Colorado Interstate Gas Company
Operations Planning Report for June 2020
Issued May 18, 2020
COLORADO INTERSTATE GAS COMPANY MAINTENANCE
Wyoming:
1. OREGON BASIN (Segment 144): Oregon Basin Compressor Station, CIG will be performing Station ESD test on June 2. Volumes will have to net to zero during this outage.
Operating Capacity
Capacity Reduction
Limit MDth/d
June 2 Cycles 1 thru 3
21
0
June 2 Cycles 4 thru 5
13**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
2. FLYING HAWK TO HI PLAINS VLV5 (Segment 178): WIC Cheyenne Compressor Station, WIC will be performing unit shutdown checks one unit on June 9,16,17 and 18 and Station ESD Test June 10. This outage results in the following impacts.
June 9 Cycles 1 thru 3
885
850
June 9 Cycles 4 thru 5
872**
June 10 Cycles 1 thru 4
663
June 10 Cycle 5
765**
June 16 Cycles 1 thru 3
June 16 Cycles 4 thru 5
June 17 Cycles 1 thru 3
June 17 Cycles 4 thru 5
June 18 Cycles 1 thru 3
June 18 Cycles 4 thru 5
Colorado:
3. GREASEWOOD CS CO/WY STATE LINE (Segment 124): Greasewood Compressor Station, CIG will be performing Station ESD Test June 9 and unit shut down checks June 10. This outage results in the following impact.
June 9
173
90
128**
Utah: None of the planned maintenance is expected to impact service
Kansas: None of the planned maintenance is expected to impact service
South of Springfield, CO (including Texas and Oklahoma):
None of the planned maintenance is expected to impact service
CIG Storage Guidelines
Storage inventory is projected to be within normal guidelines on June 1.
Field
Max Inject MMcf/d
Max. Withdraw MMcf/d
Boehm
65,000
70,000
Flank
60,000
140,000
Ft. Morgan
13,000
400,000
Latigo
85,000
100,000
Totals
340,000
710,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on June 1, 2020. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1064 Btu/cf.
CIG Services Utilizing Young Gas Storage Company
Young Gas Storage Company (Young) will be conducting scheduled reservoir maintenance starting on June 2, 2020 and continuing through June 9, 2020. Please refer to Notice(s) #119296 for additional information about the injection limitations based on the expected work schedule.
No Planning Meeting Scheduled
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Bill McMillan at (719)520-4389.
Any comments or questions about this report should be directed to Glen Petty (719) 520-4704 or Bill McMillan (719) 520-4389.