Issued April 19, 2015
Wyoming:
1. QPC/CIG (KAN) Kanda Sweetwater (800335): 5BX – 20” Crossover, CIG will be performing pipeline remediation May 2 through May 6. This outage results in the following impact:
Design Capacity Capacity Reduction
Limit (MDth/d) Limit (MDth/d)
May 2 thru May 6 128 0
2. Table Rock Master Meter TAB (895008): 44B-12" Table Rock Loop, On May 9 through May 20 CIG will be performing pipeline remediation. This outage results in the following impacts:
May 9 thru May 20 61 0
3. KING CS TO EMERALD SPRINGS (Segment 100): King Compressor Station CIG will perform Annual DOT/ESD test May 17. This outage results in the following impact:
May 17 Cycles 1 thru 4 153 0
May 17 Cycle 5 153 70**
** The nomination limit for this cycle has been prorated for the remaining time in the gas day.
4. BRIDGER CREEK TO LOST CABIN (Segment 150): Lost Cabin Compressor Station CIG will be performing Annual DOT ESD systems checks May 10 and unit shutdown checks May 11 and May 12. These outages will result in the following impacts:
May 10 Cycles 1 thru 4 118 104
May 10 Cycle 5 118 110**
May 11 Cycles 1 thru 4 118 112
May 11 Cycle 5 118 115**
May 12 Cycles 1 thru 4 118 112
May 12 Cycle 5 118 115**
**The nomination limit for this cycle has been prorated for the remaining time in the gas day.
Colorado: None of the planned maintenance is expected to impact service.
Utah: None of the planned maintenance is expected to impact service.
Kansas: None of the planned maintenance is expected to impact service.
South of Springfield, CO (including Texas and Oklahoma):
5. Baker MS TO Beaver CS (Segment 288): Beaver Compressor Station one unit will be out of service May 24 through May 27 to perform mechanical inspection. This outage will result in the following impact:
May 24 through May 27 305 242
Storage inventory is projected to be within normal guidelines on May 1.
Field Max Injection MMcf/d Max Withdrawal MMcf/d
Boehm 65,000 70,000
Flank 55,000 110,000
Ft. Morgan 125,000 250,000
Latigo 80,000 70,000
Totals 325,000 500,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on May 1, 2016. Departure from these projections can affect injection and withdrawal capabilities. To determine thermal quantities use 1064 Btu/cf.
Addionally Field maintenance is scheduled during May for each of the storage reservoirs. Please refer to Notice #115710 for additional information about the injection limitations based on the expected work schedule.
Additionally, field maintenance is scheduled during May for Totem storage reservoir. Please refer to Notice #115801 for additional information about the injection limitations based on the expected work schedule.
None of the planned maintenance is expected to impact service.
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 4.11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Bill McMillan at (719)520-4389.
Any comments or questions about this report should be directed to Glen Petty (719)520-4704 or Bill McMillan (719)520-4389