REVISION:
South of Springfield, CO (including Texas and Oklahoma):
Beaver Meter Station (800078): Mechanical Maintenance Start Date updated June 11 thru July 5
9. Beaver Meter Station (800078): Will be at a reduced capacity limit June 11 through July 5 to during the unit mechanical maintenance at Beaver Compressor Station. This outage will result in the following impact.
Operating Capacity
Capacity Reduction
Limit MDth/d
June 11 through July 5
227
100
Colorado Interstate Gas Company
Operations Planning Report for June 2019
Issued May 20, 2019
ReIssued May 21, 2019
COLORADO INTERSTATE GAS COMPANY MAINTENANCE
Wyoming:
1. OREGON BASIN (Segment 144): Oregon Basin Compressor Station, CIG will be performing Station ESD test on June 4. Volumes will have to net to zero during this outage.
June 4 Cycles 1 thru 3
21
0
June 4 Cycles 4 thru 5
13**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
2. BRIDGER CREEK TO LOST CABIN (Segment 150): Lost Cabin Compressor Station, CIG will be performing Station ESD Test June 4 and unit shut down checks one at at time June 5 through June 7. This outage results in the following impact.
Northbound
June 4 Cycles 1 thru 4
90
81
June 4 Cycle 5
85**
June 5 Cycles 1 thru 4
83
June 5 Cycle 5
86**
June 6 Cycles 1 thru 4
June 6 Cycle 5
June 7 Cycles 1 thru 4
June 7 Cycle 5
Southbound
127
102
113**
3. ECHO SPRINGS TO RAWLINS CS (Segment 132): Rawlins Compressor Station, CIG will be performing Station ESD Test June 5. This outage results in the following impact.
664
535
594**
4. ALKALI POND (SEGMENT 103): 180A - 6" CIG will be performing pigging operations Opal Lateral to Alkali Pond Meter Station June 11. This outage results in the following impact.
June 11 Cycles 1 thru 4
25
7
June 11 Cycle 5
15**
5. FLYING HAWK TO HI PLAINS VLV5 (Segment 178): WIC Cheyenne Compressor Station, WIC will be performing unit shutdown checks one unit on June 11,18,19 and 20 and Station ESD Test June 12. This outage results in the following impacts.
June 11 Cycles 1 thru 3
885
850
June 11 Cycles 4 thru 5
872**
June 12 Cycles 1 thru 4
663
June 12 Cycle 5
765**
June 18 Cycles 1 thru 3
June 18 Cycles 4 thru 5
June 19 Cycles 1 thru 3
June 19 Cycles 4 thru 5
June 20 Cycles 1 thru 3
June 20 Cycles 4 thru 5
6. GREEN RIVER TO CHROME DOME (Segment 106): 5A 22" Wyoming mainline, CIG will be performing pipeline remediation June 11 through June 13. Volumes at Segment 106 will have to net to zero. There will be no impact to Kanda Meter Station (PIN 800335).
Colorado:
7.GREASEWOOD CS CO/WY STATE LINE (Segment 124): Greasewood Compressor Station, CIG will be performing Station ESD Test and unit shut down checks June 11 through 12. This outage results in the following impact.
June 11
195
120
154**
Utah: None of the planned maintenance is expected to impact service
Kansas: None of the planned maintenance is expected to impact service
8. BAKER MS TO BEAVER CS (Segment 288): Beaver Compressor Station one unit will be out of service June 11 through July 5 to perform mechanical maintenance. This outage will result in the following impact.
305
245
CIG Storage Guidelines
Storage inventory is projected to be within normal guidelines on June 1.
Field Max Inject., MMcf/d Max. Withdraw MMcf/d Boehm 65,000 70,000 Flank 60,000 140,000 Ft. Morgan 130,000 400,000 Latigo 85,000 100,000 Totals 340,000 710,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on June 1, 2019. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1064 Btu/cf.
CIG Services Utilizing Young Gas Storage Company
Young Gas Storage Company (Young) will be conducting scheduled reservoir maintenance starting on June 4, 2019 and continuing through June 11, 2019. Please refer to Notice(s) #118715 for additional information about the injection limitations based on the expected work schedule.
No Planning Meeting Scheduled
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Bill McMillan at (719)520-4389.
For scheduling questions, please contact the Nominations and Scheduling hotline at 1-800-238-3764 option 2.
For operational issues or concerns, contact Glen Petty at (719) 520-4704 or Bill McMillan at (719) 520-4389.