Issued May 18, 2016
Wyoming:
1. Oregon Basin (Segment 144): Oregon Basin Compressor Station Annual DOT ESD systems checks will be performed on June 1. Volumes will have to net to zero during this outage.
Design Capacity Capacity Reduction
Limit (MDth/d) Limit (MDth/d)
June 1 Cycles 1 thru 3 21 0
June 1 Cycles 4 thru 5 21 13**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
2. ECHO SPRINGS TO RAWLINS CS (Segment 132): Rawlins Compressor Station will be out of service June 7 to perform annual DOT ESD system checks. This outage will results in the following impact.
June 7 Cycles 1 thru 4 664 558
June 7 Cycle 5 664 607**
3. KING CS TO EMERALD SPRINGS (Segment 100): King Compressor Station CIG will perform Annual DOT/ESD test June 14. This outage results in the following impact.
June 14 Cycles 1 thru 3 153 0
June 14 Cycles 4 thru 5 153 96**
4. LARMIE CS to WY/CO ST LINE (Segment 162): Laramie Compressor Station One unit at a time will be down June 21, 22, 23 and 24 to perform unit safety shutdown checks. The outages will result in the following impacts.
June 21 Cycles 1 thru 4 629 540
June 21 Cycle 5 629 581**
June 22 Cycles 1 thru 4 629 540
June 22 Cycle 5 629 581**
June 23 Cycles 1 thru 4 629 540
June 23 Cycle 5 629 581**
June 24 Cycles 1 thru 4 629 540
June 24 Cycle 5 629 581**
Colorado:
5. NIOBRARA PIN 965742: Niobrara Compressor Station The station will be out of service June 7 through June 8 to perform ESD, unit shutdown checks and unit mechanical maintenance. The volume will go to zero during this outage.
Utah: None of the planned maintenance is expected to impact service.
Kansas: None of the planned maintenance is expected to impact service.
South of Springfield, CO (including Texas and Oklahoma):
None of the planned maintenance is expected to impact service.
Storage inventory is projected to be within normal guidelines on June 1.
Field Max Injection MMcf/d Max Withdrawal MMcf/d
Boehm 65,000 70,000
Flank 60,000 140,000
Ft. Morgan 130,000 400,000
Latigo 85,000 100,000
Totals 340,000 710,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on June 1, 2016. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities were determined based upon an average of 1064 Btu/cf.
Young Gas Storage Company (Young) will be conducting scheduled reservoir maintenance beginning on June 7 through June 14. Please refer to Notice(s) #115844 for additional information about the injection limitations based on the expected work schedule.
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 4.11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Bill McMillan at (719)520-4389.
Any comments or questions about this report should be directed to Glen Petty (719)520-4704 or Bill McMillan (719)520-4389