Revision:
KANDA WEST (Segment 106): 5A 22" Wyoming mainline, CIG revises performing pipeline remediation from August 3 through August 7 to August 4 through August 5.
Wyoming:
1. KANDA WEST (Segment 106): 5A 22" Wyoming mainline, CIG will be performing pipeline remediation August 4 through August 5. Volumes will have to net to zero. There will be no impact to Kanda Meter Station (PIN 800335).
Colorado Interstate Gas Company
Operations Planning Report for August 2020
Issued July 21, 2020
ReIssued July 28, 2020
COLORADO INTERSTATE GAS COMPANY MAINTENANCE
Colorado: None of the planned maintenance is expected to impact service
Utah: None of the planned maintenance is expected to impact service
Kansas: None of the planned maintenance is expected to impact service
South of Springfield, CO (including Texas and Oklahoma):
None of the planned maintenance is expected to impact service
CIG Storage Guidelines
Storage inventory is projected to be within normal guidelines on August 1.
Field
Max Inject MMcf/d
Max. Withdraw MMcf/d
Boehm
65,000
124,000
Flank
50,000
164,000
Ft. Morgan
110,000
450,000
Latigo
70,000
139,000
Totals
295,000
877,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on August 1, 2020. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1064 Btu/cf.
CIG Services Utilizing Young Gas Storage Company
No Planning Meeting Scheduled
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Bill McMillan at (719)520-4389.
Any comments or questions about this report should be directed to Glen Petty (719) 520-4704 or Bill McMillan (719) 520-4389.