Issued January 19, 2016
Wyoming: None of the planned maintenance is expected to impact service.
Colorado:
1. NIOBRARA LAT (Segment 259): Niobrara Compressor Station, The station will be out of service February 15 through February 19 to perform Station and Unit maintenance. The volume will go to zero during this outage.
Utah: None of the planned maintenance is expected to impact service.
Kansas: None of the planned maintenance is expected to impact service.
South of Springfield, CO (including Texas and Oklahoma):
2. RGNCYFS/CIG (MOC)MOCANE BEAVER (PIN 895002): Mocane Compressor Station, One unit will be out of service February 2 through March 18 for mechanical maintenance.. This outage results in the following impact.
Design Capacity Capacity Reduction
Limit (MDth/d) Limit (MDth/d)
February 2 thru 25 35 18
February 26 thru March 18 35 24
Storage inventory is projected to be within normal guidelines on February 1.
Field Max Inject., MMcf/d Max. Withdraw MMcf/d
Boehm 65,000 124,000
Flank 55,000 164,000
Ft. Morgan 115,000 450,000
Latigo 65,000 139,000
Totals 300,000 877,000
Note to storage table: Maximum injection and withdrawal figures are based upon projections for gas-in-place on February 1, 2016. Departure from these projections can affect injection and withdrawal capabilities. Thermal quantities related to storage field transactions are determined based upon an average of 1064 Btu/cf.
None of the planned maintenance is expected to impact service.
No requests for a Joint Monthly Operating Plan Meeting have been received by CIG. Therefore, pursuant to Section 11.1 of General Terms and Conditions of the FERC Gas Tariff, no such meetings have been scheduled. If at any time there are any questions regarding operational issues, do not hesitate to call Bill McMillan at (719)520-4389.
Any comments or questions about this report should be directed to Glen Petty (719)520-4704 or Bill McMillan (719)520-4389