Subject:  Operations Planning Report August 2019
Notice Text:

Colorado Interstate Gas Company

Operations Planning Report for August 2019

Issued July 19, 2019

COLORADO INTERSTATE GAS COMPANY MAINTENANCE

Wyoming:

1. KANDA WEST (Segment 106): 5A 22" Wyoming mainline, CIG will be performing pipeline remediation August 6 through August 8. Volumes will have to net to zero. There will be no impact to Kanda Meter Station (PIN 800335).

Colorado: None of the planned maintenance is expected to impact service

Utah: None of the planned maintenance is expected to impact service

Kansas: None of the planned maintenance is expected to impact service

South of Springfield, CO (including Texas and Oklahoma):

None of the planned maintenance is expected to impact service

CIG Storage Guidelines

Storage inventory is projected to be within normal guidelines on August 1.

Field          Max Inject., MMcf/d       Max. Withdraw MMcf/d
Boehm               65,000                     124,000
Flank                 50,000                      164,000
Ft. Morgan         110,000                    450,000
Latigo                70,000                      139,000
Totals                295,000                    877,000

Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on August 1, 2019. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1064 Btu/cf.

CIG Services Utilizing Young Gas Storage Company

None of the planned maintenance is expected to impact service

No Planning Meeting Scheduled

No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Bill McMillan at (719)520-4389.

Any comments or questions about this report should be directed to Glen Petty (719) 520-4704 or Bill McMillan (719) 520-4389.

 

..