms of its bid as awarded by EPNG. The TSA will be in the form contained in EPNG's FERC Gas Tariff.
Evaluation Criteria:
If EPNG receives acceptable bids for capacity in excess of the actual amount of available capacity, then EPNG will award and/or allocate the capacity in a manner that yields the highest total PV as calculated below. In determining which bid(s) yield the highest total PV, EPNG reserves the right to combine multiple bids, in whole or in part, in a manner that results in a total PV of the combined bids that exceeds the highest PV achievable by accepting one or more of the disaggregated bids. This process could result in a bidder being awarded less capacity than requested (unless such bidder elects on its bid sheet not to accept a pro rata allocation of capacity).
PV will be calculated as the sum of the present values for all of the months beginning with the first month capacity is available through the end date of the bid term.
The PV for each month will be calculated as follows:
PV = (R X Q)/((1+i) to the power of n)
Where:
R = the monthly reservation bid rate
Q = the monthly bid quantity
i = the monthly discount rate of 0.3725% (which is the annual discount rate of 4.47% divided by 12).
n = the number of months from the earliest date the capacity is available in the Open Season to the month the revenue will be received (the first month capacity is available n = 1, the second month n = 2, and so on).
Contact Information:
Questions concerning this Open Season should be directed to:
Randy Barton (719) 520-4667
Thania Delgado (719) 520-4482
Mark Iverson (719) 520-4587
Robin Janes (719) 667-7555
Tim Mang (719) 520-4373
Damon McEnaney (719) 520-4472
Steve Newell (719) 520-4341
Dan Tygret (719) 520-3765
Open Season Bid Sheet
EPNG Topock
Form of Service (e.g. FT-1):__________
Email Bid To: KMWestBids@KinderMorgan.com
Legal Name of Bidder:__________________________
Name of Requesting Party:_______________________
Title of Requesting Party:________________________
DUNS Number:________________________________
Phone:_______________________________________
B. Term of Service
Effective Start Date:___________________________________
Requested Term End Date:_____________________________
C. Transportation Contract Demand (TCD):
Will you accept a pro rata allocation of capacity if necessary Yes____ NO___
Primary Receipt Point(s)
Primary Delivery Point(s)
Flow
Path
Available Dth/day MDQ
Requested Dth/day MDQ
*The sum of the MDQs at the Primary Delivery Location(s) must equal the TCD.
D. Bid Rate (express as a monthly rate per Dth or maximum reservation rate):_____________
*By submitting a bid to EPNG, the bidding party certifies that (a) all information contained in the request is complete and accurate, (b) it satisfies, or will be able to satisfy, all the requirements of EPNG's FERC Gas Tariff, and (c) the person submitting the bid has full authority to bind the bidding party.