El Paso Natural Gas Company
Update Notice of October 2017 Maintenance
October 13, 2017
The following is the current projection of maintenance that will occur on the El Paso Natural Gas Company pipeline during the month of October. If these scheduled activities change, updated notices will be posted as soon as possible. Changes are denoted by asterisks**.
**SOUTH MAINLINE MAINTENANCE
**Guadalupe Unit mechanical repair; Oct 13 thru Oct 16
RIO VISTA
There is no planned maintenance in October to affect the estimated base capacity of 154 MDthd at Rio Vista
BONDAD MAINTENANCE
Bondad Unit 1A mechanical inspection; Oct 18
Bondad Unit 1B mechanical inspection; Oct 19
Bondad Unit 2A mechanical inspection; Oct 20
From an estimated base capacity of 726 MDthd at Bondad
Station (BONDADST), the estimated capacity reductions are as follow:
Reduction Net
MDthd MDthd
Oct 18 thru Oct 20 107 619
BONDAD MAINLINE
There is no planned maintenance in October to affect estimated base capacity of 817 MDthd on Bondad Mainline.
SAN JUAN BASIN AND SAN JUAN MAINLINE
There is no planned maintenance in October to affect the estimated base capacity of 2866 MDthd at San Juan Basin and San Juan Mainline (SJ TRI).
NORTH MAINLINE MAINTENANCE
Line 1204 pipeline remediation Navajo to Leupp; Oct 1 thru Oct 31
Line 1208 pipeline maintenance Window Rock to MLV 13; Oct 1 thru Oct 31
Navajo Unit 1C mechanical repair; Oct 1 thru Oct 31
Line 1200 pipeline remediation MLV 35 to MLV 36; Oct 1 thru Oct 22 informational only
Line 1201 pipeline remediation MLV 17 to MLV 19; Oct 2 thru Oct 16 informational only
Window Rock Unit 2A mechanical inspection; Oct 3 thru Oct 6
Seligman Unit 1C mechanical maintenance; Oct 3 thru Oct 6
Window Rock Unit 5A mechanical inspection; Oct 10 thru Oct 13
Seligman Unit 1C mechanical repair; Oct 12 thru Oct 20
Leupp Station “A” & “B” Station maintenance; Oct 16 thru Oct 20 rescheduled Oct 30 thru Nov 3
Line 1200 pipeline maintenance MLV 23 to MLV 25 1/2; Oct 16 thru Oct 20 rescheduled Oct 30 thru Nov 3
Window Rock Unit 1B mechanical inspection; Oct 17 thru Oct 20 canceled
Leupp “B”,”C” and “D” Station maintenance; Oct 24 thru Oct 27
Line 1204 pipeline maintenance; Oct 24 thru Oct 27
Window Rock Unit 6B mechanical maintenance; Oct 31 thru Nov 3 rescheduled Oct 23 thru Oct 27
From an estimated base capacity of 2134 MDthd on the North Mainline, the estimated capacity reductions are as follows:
Oct 1 thru Oct 2 146 1988
Oct 3 thru Oct 6 188 1946
Oct 7 thru Oct 9 146 1988
Oct 10 thru Oct 11 177 1957
Oct 12 thru Oct 13 183 1951
Oct 14 thru Oct 16 155 1979
Oct 17 thru Oct 20 181 1953
Oct 21 thru Oct 22 146 1988
Oct 23 171 1963
Oct 24 thru Oct 27 369 1765
Oct 28 thru Oct 29 146 1988
Oct 30 thru Nov 3 220 1914
HACKBERRY MAINTENANCE
Hackberry Unit 1A mechanical inspection; Oct 31 thru Nov 2
From an estimated base capacity of 1946 MDthd at Hackberry, the estimated capacity reductions are as follows:
Oct 31 thru Nov 2 21 1925
SAN JUAN CROSSOVER MAINTENANCE
Roswell Station Annual ESD/DOT Test; Oct 4
From an estimated base capacity of 632 MDthd on the San Juan Crossover, the estimated capacity reductions are as follows:
Oct 4 77 555
HAVASU CROSSOVER MAINTENANCE
Dutch Flats Unit 1A shutdown checks; Oct 10
Dutch Flats Unit 2A shutdown checks; Oct 12
Wenden Unit 1B mechanical repair; Oct 13 thru Oct 27
Line 1104 smart pig Franconia to Alamo Lake; Oct 14
Line 1104 smart pig Franconia to Alamo Lake; Oct 15
Dutch Flats Station Shutdown smart pig Franconia to Alamo Lake; Oct 14 thru Oct 15
Dutch Flats Station Annual Dot/ESD Test; Oct 16
From an estimated base capacity of 631 MDthd on the Havasu Crossover (HAVASU), the estimated capacity reductions are as follows:
Oct 10 22 609
Oct 11 0 631
Oct 12 11 620
Oct 13 10 621
Oct 14 thru Oct 15 256 375
Oct 16 133 498
Oct 17 thru Oct 27 10 620
PHOENIX AREA MAINTENANCE
Line 20120 smart pig VLV 0 to EOL; Oct 3 and Oct 4 informational only
EUNICE AREA MAINTENANCE
There is no planned maintenance in October affect estimated base capacity of 374 MDthd at Eunice C (EUNICE C).
KEYSTONE STATION MAINTENANCE
Keystone Unit(s) 2A, 12A, 9A mechanical repair; Oct 1 thru Oct 31
Keystone Unit 2B mechanical repair; Oct 1 thru Oct 6
Keystone Unit 2B mechanical inspection; Oct 24 thru Oct 27 canceled
From an estimated base capacity of 779 MDthd at Keystone Station
(KEYST ST) the estimated capacity reductions are as follows:
Oct 1 thru Oct 6 176 603
Oct 7 thru Oct 23 100 679
Oct 24 thru Oct 27 100 679
Oct 28 thru Oct 31 100 679
PLAINS AREA MAINTENANCE
Line 1100 pipeline remediation MLV 2 to MLV 3; Oct 23 thru Nov 3 informational only
LINE 2000 Maintenance
Black River Unit 1 mechanical inspection; Oct 4
From an estimated base capacity of 575 MDthd at L2000 (L2000), the estimated capacity reductions are as follows:
Oct 4 130 445
WINK STATION MAINTENANCE
Wink Unit 3 mechanical repair; Oct 6 thru Oct 13 extended thru Oct 20
From an estimated base capacity of 577 MDthd at WINK, the estimated capacity reductions are as follows:
Oct 6 thru Oct 9 107 470
Oct 10 thru Oct 13 107 470
Oct 14 thru Oct 20 107 470
PERMIAN AREA MAINTENANCE
Line 3146 pipeline Hydro Test Puckett to L1105; Oct 1 thru Oct 18 extended thru Oct 25 Crane CPD 1(IAROPUC) shut in during this maintenance pressures will be higher in the Permian Area. EPNG updates that the WAHA GE posted Capacity 280 MDthd (Reference Force Majeure Notice Update #17478) will be reduced to 246 Mdthd during this maintenance. Deliveries at WAHA will be dependent upon pipeline pressures affected by the Line 3146 Hydro Test.
Line 3105/3104 maintenance pig; Oct 27 pressures will be higher at launch at Pegasus Plant (IMOBILPE)
Line 3125 to Line 3104 pipeline remediation; Oct 30 thru Nov 19
Informational only
From an estimated base capacity of 139 MDthd at CRANSOU, the estimated capacity reductions are as follow:
Oct 1 thru Oct 18 139 0
Oct 19 thru Oct 25 139 0
SOUTH MAINLINE MAINTENANCE
Oracle Unit 1 mechanical repair; Oct 1 thru Oct 13 extended thru Oct 20
Florida Unit 1B mechanical inspection; Oct 2 thru Oct 6 rescheduled Oct 4 thru Oct 6
Pecos Unit 1A mechanical repair; Oct 1 thru Oct 20 extended thru Oct 31
San Simon Unit 1 mechanical repair; Oct 1 thru Oct 14 extended thru Oct 31
Line 1100 Afton to MLV 32 pipeline remediation; Oct 1 thru Oct 15 completed early
Pecos Unit 3A mechanical inspection; Oct 24 thru Oct 26 postponed
El Paso 4D mechanical inspection; Oct 3
Casa Grande Unit 1C mechanical inspection; Oct 10 rescheduled Oct 11
Pecos Unit 2A mechanical maintenance; Oct 31 postponed
Guadalupe Station Annual DOT/ESD Test; Oct 10 thru Oct 12
Afton Unit 3 mechanical repair; Oct 12 thru Oct 31
Cimarron Unit 1 mechanical maintenance; Oct 16 postponed
Lorsdburg Unit 1C mechanical inspection; Oct 17
Florida Unit 1C mechanical inspection; Oct 19
Line 1100 Hydro test Lordsburg to MLV 43; Oct 23 thru Nov 11
Cornudas Unit 1C mechanical inspection; Oct 24
Line 2000 pipeline remediation Tom Mix to Casa Grande; Oct 30 thru Nov 11 informational only
Lordsburg Unit 1B mechanical inspection; Oct 31 thru Nov 22
From an estimated base capacity of 1229 MDthd at Pecos (PECOS), the estimated capacity reductions are as follows:
Oct 1 thru Oct 2 68 1161
Oct 3 thru Oct 5 68 1161
Oct 6 thru Oct 9 68 1161
Oct 10 thru Oct 12 273 956
**Oct 13 thru Oct 16 273 956
Oct 17 thru Oct 20 68 1161
Oct 21 thru Oct 31 68 1161
From an estimated base capacity of 1746 MDthd at Cornudas LPW, the estimated capacity reductions are as follows:
Oct 3 74 1672
Oct 19 87 1659
Oct 24 34 1712
From an estimated base capacity of 598 MDthd at Cornudas HPW
(CORN HPW), the estimated capacity reductions are as follows:
Oct 2 thru Oct 3 0 598
Oct 4 thru Oct 6 48 550
Oct 25 thru Oct 26 0 598
From an estimated base capacity of 1334 MDthd at Lordsburg (LORDSBRG), the estimated capacity reductions are as follows:
Oct 16 88 1246
Oct 17 88 1246
Oct 23 thru Oct 31 22 1312
From an estimated base capacity of 592 MDthd at LORDS B, the estimated capacity reductions are as follows:
Oct 31 48 544
From an estimated base capacity of 588 MDthd at Oracle, the estimated capacity reductions are as follows:
Oct 1 thru Oct 2 31 557
Oct 3 thru Oct 13 31 557
Oct 14 thru Oct 20 31 557
From an estimated base capacity of 1371 MDthd at Afton, the estimated capacity reductions are as follows:
Oct 1 thru Oct 12 25 1346
Oct 13 thru Oct 31 31 1340
From an estimated base capacity of 876 MDthd at Vail, the estimated capacity reductions are as follows:
Oct 1 thru Oct 14 21 855
Oct 15 thru Oct 31 21 855
From an estimated base capacity of 810 MDthd at Casa Grande LP West (CASAG LP), the estimated capacity reductions are as follows:
Oct 10 0 810
Oct 11 93 717
For scheduling questions, please call your Scheduling Representative at
(800)238-3764.
For operational information, call Dan English (719)520-4722
For capacity information, call Vic Villalva at (719)520-4251
For press inquiries, please call Media Relations at (713) 420-6828